Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Memorandum from London TravelWatch (UPP 03)

1.  INTRODUCTION

  London TravelWatch is the official body set up by Parliament to provide a voice for London's travelling public, including the users of all forms of public transport. Our role is to:

    — speak up for transport users in discussions with policy-makers and the media;— consult with the transport industry, its regulators and funders on matters affecting users;

    — investigate complaints users have been unable to resolve with service providers; and

    — monitor trends in service quality.

  Our aim is to press in all that we do for a better travel experience all those living, working or visiting London and its surrounding region.

2.  THE INQUIRY

  London TravelWatch welcomes the House of Commons Transport Committee's further inquiry, which will build on its previous work, and will consider:

    — Whether the lessons learned from the collapse of the Metronet PPP consortium have been applied to the Tube Lines PPP?

    — How the upgrades are progressing?

    — What contractual arrangements are appropriate for the future?

    — What risks are associated with the PPP arrangements with Tube Lines?

    — What impact is the current economic situation having on transport PPP and PFI schemes and what are the financial implications for other transport schemes?

    — What role has the Government played in these matters?

  Recently, we have worked closely with the London Assembly Transport Committee on this issue, and attached as Appendix A is our written evidence to them.[11]

3.  GENERAL PRINCIPLES OF THE PPP

  In general terms Public Private Partnerships (PPP) are typically characterised by the following features:

    — long term relationship between the public sector and a private partner for the delivery of a project, typically contracts are between 15 to 30 years;

    — funding is provided by the private partner, however some level of public funding may be included to complete the funding requirements of the project;

    — the private partner is typically involved in all levels of delivery of the project the objectives of which have been defined by the public sector; and

    — a transfer of risk takes place from the public to the private sector. This does not mean that the public sector is left without risk, but much of the risk associated with a portion of the financing, the delivery and operation of the project would typically be transferred. The actual distribution of the risk is dependent on the ability of each party to be able influence and control the risk. The public sector will therefore retain a substantial amount of risk over which it retains control. Examples of retained risk might include:

    — changes in scope of the project;

    — changes in the law;

    — force majeure; and

    — indemnities for specific issues such as existing asset conditions.

  Globally PPPs can vary substantially within these broad features and even within the UK a wide variety of structures can be observed.

  As previously submitted to this committee, London TravelWatch supports the objective of the London Underground PPP to guarantee the flow of investment into the Underground, after many years of inconsistency and fluctuation. We consider it of the utmost importance that the periodic reviews at 7.5 year intervals should not be allowed to become vehicles for under-funded price rises and for the scope of investment plans to be cancelled or reduced in scope. This concern is given added importance by the slippage that has occurred in parts of the investment schedule, and by Metronet going into administration, each of which phenomena increases the opportunity for cuts to be made in previously agreed investment programmes.

  We were initially concerned that animosity to the principle of the PPP would adversely affect relationships between London Underground (LU) and the PPP contractors. We are therefore encouraged by the determination of LU's top management to work constructively for the success of the PPP in the interests of Underground users, whatever may have been the political debate over its introduction.

  We are, however, concerned that—despite assurances that the Infrastructure Companies (Tube Lines and Metronet) would get on top of the problems, once the period of climbing the "learning curve" had passed—placing contracts for looking after 70% of the LU network with a single organisation was too much. Tube Lines, with only 30% of the business, has shown itself to be more capable of delivering projects on time and to budget, although its slowness to rise to the challenge of improving performance on the Northern line has been disappointing.

  However, we are now somewhat alarmed by the increasing number of weekend engineering possessions being required on the Jubilee line in recent months, and about how the upgrade of the Piccadilly line will take place particularly on the central London section of route. We submitted evidence to the London Assembly Transport Committee scrutiny of this issue and this we attach as appendix A to this submission. We believe that whilst passengers are willing to accept some measure of "pain", provided that they are informed about alterations to their services well in advance and can plan accordingly, when these are then supplemented by short notice additional closures for example, passengers' patience can be severely tested. This is particularly important when passengers may be making leisure journeys (say to the O2 arena) or to places of employment which require attendance at weekends.

4.  Lessons learned from the collapse of Metronet and progress of the upgrade work subsequently?

  As we highlighted in previous submissions the structure of the Metronet PPP and its modes of operation were complex and in many cases did not deliver value for money for the taxpayer or the standard of service expected for the passenger. We believe that in the case of Metronet, now under the control of London Underground, there have been substantial changes in working and accounting practices since the takeover of Metronet that have produced substantial cost savings and increased overall efficiency.

The structure of the Tube Lines PPP shares much in common with the Metronet PPP, but the characteristics of the Tube Lines are fundamentally different in respect of their supply chains. The principal lessons of the Metronet collapse that are applicable directly to Tube Lines are:

    — a proactive management of PPP risk by the public sector; and

    — formal recourse to the PPP Arbiter in assessing costs.

5.  What contractual arrangements are appropriate for the future?

  London TravelWatch strongly advocates for the contractual arrangements which balance the least disruption and greatest benefits to passengers. In the shorter term changing the contractual arrangements are likely to result in disruption which would not be in the interests of passengers. In the longer term consideration should be given as to whether PPP is the best means to deliver infrastructure maintenance and enhancements to London Underground's network. The collapse of Metronet has illustrated the complexity and costs incurred when PPP structures are not successful. It also illustrates that in reality it is challenging to achieve genuine risk transferral.

