3 Responding to the sudden economic
change
12. The widespread pit closures began in 1981
but the Government did not establish the Coalfields Task Force
until 1997.[39] During
this time, many people of working age in the coalfield communities
withdrew from the labour market and moved onto incapacity benefits.[40]
Although there had been various European initiatives aimed at
physical development and inward investment in these areas, by
the late 1990s the coalfields as a whole still had a substantial
job deficit.[41] The
Department told the Committee it was likely that the time between
the height of the redundancies and the start of the initiatives
contributed significantly to the increase in incapacity benefits
claimants and worklessness.[42]
13. The Department apologised for the time taken
to develop the Coalfields Enterprise Fund.[43]
The Coalfield Task Force report recommended in 1998 that the Department
should establish a Coalfield Enterprise Fund of an initial £50
million with an aspiration to increase the fund further. It took
five years for the Government to establish the Fund with an initial
budget of £10 million and it has so far invested only £20
million of public funds.[44]
14. The main purpose of the coalfield initiatives
was to bring land back into productive use to create jobs.[45]
Ministers chose to spend the largest proportion of funding on
regeneration of physical sites.[46]
The Department set target outputs from land reclamation without
sufficient assessment of each site's potential and had to include
more sites in the Programme to meet the jobs target.[47]
Although each site had project milestones, the Department did
not set interim milestones or targets at a Programme level against
which to monitor progress.[48]
Investment for site developments depended in part on receipts
from private investors which have decreased in the economic downturn.[49]
As a result the Department is not confident that it will achieve
its targets by 2017.[50]
15. The Department has not routinely monitored
the occupancy rates on the developments it has created.[51]
The occupancy rate on two sites that have been completed since
November 2007 is below 20%,[52]
and the capacity of coalfield areas to make the most of employment
opportunities on new site developments depends on the pace of
the economic recovery.[53]
The initial allocation for the balance of spending between the
physical regeneration on sites, support for training and skills
development was not based on a robust evaluation and may no longer
be valid.[54] The Department
said that it reviewed the balance of need over the three initiatives
annually up to 2007 and considered the shape of the funding going
forward.[55] The Department
has considered on a site-by-site basis if development of jobs
off the site was a more appropriate and cost effective way to
regenerate the local community, but it said the economic downturn
may require a different approach.[56]
39 C&AG's Report, paras 1.1 and 1.3 Back
40
Q 53 Back
41
Q 97; Ev 14 Back
42
Q 53 Back
43
Qq 88 and 94 Back
44
Qq 67-76; C&AG's Report, paras 3.10 and 3.16 Back
45
Q 59 Back
46
Q 60 Back
47
Qq 10 and 64 Back
48
Qq 9 and 10 Back
49
Q 52 Back
50
Q 12 Back
51
Q 55 Back
52
C&AG's Report, para 4.5 Back
53
Q 12 Back
54
Q 72 Back
55
Q 67 Back
56
Q 93 Back
|