Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Memorandum from the PPP Arbiter (UPP 02)

INTRODUCTION

  1.  The role of statutory Arbiter for the London Underground Public-Private Partnership Agreements was created by the Greater London Authority Act 1999. I was appointed as the first PPP Arbiter in December 2002, and my appointment runs to 30 December 2010. My role is concerned principally with assessing the efficient level of costs and pricing at Periodic Review (and at the Extraordinary Reviews which may take place between Periodic Reviews). Annex 1 summarises my functions and duties.

2.  Based on my experience to date, I set out below my views on some of the questions covered by the call for evidence. I do not respond on questions which are outside the scope of my role as PPP Arbiter. Nor do I comment on matters directly related to the Periodic Review of Tube Lines' PPP Agreement which are the subject of a reference to me from London Underground dated 23 September 2009.

What lessons can be learned from the collapse of the London Underground PPP Agreement with Metronet?

3.  My views on the collapse of Metronet were set out in evidence to the Committee in 2007, when it last considered the London Underground PPP.[1]

4.  I consider that the main lessons which are relevant to the management of the PPP Agreements are that their effectiveness depends on:

    — an agreed base plan, to enable effective monitoring of both costs and performance;

    — a clear understanding between the contract parties about the allocation of risk, with effective monitoring of key risks, in order to incentivise delivery by the infracos;

    — effective partnership;

    — regular independent reporting on the performance of the infracos; and

    — provisions which prevent an Infraco deferring a request for Extraordinary Review once it is clear that increases in costs are likely to exceed the Materiality Threshold.

  5.  In terms of delivery, there was a general consensus that Metronet's governance was ineffective and that this, coupled with its supply chain structure, made a major contribution to its failure. Tube Lines competitively tendered its major contracts, for example in respect of the signalling upgrades for its three lines, although secondment agreements with its shareholders, Bechtel and Amey, give those companies a major role in managing major projects and operations respectively. In preparing for a Periodic Review reference, I have sought advice on whether this approach to procurement and project management has delivered an outcome consistent with that of a Notional Infraco.[2]

  6.  Although London Underground has claimed savings of £2.5 billion as a result of taking Metronet in-house, this largely reflects reductions in costs from levels which, as part of my uncompleted 2007 Extraordinary Review of Metronet, I had concluded were inefficient. It is too early to make a robust comparison between the costs of public sector and private sector provision of infrastructure services. However, the report on Phase V of the joint benchmarking programme comparing the operating expenditure of Tube Lines with the former Metronet companies, which covers 2008-09, will be available shortly. Initial results from the draft analysis undertaken for this report suggest that the former Metronet companies' maintenance costs for track, signalling, stations, lifts and escalators have risen in 2008-09 compared with 2007-08 levels. The draft analysis also reinforces previous year's benchmarking results which have found Tube Lines' maintenance costs to be lower on average than for the former Metronet companies.

Are these lessons being applied to the London Underground PPP Agreement with Tube Lines?

  7.  As part of the preparation for the Periodic Review, my Office has developed a format for the submission of information about future costs (the "Data Breakdown Structure"—DBS) which both London Underground and Tube Lines have agreed to adopt. This will ensure consistent provision of information, which London Underground is also following for the former Metronet companies. In particular, it will facilitate monitoring of costs and activities against plans, and make it easier to compare performance both between the infracos and with external comparators.

8.  Under the terms of the PPP Agreement, an Infraco is protected, through the Extraordinary Review mechanism, against all changes in the efficient cost of delivering its contractual obligations, except for the first £50 million in each 7½ year period.[3] This is only about 1% of the contract value. An important part of the Periodic Review is therefore establishing an appropriate allowance for risk. If this is too high, London Underground could pay too much for the contract; if it is too low, an early Extraordinary Review could be required, which would impact adversely on incentives to deliver improved efficiency over the whole Review Period.

