Ministry of Defence: Major Projects Report 2009 - Public Accounts Committee Contents


2 Improving the Department's skills in cost estimation

6.  Although the Department and Treasury have recently worked to improve cost estimating by agreeing a rolling 10-year planning horizon, pressure on the Equipment Plan is significantly affected by wider defence budget pressures.[20] These include: Armed Forces' pay, pensions, receipts from Defence Estates, adverse movements in foreign exchange, and pressure to shift funds to support current operations.[21] For example, the Department noted that successive Armed Forces' pay reviews had recommended pay rises that exceeded the level of inflation built into the Comprehensive Spending Review settlement, adding 'several hundred million' in costs per year over the past three years.[22] Foreign exchange movements had added a further £1.3 billion over four years.[23]

7.  To find the money to cover these cost increases, the Department has deliberately delayed equipment projects to generate short-term savings, even though such delays invariably result in poor value for money.[24] Longer term, given the wider economic position, the funding provided for defence as a whole, including the slice allocated for equipment acquisition, will undoubtedly be under considerable pressure. The Department told us it would model the implications of a range of budget settlements over a 10-year horizon so that future decisions were carefully planned, rather than the knee-jerk reactions of late.[25]

8.  Critically, the Department does not have any contingency funding in place within its budget to address either external pressures or cost growth from within the Equipment Plan. Currently, projects are budgeted on the 'most likely' cost (the expected cost of the project) and not their 'not to exceed cost' (the highest cost estimate approved). A recent report showed average project costs of 40% more than their 'not to exceed' cost by the time they are completed, putting the overall affordability of the Equipment Plan at risk.[26]

9.  The Department acknowledged that its historic over-optimism on project costs has contributed to cost growth. This trend has been so marked that, of the projects in this year's Major Projects Report, the total cost over-run is in excess of £4.5 billion—an average of over £300 million per project. A dedicated cost estimation team is being established to support all acquisition work, and it is critical that its work is both independent and authoritative.[27]


20   Qq 16 and 59 Back

21   Qq 1-2 and 36; C&AG's Report, para 7 Back

22   Qq 1, 13 and 14 Back

23   Qq 2 and 25 Back

24   Qq 1 and 104-106 Back

25   Q 6 Back

26   Review of Acquisition for the Secretary of State for Defence: An independent report by Bernard Gray, October 2009, page 7 Back

27   Qq 116 and 121-124 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 23 March 2010