Cutting crime: the case for justice reinvestment - Justice Committee Contents


Third supplementary memorandum submitted by the Ministry of Justice

AVAILABILITY OF DIFFERENT REQUIREMENTS FOR COMMUNITY ORDERS

  We do not have an absolutely clear picture at present, but the recent National Audit Office report on Community Orders found that some community order requirements such as Alcohol and Mental Health treatments were "not available or rarely used in some of the 42 Probation Areas".

The actual use of requirements as detailed in their report can be found in the attached Appendix.

There are two main reasons for these restrictions:

  1.  The Health Service is responsible for delivering some of the requirements, such as Alcohol and Mental Health Treatment, but services have not been established in many areas at present. NOMS is in negotiation with Health to improve the level of service. NOMS has also provided additional resources to probation areas, to support the delivery of alcohol treatment in particular and will make available an accredited programme on alcohol treatment later this year.

  2.  Probation workloads have increased over the past 12 months and some areas have taken decisions to restrict delivery of some requirements for a temporary period in order to manage resources effectively. The details of those restrictions are outlined in Appendix B (not printed). To address this problem NOMS has made available an additional £40 million of funding for 2008-09.

  The £40 million investment has been targeted at facilitating the use of community orders rather than short prison sentences, where deemed appropriate by the sentencing court. It is supported by a national action plan which addresses a range of issues, including seeking increases in the availability of requirements for offenders subject to community orders, which in turn is designed to improve the confidence that sentencers can have in the Probation Service provision and delivery and in community sentences.

  Under the auspices of the national action plan, there will also be a major mapping exercise to establish the involvement of the Probation Service in partnerships with other organisations. The project will examine the effectiveness of this involvement and the potential for development with a particular emphasis on accommodation and alcohol provision.

  Probation Areas are involved in a wide range of partnerships, some statutory, some closely linked to direct service delivery through commissioning arrangements and some that have evolved to facilitate co-ordinated working between agencies. Effective partnership working is essential to ensure that offenders are able to access, in a timely manner, appropriate services in respect of housing, housing related support, drug and alcohol treatment, employment, health, debt, etc.

  The additional funding and the mapping exercise will enable us to have a much more accurate picture of the availability of requirements at the end of the 2008-09 and we also expect the availability of provision to have increased.

INTEGRATED PROSECUTION TEAM FUNDING

  The London CJS Reform Programme is a significant programme of change designed to deliver an efficient and effective criminal justice service (CJS) that everyone has confidence in. Key to this is ensuring greater joint working between CJS agencies in London, and evidence that this is happening is visible at many levels, from strategy development to resource-sharing. The Integrated Prosecution Team (IPT) project is a key example of how agencies are collaborating to deliver a new, highly integrated prosecution process.

The aim of the Integrated Prosecution Team (IPT) project is to reduce duplication and stream line the administrative prosecution process. The police (MPS and City) will focus on pre-trial and case build work with the CPS taking over the administrative function post charge, the use of a single file is key to the new process. Borough prosecution teams (CPS and police) will be co-located at police stations with some CPS staff being based at court centres.

  The MPS and CPS are taking a holistic approach to the funding for this project, driven by the need to support the transition to the new process and the realignment of responsibilities between the two agencies. The approach takes account of where the benefits fall, particularly in terms of staffing and lease agreements. For example, the MPS is funding two CPS administrative posts for each IPT for the first six months after they each Go Live as the CPS will have to deal with outstanding MPS and CPS actions on existing case files.

  A joint economic case is being developed which will confirm the projected costs and savings for IPT as a whole. This will be an integrated assessment of CPS and MPS savings, net of delivery costs.

EVIDENCE ON EFFICIENCY SAVINGS ASSOCIATED WITH LARGER (TITAN) PRISONS

  The Carter Team reviewed the unit costs of various size prisons: 1,000 places, 1,500 places, 2,000 places and up to 2,500 places (the titan model). As you might expect there is a fixed cost of "opening the shop" in any prison and economies of scale determine that unit costs diminish as size increases. The Carter team commissioned detailed staff profiling at different size prisons to determine the level of resources required and also consulted a number of private prison providers. The Carter Team also held a workshop on the operational challenges of Titan prisons with Prison Service Area Managers and selected Prison Governors. This helped shape the staff requirements and ultimately the anticipated operating costs. This detailed evidence gathering demonstrated that "Titan" sized prisons were between 20 to 25% less expensive to operate than the existing core prison estate.

The Carter Team also undertook analysis of the construction costs of new prisons and gained detailed costings from a number of major prison building firms. This was also supported by the internal NOMS analysis of construction costs. Again, considerable savings were identified by building Titan sized prisons, relative to building medium size prisons.

  Using the above evidence the Titan Business Case was developed by an exceptional management accountant with experience of developing and appraising the business case for billion pound construction programmes. This evidence and analysis produced by the independent Lord Carter Review was then peer reviewed by HM Treasury officials, Prime Minister's Delivery Unit and Ministry of Justice officials.

  As you will be aware, since Lord Carter published his report the Ministry of Justice has been closely looking at the prospect of taking forward the Titan proposal, has undertaken site searches to identify suitable locations and launched the public consultation exercise. This information will be fed into further developing and appraising the Titan business case and will provide a firmer fix on the costs, benefits and opportunities of alternative measures. As this work is in progress, detailed information is not currently available.

MORE DETAIL ON ANNOUNCED £1.2 BILLION FUNDING

  The £1.2 billion additional funding announced following the Carter report is for the CSR07 period. It does not include funds related to Titans. HMT have exceptionally agreed a provisional capital allocation for 2011-12 (in the next SR period) of £230 million which includes funding for land acquisition for Titan prisons.

The £1.2 billion Carter funding is additional funding, not a loan, so it does not have to be repaid to the Treasury. HMT is unlikely to allow spending on other purposes.

  Any change in utilisation of the funding would have to be agreed with the Treasury.

Rt Hon Jack Straw MP

July 2008



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 14 January 2010