  9.  I have also, therefore, discussed with the Parties through the regular tripartite meetings which I chair the linkage between the risk allowance at Periodic Review and the form and conduct of the Extraordinary Review mechanism in the second Review Period. This will now be considered further as part of the Periodic Review reference.

  10.  Under Metronet's PPP Agreements, it was envisaged that the Arbiter would report annually on efficiency and economy. In the event, I was only asked to carry out one such annual review, in 2006, before Metronet went into administration. Although the Metronet PPP Agreements remain in place, London Underground has indicated to me that it does not propose to seek annual reports in future.[4] The Committee recommended in its last report on the PPP that a mechanism be put in place to allow the PPP Arbiter to report annually on the performance of all the Infracos, including Tube Lines, whether or not he is called on to do so; the recent report from the National Audit Office[5] made a similar recommendation.

  11.  Unless the Arbiter's role is extended in the way the Committee recommended, the future role of the Arbiter would be restricted to Periodic and Extraordinary Reviews of the Tube Lines Agreement alone. With this restricted role, and no regular reporting function, it would be difficult to retain or recruit staff of the current calibre beyond the current Periodic Review. This could seriously prejudice the effectiveness of the Arbiter's statutory role, for example by losing continuity in the benchmarking work which I have initiated.

  12.  If the Arbiter was able to prepare and publish regular assessments of Infraco performance, it might not be necessary to make contract changes to prevent an Infraco deferring a request for Extraordinary Review (or giving London Underground the right to trigger such a Review). With that degree of transparency, it is much less likely that lenders would waive the requirement to seek Extraordinary Review than was the case with Metronet.

How has the upgrade work progressed since the demise of Metronet?

  13.  It is currently difficult to make a full assessment of the upgrade projects, given that most are still under way, and because of changes in reporting arrangements for Metronet following administration. The Arbiter is working with London Underground to develop information that would permit him to monitor the Metronet upgrades and use data gathered in this way as a benchmark for Tube Lines.

14.  The Arbiter's Independent Reporter has reviewed the basis of London Underground's cost projections for the former Metronet companies and raised a number of concerns about the robustness of the projections.[6] A further review will be undertaken by the Reporters in the New Year.

What contractual arrangements are appropriate for the future?

  15.  Experience with the PPP Agreements over the first Review Period suggest that areas where contractual changes might be considered for the future include the following:

    — a requirement to produce data in a stable (DBS) format that tracks progress against the financial baseline for Net Adverse Effects;

    — a requirement for Infraco to prepare, in DBS format with appropriate commentary, a delivery plan for each Review Period following completion of the Periodic Review;

    — an annual review (either by London Underground or the Arbiter) of contract delivery based on a comparison between updated plans for the remainder of the Review Period and the delivery plan;

    — clarification of the treatment of investment to deliver improved efficiency where the payback period straddles a Periodic Review;[7]

    — clarification of the potential overlap and conflict between Extraordinary Review and contractual claims;

    — clarification of overlapping jurisdiction between the Arbiter and an Adjudicator at Periodic Review, for example in relation to financeability; and

    — review of the Extraordinary Review mechanism given the lower materiality threshold for RP2.

  16.  Although a number of these matters are covered by "entrenched provisions", which means that London Underground is unable to propose changing them as part of the Periodic Review, I have the power in giving directions to make directions which are ancillary and incidental to the matter referred.[8] As with all my directions, these have the effect of modifying the contract unless both Parties agree to set the directions aside. I will therefore want to consider as part of the Periodic Review reference whether there are matters in respect of which I have the power to make such ancillary or incidental directions in order better to achieve the objectives set out in my statutory duty.

  17.  I have no role in respect of contractual arrangements which are not designated PPP Agreements. This includes, for example, the proposed contract for resignalling of the Sub-Surface Lines. However, many of the principles outlined above are equally relevant to other contractual models.

