Update on the London Underground and the public-private (PPP) partnership arrangements - Transport Committee Contents


1  Introduction


1. The Transport Committee and our predecessor committees followed closely the process which led to the London Underground Public Private Partnership (PPP) agreements in 2003. Over the last seven years we have continued to monitor the performance of the PPP and we have, on a number of occasions, placed on record our judgement that the PPP is flawed. In 2005, we concluded that "on the evidence we received, improvements in facilities and performance are not in proportion to the huge sums of money flowing through the PPP."[1] We stand by that judgement which was reinforced in July 2007 when Metronet, one of the two infrastructure companies (infracos) in a PPP agreement with Transport for London (TfL), went into administration with significant debts and having failed to meet its obligations for network improvements.[2] Our 2008 Report, The London Underground and the Public-Private Partnership Agreements, recommended that, "If it is not possible in reality to transfer a significant proportion of the risk away from the public purse, a simpler—and potentially cheaper—public sector management model should seriously be considered."[3]

2. Our previous reports have described the PPP agreements in detail and what we consider to be their failings; it is not our intention to reiterate our full analysis here.[4] The purpose of this short report is to provide an update on the remaining PPP agreement between TfL and Tube Lines. We consider whether the remaining PPP agreement has been working in the interests of taxpayers and passengers since the failure of Metronet. We also consider the performance of London Underground (LU) since May 2008 when it took over responsibility for the Underground lines formerly managed by Metronet. Finally, we provide an update on the first periodic review which will establish the context for the PPP until 2017.

3. We are grateful to the organisations and individuals who submitted written evidence and to the nine witnesses from whom we took oral evidence in December 2009 and January 2010. In connection with this inquiry, we visited London Underground in December 2009. The visit provided us with an insight into the work being undertaken by LU in introducing new trains, replacing signalling and renovating stations on the Victoria line. We are grateful to those who helped arrange our visit.

The demise of Metronet

4. LU entered into three separate PPP Agreements—with Tube Lines in December 2002 and with Metronet (two separate Agreements) in April 2003. Under the agreements, which were due to run for 30 years, the infracos would maintain, renew and upgrade parts of LU's infrastructure in return for a set price agreed between TfL and the infraco. Any additional work carried out would be for an amount agreed by both parties. LU remained responsible for delivering services to customers. The Government predicted that the PPP agreements would realise over £16 billion of investment in the Underground and £4 billion of savings through efficiency gains whilst utilising the expertise of the private sector.[5]

5. It soon became clear, however, that the PPP agreements were not delivering many of the improvements to the network that the Government had hoped. In 2005, we concluded that:

Availability is the most important factor for Tube travellers. All the infracos needed to do to meet their availability benchmarks was to perform only a little worse than in the past. On most lines, they did not even manage that. We hope that they will be able to meet the more demanding targets for availability expected in future; we have no confidence that will be the case. [6]

6. In addition, the claim that the PPP would result in value for money for the taxpayer was undermined when Metronet went into administration in July 2007. Metronet had overspent its budget for renovations and refurbishment, and was refused additional loans by its creditors. In our detailed analysis of Metronet's failure, The London Underground and the Public-Private Partnership Agreements, we concluded that "the PPP model was flawed" and that the failings of Metronet's management had led to its downfall.[7] Our report, and the July 2009 report by the National Audit Office (NAO), The failure of Metronet, ascribed the infraco's failure to:

a)   Metronet's poor corporate governance and leadership;

b)   Metronet's shareholders also acting as suppliers in a tied supply chain with management structures which gave power to the suppliers, rather than the management of the business;

c)  London Underground's limited ability to manage the contract in a way that prevented costs from escalating, and

d)  the inability of the PPP Arbiter to initiate an Extraordinary Review of the PPP Agreement with Metronet when it was clear that the infraco was experiencing difficulties,[8] but before it entered Administration (under the terms of the PPP, the Arbiter could intervene only if invited to do so by one of the parties involved).[9]

7. Although Metronet's failure was largely of its own making, the terms of the PPP agreements meant that it was taxpayers who footed most of the bill for its demise. According to the NAO, the total cost of Metronet's collapse was £1.75 billion. Of that figure, Metronet's parent companies—Atkins, Balfour Beatty, Bombardier, EDF Energy, and Thames Water—were liable only for £70 million each. The taxpayer was liable for approximately £1.7 billion, equivalent to 95% of Metronet's debt obligations. However, the NAO concluded that the overall direct loss to the taxpayer was in the range of £170 million-£410 million. The remaining loss was "an unanticipated upfront cost to the taxpayer and equivalent to paying off a mortgage early"an obligation on the taxpayer through a grant from the DfT to TfL which would have fallen due at a later date in any case.[10]

8. The Mayor of London, Boris Johnson, argued that the cost to TfL of Metronet's demise was in fact £550 million because, he argued, the NAO estimate did not take into account work left undone by Metronet, which LU has addressed subsequently, or work outstanding which needs to be completed by LU in the future.[11] TfL's submission to this inquiry stated that "LU has also had to deal with the financial legacy of Metronet's collapse—the result of poor programme management and system integration, ineffective cost control, a lack of forward planning and inefficient fiscal management". [12]

9. All witnesses to our inquiry accepted that Metronet's failure cost the taxpayer millions of pounds and that the structure of the PPP left the taxpayer to bear a large financial risk. The Mayor, Boris Johnson, described Metronet's PPP agreements as "a system that was not operating in the interest of taxpayer value, that ballooned until the point of explosion".[13]

10. As we stated two years ago, the failure of Metronet demonstrates the flawed nature of the PPP agreements which placed an unacceptable burden of risk on the taxpayer. Metronet's demise, which cost the taxpayer at least £170 million, has cast a long shadow of doubt over the remaining PPP agreement with Tube Lines.


1   Transport Committee, Sixth Report of Session 2004-05, The Performance of the London Underground, HC 94 Back

2   Transport Committee, Second Report of Session 2007-08, The London Underground and the Public-Private Partnership Agreements, HC 45 Back

3   HC (2007-08) 45 Back

4   For a detailed explanation of the principles of the PPP see HC (2007-08) 45 and HC (2004-05) 94. Back

5   HC (2004-05) 94 Back

6   IbidBack

7   HC (2007-08) 45 Back

8   The PPP Arbiter, established by the 1999 Act, has two principal statutory functions:- to give directions on matters specified in the PPP Agreements, when asked to do so by one of the Parties to a PPP Agreement, and to give guidance on any matter relating to a PPP Agreement, when asked to do so by either (or both) of the Parties to a PPP Agreement. Back

9   The National Audit Office, The failure of Metronet, HC 512, 5 June 2009 Back

10   The National Audit Office, The failure of Metronet, HC 512, 5 June 2009 Back

11   Q 18 Back

12   Ev 46 Back

13   Q 2 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010