Department for Transport: The failure of Metronet - Public Accounts Committee Contents


Examination of Witnesses (Questio Numbers 40-59)

DEPARTMENT FOR TRANSPORT AND LONDON UNDERGROUND PPP ARBITER

19 OCTOBER 2009

  Q40  Mr Touhig: Good; on both counts.

  Mr Devereux: If you are interested in the lessons learned, we will go on to those.

  Q41  Mr Touhig: On page 6, paragraph 10 we see that you told those who loaned money to Metronet that you would step in if there were a problem. Why did you do that?

  Mr Devereux: We did two different things. First of all, the deals were structured on the basis that London Underground itself guaranteed 95% of the debt and associated costs in the event of a default. Since the lenders were looking at London Underground and seeing a body largely financed by the Department itself, they looked to us for some comfort that, were LUL unable to meet that guarantee, we would not leave them in a position where they could not meet it. We issued a comfort letter to the effect that we would meet that. To answer the question why we did it and why the number was 95%, you will be aware from conversations with my predecessor and some of the evidence from the Transport Select Committee that, at the time these deals were being brought to conclusion, there was a fairly substantial disagreement going on between the Government and then Mayor as to his likely attitude to these contracts which in our judgment affected the level of guarantee which was ultimately given.

  Q42  Mr Touhig: So although you did not guarantee Metronet's borrowing, you were under pressure to protect the investors.

  Mr Devereux: No, the point I am making is a slightly technical one. London Underground guaranteed the borrowing. We gave a comfort letter to the lenders to say that in the event that guarantee was called, we would not stand by if they found themselves unable to meet it.

  Q43  Mr Touhig: I wish you were my bank. Can we go on then? We see on page 22, paragraph 2.23 that when Metronet went into administration in 2007, you made £1.7 billion available to pay its lenders. Can we get back to the point I was just asking about? That meant that you picked up the tab for the 95% guarantee that Transport for London offered.

  Mr Devereux: I paid £1,700 million for a settlement of an obligation which the NAO records.

  Q44  Mr Touhig: So you picked up the bill. They gave a guarantee and you picked up the bill.

  Mr Devereux: TfL paid £1,747 million and I paid £1,700 million, so I substantially picked it up.

  Q45  Mr Touhig: So the taxpayer substantially picked it up because of your Department. Can you understand that there must be a lot of anger at this awful waste of public money? Would it not have been simpler to have given these people the keys to the Royal Mint at Llantrisant and they could have gone in and printed their own money? It is an appalling effort on your partner's part, is it not?

  Mr Devereux: I am afraid I am going to come back to the same line I took with the Chairman. We are talking about a particularly complicated investment and upgrade programme in tunnels where there is a great deal of uncertainty as to what is in there. Previous attempts to do this have produced very, very substantial cost overruns. We have tried something different this time in the context of a devolved settlement and the extent of the uneconomic cost which has now been estimated—and you have never had one before in this Committee—is actually lower than the overall cost overruns previously. What am I pleading? I am pleading that we are protecting the taxpayer better than our predecessors but clearly not perfectly.

  Q46  Dr Pugh: There were cost overruns in the past, I understand the point you are making, but nevertheless we do not have the improvements we were expecting to get and, as the Chairman said, four years for the whole project instead of 30 years.

  Mr Devereux: I am sorry. You said you do not have the improvements you expected. Some things clearly have not been delivered to the time expected, some things have. We do have District Line trains refurbished, we do have a Jubilee line, we do have Wembley Park; the list is growing all the time.

  Q47  Mr Touhig: So it is growing all the time.

  Mr Devereux: To say that you do not have any benefit is wrong.

  Q48  Mr Touhig: I did not say we do not have any improvements. We have not had what we expected to have.

  Mr Devereux: You have not had what you were expecting but the C&AG is telling you that £4,500 million has been economically and efficiently spent. I would have thought the Committee would welcome that.

  Q49  Mr Touhig: I am sure we do but we do not welcome the fact that your Department oversaw and were responsible for a massive draw on the taxpayer, wasting public money. I think you ought to be ashamed of yourselves.

  Mr Devereux: I explained already that the massive draw you keep coming back to, the £1.8 billion, is not of itself an estimate of loss, nor does the C&AG accept that.

  Q50  Keith Hill: I probably ought to begin by making a declaration of interest, not for the first time. I was the Minister for Transport in London between 1999 and 2001 and the chief public advocate of the London Underground PPP; very enthusiastic. My excuse is of course that I had moved on to other things by the time the contracts were signed. Naturally I am disappointed with the way the Metronet contracts developed. I recognise that the DfT was not a party to the contracts but the Department were paying £1 billion a year to TfL specifically for the PPP contract and in the end, as we know, had to provide £1.7 billion of public money when Metronet went bust, of which up to £410 million was not spent economically or efficiently. Therefore I do sense that in these circumstances the Department did adopt a rather arm's-length relationship with the project. It liaised with London Underground and TfL. As the problems of Metronet developed, you received informal briefings from the Arbiter but you did, for example, refuse to meet directly with Metronet.

  Mr Devereux: Indeed.