  18.  Given my limited remit, it would not be appropriate to comment in detail on alternative contractual models. However, I have previously compared the PPP structure with the regulation of the national rail network,[9] noting the greater flexibility under a licence structure than under a contract. My conclusion then was that "if the Parties are able to agree changes in the incentive structures where there are weaknesses, learning from the experience of the regulated utilities, then the outcome in terms of efficient delivery of customer requirements could be very similar to that achieved by economic regulators—even with an Arbiter reacting to disputes rather than driving the process. But if these opportunities cannot be taken, then the superiority of a licence structure will have been demonstrated." I stand by that conclusion.

What risks, if any, are associated with the PPP Agreement with Tube Lines?

  19.  The main risks associated with Tube Lines' PPP Agreement are, in my view, as follows:

    — inability for Tube Lines to finance the difference between the efficient costs of delivering contract obligations in the second Review Period and London Underground's Affordability Constraints, leading to a requirement to descope or, in certain circumstances, Special Mandatory Sale;

    — increases during the second Review Period in efficient costs of delivering contract obligations, leading to additional ISC payments by London Underground, or a requirement to descope for affordability reasons, at an Extraordinary Review;

    — financial failure as a result of Tube Lines incurring costs inefficiently, or failing to deliver contract obligations as a result of inefficiency; and

    — "regulatory risk".

  20.  I have yet to make any directions under the provisions of the GLA Act, which inevitably creates a degree of uncertainty about the basis on which I would reach decisions. I have sought to mitigate this by:

    — consulting on, and publishing a Procedural Framework for handling references, with accompanying Procedural Approach documents for different types of reference updated in the light of experience;

    — sharing technical reports and advice (for example benchmarking reports) with the Parties, seeking comments on that advice, and in most cases publishing the reports;

    — responding positively to requests for guidance, even where I have discretion not to give it,[10] and giving full reasons for guidance, supported by detailed technical reports; and

    — in respect of the Periodic Review, establishing and (with the agreement of Tube Lines and London Underground) chairing a regular tripartite meeting to ensure adequate preparation for the Review.

Annex 1

THE FUNCTIONS AND DUTIES OF THE PPP ARBITER

  1.  The role of the PPP Arbiter was established by the Greater London Authority Act 1999 (GLA Act). Under the terms of the GLA Act, the Arbiter is independent of Government and of the PPP Parties and can only be dismissed by the Secretary of State on grounds of incapacity or misbehaviour, or for unreasonable delay in the discharge of his functions.

2.  The Arbiter is a corporation sole. I was appointed as the first Arbiter on 31 December 2002, and my appointment now runs to 30 December 2010. I am supported by a small permanent staff. As I am appointed as an individual, and am personally responsible for the exercise of my statutory functions, I have also appointed an Advisory Board to provide independent and expert challenge to my decisions and procedures. Although I am not required by statute to do so, I have published each year a Business Plan and my Annual Report and Accounts setting out the work programme of my Office and the resources used.

  3.  As PPP Arbiter, I have two principal statutory functions:

    — to give directions on matters specified in the PPP Agreements, when asked to do so by one of the Parties to a PPP Agreement; and

    — to give guidance on any matter relating to a PPP Agreement, when asked to do so by either (or both) of the Parties to a PPP Agreement.

  4.  When the Arbiter is asked for guidance by one Party only, the Act gives me discretion about whether to give guidance. Where I am asked for directions, or am asked for guidance by both Parties to an Agreement, I am required to give directions or such guidance as I consider appropriate.

  5.  Although the Arbiter can be asked for guidance or directions at any time, it was expected that he would exercise formal functions in three main circumstances:

    — in giving an annual "definitive statement" on the performance of the two Metronet infracos;

    — at the Periodic Review of the Agreements which takes place every 7½ years; and

    — at an Extraordinary Review of the terms of a PPP Agreement if there were material changes in costs and revenues within a Review Period.

