Update on the London Underground and the public-private (PPP) partnership arrangements - Transport Committee Contents


4  The 2010 periodic review

47. The poor relationship between Tube Lines on the one hand, and TfL and LU on the other has continued into the periodic review exercise. Under the PPP Agreement, LU and Tube Lines are required to set out a programme of work for 2010-17 along with estimated costs. Some tension in the process is inevitable because the parties have conflicting objectives: Tube Lines wants to deliver the work as cost-effectively as possible so that it can provide dividends for its shareholders; TfL is seeking to maximise the work done whilst minimising cost.

48. TfL and Tube Lines began planning for the periodic review in 2009. Following informal discussions between the two parties, it became apparent that the two organisations' estimates of the work that needed to be done during 2010-17 diverged very significantly. As negotiations between the two parties stalled, both parties submitted to the PPP Arbiter their estimates of the cost of an upgrade and maintenance programme from 2010-17, including an extensive upgrade of the Piccadilly line. The second set of projections were submitted by each party to the Arbiter, as required, on 17 November 2009. The main difference between the two submissions was "updating" to reflect the agreement reached between Tube Lines and TfL on the scope of the work programme and to take into account inflation. In total, Tube Lines' 17 November submission proposed costs of £5.75 billion. London Underground considered that the appropriate level of costs was £4 billion.

49. On 17 December, the Arbiter published his "draft directions on costs and related matters" for the period 2010-17. The Arbiter judged that the cost of works on the Jubilee, Northern and Piccadilly lines over the seven and a half years from 1 July 2010 should be set at £4.4bn. According to Chris Bolt:

I have reviewed carefully the submissions from Tube Lines and London Underground, and taken expert advice. On the basis of my analysis, I consider that a company operating in an overall efficient and economic manner and in accordance with Good Industry Practice—the test in the PPP Agreement—could deliver its obligations at a substantially lower cost than projected by Tube Lines, though not as cheaply as suggested by London Underground.

50. The Arbiter reached his initial judgement by comparing Tube Lines' estimated costs with similar projects undertaken on other metro systems, a process he referred to as international benchmarking. He found Tube Lines' estimated unit costs to be significantly higher. In addition, the Arbiter explained that part of the £1.35 billion difference between his estimate and that of Tube Lines was a consequence of Tube Lines' poor performance on the Jubilee line:

My assessment is that the notional infraco, which is the standard I have to use for pricing, would have delivered or could have delivered the Jubilee line on time and that as a consequence about three-quarters of the work on the Northern line would be completed in the first review period.[46]

Therefore, some of the costs that Tube Lines expects to accrue in the second review period, should, according to the Arbiter, have been borne by the company during the first period. The Arbiter's judgement encouraged TfL and Tube Lines to make further representations to his office before he published his final guidance in "early March 2010".

51. The PPP Arbiter's final directions and guidance, published on 10 March 2010, increased his initial estimate of the cost of the work to be carried out by Tube Lines during 2010-17 by £65 million to £4.465 billion.[47] Alongside this guidance, the Arbiter recommended that London Underground should either: finance the £465 million shortfall between its estimate and the Arbiter's final directions, or scale back the work that it required Tube Lines to carry out during 2010-17.[48] TfL's initial reaction to the Arbiter's guidance was that the Arbiter had exceeded his powers by making directions on finance and that TfL would keep its options open.[49]

IMPLICATIONS FOR THE FUTURE OF THE PPP

52. The Arbiter's guidance for 2010-17 has led some commentators to question whether Tube Lines and with it, in all likelihood, the PPP itself has a viable future. If Tube Lines is to deliver what it has agreed to, it will have to make up the funding gap of £1.5 billion between its own cost estimate and what TfL will pay. Tube Lines' shareholders (Bechtel and Amey) must decide if they can afford to make up the difference or seek to raise additional funds for Tube Lines' 2010-17 programme in a very difficult financial environment. Alternatively, if the management board of Tube Lines decides that neither option is feasible, then the company's future involvement in the PPP will be in doubt. The former Chief Executive, Dean Finch, told us that Tube Lines would not follow Metronet into administration and that no conclusion about the company's viability should be drawn from his decision to leave his position as Chief Executive of Tube Lines.[50]

53. The Arbiter's initial guidance also has implications for TfL which will have to find an additional £400 million to finance the work planned for 2010-17. If it cannot provide the additional funding through further increases or additional grants from the Government, it will need to review the scope of its requirements for the next seven and a half years. In all likelihood, this could result in fewer station refurbishments or less ambitious track renewals.

54. The fall out from the PPP Arbiter's ruling on the costs for the second review period may take a while to become apparent. In the meantime, the process leading up to the Arbiter's final ruling in March 2010 has subjected Tube Lines, responsible for three Underground lines, to a great degree of scrutiny. The level of transparency given to Tube Lines' project planning and cost estimates is welcome; however, this degree of scrutiny is currently not applied to London Underground, itself responsible for managing improvements to seven Underground lines. As stated previously, this situation is one that this Committee recommended should be improved by granting the Arbiter more power to monitor the performance of TfL.


46   Q 153 Back

47   www.ppparbiter.org.uk/output/Page1.asp Back

48   Tube Lines will be required to deliver the refurbishment of stations and the completion of upgrades to the Northern and Piccadilly lines. Back

49   TfL Press Release, Mayor and TfL: Arbiter's Directions show PPP is "not delivering for Londoners and taxpayers" 10 March 2010 Back

50   Q 44 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010