  Q51  Keith Hill: We have to think really about this management for the future and I want to turn to the recommendations which the NAO make in recommendation B on page 9 and ask really how the Department propose to respond to these proposals. First of all, it is recommended that the Department should "collect and analyse a range of financial and performance data held by parties to the contract or available independently". Is that work underway?

  Mr Devereux: Let me start by coming back to your observation about the letter my predecessor wrote on 17 May because I have it in front of me. Let us just think what the alternative is. Here I have two parties who have signed a contract with respective obligations in, and it becomes apparent to all parties that Metronet the company is not delivering what it should do. In those circumstances I understand perfectly why my predecessor chose not to accept a briefing from the Metronet chief executive who, I suspect, was at that stage seeking somehow to make his case to a party who was not responsible for fixing it. If you think about what sort of messages would be sent, you risk the public sector giving mixed messages about what is going on here. It seemed to him far better that the contractual counterparty, in this case London Underground—and we did know what they were doing—should get on and have those conversations, not the Department to give its own views and opinions to Metronet, but rather say "Look, this is your problem, you need to fix it"—

  Q52  Keith Hill: Sorry to cut across you but my time is limited. That is a bit of historical speculation in a way.

  Mr Devereux: But it is the reality.

  Q53  Keith Hill: Going forward, there does seem to be a strong argument that DfT should perhaps be a little more on top of what is actually happening—I was going to say on the ground—in this case under the ground. Just let me ask. Are you collecting data about performance in a way that maybe historically you did not? That is a yes or no one really.

  Mr Devereux: The answer is that I already have performance data, which I was telling you that I was looking at, both in respect of what LU was up to and also what the Arbiter was telling me. I do have information such as that.

  Q54  Keith Hill: Okay. In that case I will take it that the answer to the first proposal under recommendation B is yes. What about the second item in the recommendation which is to "request regular risk reports from London Underground and TfL as the contracted clients"?

  Mr Devereux: The reason I am just pausing on this is because I do want to come back to the nature of the devolution settlement with the Mayor. I do not know whether you've had a long conversation with the Mayor about his view as to where the buck stops with him and where it goes to the Department. But when it comes to these contracts, I am indeed paying £1 billion for the Tube through a grant, a grant which Parliament has specifically restricted me from setting any conditions on, conditions along the lines of "By the way, here's £1 billion, I'd like to see the following information every Monday in my office; I'd like to see all these risk reports".

  Q55  Keith Hill: But it is possible for departments to have a close and successful and efficient working relationship with third parties which have devolved expenditure. We have had before us quite recently the Department for Children, Schools and Families to talk about the Building Schools for the Future programme which, after a bit of a faltering start, is proceeding very, very efficiently, delivered by local government primarily but on the basis of a very close working relationship between national government and local government. Here you have national government and a regional authority. Surely it ought to be possible for you to have and expect regular risk assessments from London Underground about the progress on both the contracts on which we are expending £1 billion a year.

  Mr Devereux: I am agreeing that it ought to be reasonable to ask for that. In practice, the nature of the relationship we have with TfL is that we see a lot of this. I am trying to draw a line between what actually happens in practice as a piece of influence and what I can require as a piece of policy and legislation. Were the Mayor to determine that he did not want to show me this, he would be entirely within his rights as Parliament has granted to him.

  Q56  Keith Hill: I understand that but I am sure this Mayor, just like the last Mayor, would be only too willing to work on a reasonable basis with the Department on this, if requested to.

  Mr Devereux: I agree and when we come onto the future that is the place we are going to be.

  Q57  Keith Hill: I am on the future now. Let me just ask you finally about the third part of recommendation B, and this is what we have been talking about, "review the devolved body's understanding of the key risks of the project". This is really very important, is it not? At the end of the day you really, as a department, relied on London Underground and TfL to assess whether the project was being delivered in a cost-effective way.

  Mr Devereux: Yes.

  Q58  Keith Hill: And actually it is perfectly arguable that they did not, particularly in the case of Metronet, monitor and scrutinise the performance of that body in as much detail as possible. Therefore it is very important for you to be assured that they are going to do that job properly in the future. Do you have that assurance?

  Mr Devereux: The position on where we are going to be in the future is covered by recommendation F later on, is working with the Mayor and TfL on what the successful arrangements for Metronet are. I am expecting my Secretary of State and the Mayor to make announcements about this very shortly. I think that will give you some comfort that we are in the space of reasonable men.

  Q59  Keith Hill: That is very interesting. We look forward very much indeed to that. It seems to me that you have been really rather positive about the future role of the Arbiter. I think I quote you correctly when you said in retrospect that the Arbiter should have been given greater powers. Actually, if you look at recommendation E on page 10 three powers are set out there which the NAO recommends that the Arbiter should exercise in future, namely to carry out recommendations, where appropriate, to require an annual review of the Arbiter and to allow an extraordinary review even if not requested by the parties to the contract. Is it your intention as a Department to strengthen the Arbiter in this way?

  Mr Devereux: Strictly speaking one, two and three are not all addressed to the Arbiter but the general point is this. If we are to exist in a world in which LU on the one hand and a contractor on the other is delivering work with very large sums of money at stake, I want to see a degree of transparency about what is going on there and a degree of prospective looking at what is economic and what is inefficient.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 2 March 2010