  6.  In addition, the Act gives the PPP Arbiter further powers "for the purposes of the proper discharge of the functions" conferred on him by the GLA Act. For example the PPP Arbiter may do "all such things as he considers appropriate for or in connection with the giving of a direction or guidance and ... do such other things as he considers necessary or expedient ... for purposes preparatory or ancillary to the giving of directions or guidance generally| notwithstanding that there is no matter in relation to which a direction or guidance is required".

  7.  The PPP Arbiter's function in respect of directions is limited by the terms of the PPP Agreements: if there is no specific provision in a PPP Agreement for the PPP Arbiter's involvement then disputes are dealt with through contractual dispute resolution. Even on matters within his remit, he is only brought in if one of the Parties seek a direction from him. The PPP Arbiter therefore has no unilateral power to change, or propose to change, provisions in the PPP Agreements. Even where he has made a direction on a disputed matter within his remit, the Parties may, under the provisions of the GLA Act, jointly agree to set it aside.

  8.  In exercising his functions, the Arbiter is under a statutory duty to act in the way he considers is best calculated to achieve four objectives:

    — to ensure that London Underground has the opportunity to revise its requirements under the PPP Agreements if the proper price exceeds the resources available;

    — to promote efficiency and economy in the provision, construction, renewal, or improvement and maintenance of the railway infrastructure;

    — to ensure that if a rate of return is incorporated in a PPP Agreement, and taking into account matters specified in the Agreement, a company which is efficient and economic in its performance of the requirements in that PPP Agreement would earn that return; and

    — to enable the Infracos to plan the future performance of the PPP Agreements with reasonable certainty.

  The Arbiter is also under a duty to take account of any factors which are notified to him by both Parties to an Agreement, or are specified in the relevant PPP Agreement, as ones to which he must have regard.

  9.  For the purposes of assessing costs at a Periodic Review or Extraordinary Review, the PPP Agreement establishes the concept of the Notional Infraco. This is defined as the entity which has the same obligations as Infraco, which carries out its activities in an overall efficient and economic manner and in accordance with Good Industry Practice, and has certain other specified characteristics. A key part of the Arbiter's role is therefore to assess what constitutes Good Industry Practice and the level of performance and cost which would be efficient and economic.

September 2009








http://www.ppparbiter.org.uk/output/page21.asp?DocTypeID=5.

http://www.ppparbiter.org.uk/files/uploads/n_guidance/200611811558_Tube%20Lines'%20straddling%20reference.PDF.

http://www.ppparbiter.org.uk/files/uploads/f_articlesLectures/200741792822_CRI%20Occasional%20lecture.pdf.



1   HC45: The London Underground and the Public-Private Partnership Agreements, Second Report Session 2007-08, 25 January 2008. Back

2   The Notional Infraco is defined in the PPP Agreement as the notional entity with the same contractual terms and financing as Infraco, and which carries out its activities in an "overall efficient and economic manner and in accordance with Good Industry Practice". The Notional Infraco is the basis of repricing the contract at Periodic Review. Back

3   This "Materiality Threshold" was £200 million for Tube Lines in the first Review Period. Back

4   London Underground has also indicated that it has no intention of involving me in the Periodic Review of the agreements. Back

5   The Department for Transport: The failure of Metronet, HC 512 Session 2008-09, 5 June 2009. Back

6   Independent Reporter's Report on BCV's Annual Asset Management Plan: Annual Report to the Arbiter and Independent Reporter's Report on Metronet SSL's Annual Asset Management Plan: Annual Report to the Arbiter, 17 July 2008 at Back

7   This issue was covered in guidance issued in 2006, following a reference by Tube Lines: Reference for guidance by Tube Lines Limited: Investment which straddles the Periodic Review, 8 November 2006 at Back

8   GLA Act, section 229(3)(b). Back

9   Regulating by contract and licence: the relationship between regulatory form and its effectiveness, CRI Occasional Lecture, 28 March 2007 at Back

10   Under the provisions of section 230(2) of the GLA Act, I may give guidance if the reference comes from one party; I shall give guidance where both the Parties to an Agreement request it. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010