Scrutiny of value for money at the BBC - Public Accounts Committee Contents


4  Learning lessons to improve value for money

24. Identifying and applying lessons from previous experience can improve value for money. The BBC's track record, however, suggests that lesson learning is more opportunistic than structured and culturally embedded.

25. We were pleased to see from our recent examination of the BBC's three major estates projects, that the BBC had applied lessons from phase 1 of the Broadcasting House project to phase 2, and to the Pacific Quay and Salford Quay projects. The BBC also, over the lifetime of these three projects, improved the way it identified and recorded lessons learnt. For example, it prepared a post­project implementation review for the Pacific Quay project which identified good practice and areas for improvement when managing future estates projects. In addition, the BBC had introduced arrangements for sharing lessons between these projects.[32]

26. Lesson learning has been less evident in other areas of the BBC's work. The Comptroller and Auditor General's report on the BBC's management of its strategic contracts showed that the BBC's Strategic Relationships Board was little more than a talking shop, and that the lack of executive authority meant it was unable to enforce compliance with minimum standards in contract management. The report also showed that while the BBC's approach to supplier relationship management was above average compared with other organisations, the engagement of senior managers varied, as did the extent to which the BBC and the supplier had a shared understanding of the status of the relationship. The latter point was a particular difficulty in the case of the BBC's largest strategic contract, the £230 million spent annually with Siemens.[33]

27. In June 2007, we recommended that the BBC ensure that contractors' profits were not excessive through the robust enforcement of the 'open book' terms of its contract with Siemens. However in 2009, the Comptroller and Auditor General reported that the BBC had failed to utilise its 'open book' provisions across four of the five strategic contracts he examined.

28. In looking to challenge the cost of programmes, the BBC has made limited use of the information available to it. The BBC's reviews of its coverage of major events lacked coherence as they did not bring together a review of the cost and quality of the coverage and of the management of the coverage, in one place. The impact of the reviews was further weakened by the absence of criteria for measuring success and the irregular frequency of the reviews.[34] Internally, the BBC did not use the results of a report it commissioned into the cost of similar radio programmes to identify possible savings.[35] Nor has it benchmarked internally the different cost elements of its coverage of major sporting and music events.[36]

29. Comparisons with rival programme makers can also be helpful, although we recognise that commercial sensitivities can make that difficult. However, in response to our report on the efficiency of its radio production, the BBC committed to work with the commercial radio sector to develop a suitable benchmarking process and for radio production and major events it has acknowledged the need to take a more systematic approach to cost comparisons.

30. The BBC recently established a pan­BBC Programme Management Office to support its programme and project management capabilities. The Office offers guidance and bespoke support to specific programmes, and looks to spread good practice. The early focus of the Office's work is on the BBC's strategic priorities. Over time, the work of the Office could usefully cover, say, production as a way of ensuring good practice is applied as widely as possible.[37]

31. Elsewhere, the BBC faces and needs to manage a variety of risks, ranging from the reputational risk of its programmes to the health and safety risk of those working overseas. Using external guidance, such as that provided by HM Treasury, could help the BBC. For example, contrary to Treasury guidance, the BBC had not aligned its main themes for risk management with its corporate objectives, and had not assigned all risks to named owners. In addition, many BBC risk managers (29%) had never looked at the BBC's guidance.[38]


32   C&AG's Report, The BBC's management of three major estates projects, February 2010, para 2.33 and 2.34; Qq 196 and 197 Back

33   C&AG's Report, The BBC's management of strategic contracts with the private sector, March 2009, paras 46 and 64 Back

34   Qq 9 and 33  Back

35   C&AG's Report, The efficiency of radio production at the BBC, February 2009, para 55  Back

36   Q 97  Back

37   C&AG's Report, BBC's management of its coverage of major music and sporting events, December 2009, para 58  Back

38   Committee of Public Accounts, Sixty­sixth Report of Session 2006­07, The BBC's management of risk, HC 643, paras 3, 4 and 11  Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 7 April 2010