The Decent Homes Programme - Public Accounts Committee Contents


Conclusions and recommendations


1.  There has been substantial progress towards the objective that all social housing should be of a decent standard by December 2010. Over a million homes have been improved since 2001 and there have been wider benefits such as more tenant involvement in housing decisions and jobs created in deprived areas. However, some elements of the Department's financial control were weak and the Department did not exercise sufficient oversight of the Decent Homes Programme's devolved delivery. Our recommendations reflect the need for the Department to get a stronger grip of these issues in future.

2.  An estimated 305,000 social sector homes will still be non-decent at December 2010, and work on these will not be completed until 2018-19. Although the Department has stated its commitment to fund the remainder of the Programme, there is a risk that such funding will not be forthcoming, given likely pressures on future public spending. The Department should prepare a contingency plan for the Programme's completion, with options and priorities clearly identified should funding not be available.

3.  If the Decent Homes Programme is to achieve value for money in the long term, local authorities need clear plans in place to prevent the build up of another maintenance backlog. The Department intends that each local authority will fund maintenance themselves in future. The Department will be announcing details of its proposals imminently, and it is vital that it then acts quickly to finalise the new funding arrangements with individual local authorities, based on reliable assessments of likely costs and revenues.

4.  It is unsatisfactory that the Department did not identify the likely cost of the Decent Homes Programme to the social housing sector at its start. The £19 billion estimate it did prepare was not 'fit for purpose' as it omitted the cost of improving housing that would fall below standard as the Programme progressed, the cost of inflation and the costs to Registered Social Landlords. The Department should, for future programmes, provide more robust estimates of the likely costs before starting.

5.  It is not clear how much the Department has given to the social housing sector to fund the Programme. Decent Homes funding streams and costs are not separately identified from other money spent on housing and the Department can only estimate how much has been used on Decent Homes. In future, when setting up major programmes, the Department should first be clear on what costs it is letting itself in for, and then put in place arrangements that enable the costs it then incurs to be accurately identified.

6.  Arms Length Management Organisations (ALMOs) have spent more on improvements per property than local authorities that retained their stock. The Department has not gone back to examine whether ALMOs were provided with more funding than was necessary. The Department and the Homes and Communities Agency should go back to those ALMOs that have completed their work to identify why they spent more per property and assess whether any future funding needs to be reduced.

7.  The Department has done little to compare unit costs of different approaches to carrying out work to improve the standard of homes or to share this information with landlords. The Department should, as part of its current evaluation of the Decent Homes programme, identify the most cost effective approaches and then disseminate good practice.

8.  It is unacceptable that the Department lacks basic information, such as the total number of homes made decent. The Department should, in the first instance, make sure that information on monitoring returns is accurate, and that the numbers of homes made decent can be separately identified from those where tenants refuse work or where homes are scheduled for demolition. For future programmes, it should ensure that it builds in adequate arrangements for the collection of robust monitoring data from the very start.

9.  The Department has only provided extra funding for Decent Homes to those local authorities which have set up ALMOs, used the Private Finance Initiative or transferred their housing stock. Local authorities that wished to retain day-to-day management of the housing stock had to fund improvements from their own resources. As part of its current evaluation of the Decent Homes programme, the Department should examine whether the policy decision not to provide additional funding to some local authorities has had a negative impact on value for money, for example, if lack of funding led to cheap materials being used that consequently needed to be replaced earlier.

10.  The Department has very little information on whether the funds provided for improving private sector homes have been spent well. It does not separately track this spending and has done little to monitor individual local authority performance. The Department should assess the impact of the funding it provides through local authorities, in order to identify and disseminate good practice.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 17 March 2010