The Decent Homes Programme - Public Accounts Committee Contents


3  Improving monitoring and evaluation

13. At the start of the Programme the Department did not calculate an estimate of the total cost to local authorities and Registered Social Landlords of making all their homes decent. While it did produce an estimate of £19 billion using data from the English House Condition Survey, this covered local authority housing only. According to the Department, the estimate did not cover Registered Social Landlords as the extent of non-decency in their housing stock was much less and they were more able to tackle the problem using their own resources. In contrast, the condition of local authority housing was much worse and would require government assistance.[24]

14. According to the Department's latest figures, local authorities and Registered Social Landlords will spend over £37 billion making their housing decent (Figure 1), with local authorities spending an estimated £29.3 billion compared to the initial estimate of £19 billion. According to the Department, these two sums are not comparable. For example, the outturn figures overestimate expenditure on Decent Homes as they include other capital works to communal areas, lifts and the wider estate. In addition, the £19 billion was not an estimate of the total long-term cost to local authorities as it did not include the cost of future inflation or allow for properties that were decent at the start but which subsequently fell below standard. Finally, the English House Condition Survey, which formed the basis of the estimate, only examined the condition of samples of properties. Subsequent examinations by each local authority of all their housing revealed that the level of non-decency was higher than initially identified.[25]Figure 1: Landlord expenditure in the social housing sector: 2001-2011
Local authorities and ALMOs
Registered Social Landlords
Total
£ billion
£ billion
£ billion
29.32
8.07
37.39

Source: C&AG's Report, Figure 8

15. According to the Department, the production of a long-term estimate would have depended on the Department making such a series of assumptions about the way that the Decent Homes work was going to be done by landlords that the resulting estimate would have been of little use. The Department considered that the £19 billion estimate produced was, nevertheless, a good estimate of the total cost of work in the local authority sector and that it gave the Government a reasonable measure of the scale of investment required in that sector.[26]

16. The Department does not have robust information on the number of social housing properties made decent under the Programme. Although it has estimated that 1.4 million local authority properties have been made decent, this figure is based on local authority returns which include properties that are still non-decent but where tenants have refused work or demolition is planned. The Department also has no estimate for Registered Social Landlord properties.[27]

17. The Department considers that its figures for the year-on-year improvement in the overall number of decent homes in the social housing stock are robust.[28] Despite this, there is a significant difference in the extent of the improvement shown by returns from landlords and by the English House Condition Survey. According to landlord returns, the number of decent homes in the social housing stock had increased by 1.1 million by April 2009, whereas the Survey only showed an improvement of 500,000 by April 2007.[29] These differences have arisen, in part, because the landlord returns count tenant refusals and planned demolitions as being decent, whereas the Survey does not.[30] In the Department's view, the landlord returns provide the most reliable figures for progress on the Programme, although it also continues to publish the Survey's figures.[31]

18. Ministers set the parameters within which the Programme was to be delivered and decided that gap-funding specifically for Decent Homes would not be given to local authorities that chose to retain their housing stock.[32] The decision over whether to retain or to use one of the three delivery options that attracted gap-funding rested with local authorities.[33] Factors influencing their decision included the extent to which their properties were non-decent, whether they had sufficient funds to carry out the refurbishment needed, and their tenants' preferences.[34]

19. Although retaining local authorities have still received funding from the Department via the Major Repairs Allowance and Regional Housing Pot, the decision not to provide them with gap-funding ensured they received less money from the Government than authorities who chose one of the other three options for delivering Decent Homes.[35] Despite this, according to the Department the vast majority of local authorities are successfully implementing the Programme.[36] Where authorities still have work outstanding, the Department and the Homes and Communities Agency are actively engaging with these authorities about how they will complete this work within the Programme parameters set by ministers.[37]

20. In 2002 the Department set a target for private sector housing, that 70% of vulnerable households in such housing should be in decent accommodation by 2010. By April 2006, this target had almost been achieved, with 68% of vulnerable households in decent private sector housing. However, because of the introduction of the more demanding Housing Health and Safety Rating System in 2006, the number of such households in non-decent private sector accommodation increased. As a result, by April 2007, the number of vulnerable households in decent private sector housing had fallen to 61%.[38]

21. The funding of the private sector element of Decent Homes is much simpler than for the social housing sector, with local authorities receiving grants allocated by the Regions from the part of the Regional Housing Pot meant for private sector renewal. However, the Department only has an estimate of £1.2 billion for the amount of this grant that will be spent by 2011 on private sector Decent Homes.[39]

22. In overseeing the private sector element of the Decent Homes Programme the Department has given local authorities much greater discretion and has only monitored progress at a national level.[40] As a result, it does not know how much individual local authorities have spent on the private sector element of the Programme. It is more challenging for local authorities to monitor this element of the Programme because they do not control the housing stock.[41]


24   Qq 2, 3 and 39 Back

25   Qq 38-40 Back

26   Qq 2, 3 and 38 Back

27   Qq 44, 48 and 75; C&AG's Report, para 2.14 Back

28   Qq 13-15, 47 and 48 Back

29   Qq 16 and 75 Back

30   Qq 42 and 43 Back

31   Qq 16 and 43 Back

32   Qq 24, 25 and 31 Back

33   Qq 28, 29 and 33 Back

34   Qq 5, 12, 24, 28, 35, and 72 Back

35   Qq 24 and 26 Back

36   Q 20 Back

37   Qq 11 and 18-21 Back

38   Q 45; C&AG's Report, Figure 6 Back

39   Q 45 Back

40   Q 37 Back

41   Q 45; C&AG's Report, para 3.4 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 17 March 2010