As an example of the high costs of PPP/PFI projects, the Intercity Express Project incurred £14.95 million of consultancy fees[12] up to March 2009. The complexity of the PPP/PFI structure and the tendency to develop bespoke structures for each deal means that the advisory costs to the public sector are high. These costs have to be recovered by private sector efficiencies. The reality of the efficiency gains are hard to establish given that the life time of a typical PPP of 30 years.

6.  What risks are associated with the PPP arrangements with Tube Lines?

  The principal risks associated with the PPP arrangements with Tube Lines for passengers are programme overruns. As an example London Underground informed London TravelWatch of additional closures of the Jubilee Line on the weekend of 26 to 27 September and 3 to 4 October in order to allow Tube Lines more engineering access to meet their programmed deadlines for the Jubilee Line signalling upgrade. Line closures are disruptive to passengers at the best of times, but the unplanned closures were announced with minimal warning to passengers on 23 September three days prior to the first altered closure date. It would also appear from recent press statements that Tube Lines, despite additional line closures, is unlikely to be able to deliver the Jubilee upgrade on time.

There are also risks related to the continued disagreement between London Underground and Tube Lines over the restated terms. London TravelWatch urges both sides to come to an agreement over the Tube Lines PPP programme that is in the interest of passengers. This means ensuring that the full planned upgrades are carried out on time and at a cost which means that passengers are not penalised with higher fares.

7.  What impact is the current economic situation having on transport PPP and PFI schemes and what are the financial implications for other transport schemes?

  PPP/PFI is dependent on the availability of credit to the private sector in order to raise debt to finance projects. The impact of the current economic climate has been to reduce the availability of credit and to decrease the appetite for risk. Increased equity investment may also be required from PPP bidders by commercial lenders. For upcoming transport PPP/PFI deals in the UK transport market the consequences are to potentially reduce the number of bidders as well to increase the cost of finance. Bidders may also find it difficult to make definitive quotes for costs which are dependent on sub-contracts or supply chains. The result is that at the bid submission all bidders' offers are likely to be higher over the whole life costing to cover that risk and the cost of finance.

The UK is a mature PPP/PFI market with well established legal and contractual structures. Transport is one of the most long established sectors for PPP/PFI in the UK with historically the largest cumulative volume of deals. However, many of the factors effecting PPP/PFI are global because of the debt finance requirements and also because many of the bidders are global companies.

  The Treasury has set up the Treasury Infrastructure Finance Unit (TIFU) in an attempt to provide liquidity to this market both for upcoming projects and for existing providers. In the Treasury's view, "it is unlikely that private sector lending will be sufficient to deliver the scheduled pipeline of projects even taking account of increased lending activity by the EIB."[13] This action by the Treasury may address the immediate issue as a last resort, but the involvement of the Treasury in providing debt finance calls into question part of the logic of private sector involvement in public sector procurement.

  Historically Transport has made up the largest element of the PPP/PFI market in the UK. However, the volume of transport PPP/PFIs have reduced substantially and no deals took place in 2008. Of the current transport projects in procurement, the Intercity Express Project and Thameslink Rolling Stock Project both involve providing financing for the rolling stock to be procured. They are therefore considerably impacted by the economic conditions. It is notable that of a number of recent transport procurement projects (not all PPP/PFI related) that either planned bid submission dates have been delayed or bidders have been invited to revise certain assumptions. This suggests that the public sector is likely to have to shoulder a greater portion of the risk of PPP/PFI projects. Bidders' are likely to ask for greater guarantees and conditions which would reduce the overall risk transfer to the PPP provider. The value for money that is achieved by the public sector from PPP/PFI is therefore also likely to be reduced. This could lead to either greater cost to tax payers and the travelling public, or to a more limited scope of investment.

8.  What role has the Government played in these matters?

  Given the contractual structure between TfL and the Infrastructure Companies the direct involvement of the Government has not been significant. This is because the DfT had no direct controls over the risks associated with the PPP. The NAO report into Metronet identifies this key issue.

In the demise of Metronet, TfL has been left in the position of control over Metronet's former activities. The fixed grant settlement for TfL has not been revised in order to address this funding requirement going forwards. London TravelWatch urges Central Government to reconsider this position in order that passengers are not affected by:

    1. cost savings in the investment programme; and

    2. a rise in fares in order to recover additional expenditure costs.

9.  CONCLUSIONS

  London TravelWatch believes that the scale of the London Underground PPPs meant that they were always a challenging prospect to deliver. Whatever the rights or wrongs of the way in which it was carried out, it has attempted to tackle the historic problem that has faced London Underground and its passengers—namely the need for long term commitment to fund investment in the system. In common with other infrastructure operators LU's previous funding regime had been hampered by a stop-start cycle of capital funding governed by the fiscal requirements of the Government of the day.

London's transport users would be seriously disadvantaged if either the costs to LU of taking over the Metronet upgrade programme, or the current issues with Tube Lines restated terms, were to put in jeopardy the commitment to continuing investment that the PPP has sought to guarantee. We therefore urge that the interests of passengers are held as paramount in resolving the issues surrounding the restated terms and TfL's wider funding.

  From the collapse of Metronet, there are lessons that can be learnt about the performance of the PPP which could lead to benefits for passengers, and we await the Select Committee's conclusions with interest.

October 2009








11   Appendix A has not been reproduced as already in public domain. Back

12   Page 43, Modern Railways, August 2009. Back

13   http://www.hm-treasury.gov.uk/d/ppp_tifu_letter_050509.pdf Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010