Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Memorandum from Tube Lines (UPP 04)

OVERVIEW

  1.  Tube Lines is the infrastructure and asset management company responsible for maintaining and upgrading the Jubilee, Northern and Piccadilly lines, under a 30 year partnership with London Underground, which commenced on 31 December 2002.

2.  Tube Lines consistently learns from its experience of running the PPP Agreement that it has with London Underground (the "PPP Agreement"), as well as the broader experience of its members, and has where possible learnt the lessons arising from the Metronet collapse. That approach, and its particular structure and expertise, has enabled Tube Lines to carry out its obligations under the PPP Agreement in an economic and efficient manner, delivering improved safety and substantial enhancements to the efficiency and effectiveness of the lines for which it is responsible. Although the PPP Agreement could be improved in some respects, Tube Lines still considers that the PPP model is a robust one that can deliver real benefits for passengers and the taxpayer.

3.  Tube Lines believes that the PPP would work most effectively if there was greater recognition of the benefits brought by the partnership element as originally envisaged in the PPP. There is not always a clear understanding at all levels of London Underground of how to get the best out of the PPP. Tube Lines considers that this lack of understanding of the PPP arrangements and consequent lack of a partnership approach has made the PPP unnecessarily adversarial.

What lessons can be learned from the collapse of the London Underground PPP Agreement with Metronet?

  4.  On 5 June 2009, the National Audit Office published its report (the "NAO Report") on the failure of Metronet. The NAO Report suggests that a number of factors contributed to Metronet's failure.

5.  The main cause identified in the NAO Report was Metronet's poor corporate governance and leadership. Tube Lines agrees with this assessment, which echoes the Transport Select Committee's view that Metronet's structure "contributed to the inefficiencies of Metronet" (p 7, TSC, 25 January 2008).

  6.  The other principal causes identified in the NAO Report were as follows:

    (a) many decisions had to be agreed unanimously by Metronet's five shareholders;

    (b) Metronet guaranteed subcontracts for capital works to its shareholders, thereby creating a tied supply chain and so preventing Metronet from being able to act economically and efficiently;

    (c) Metronet's executive and management changed frequently and was unable to manage the work of its shareholder-dominated supply chain effectively; and

    (d) the poor quality of information available to Metronet's management, particularly on the unit costs of the station and track programmes, meant that Metronet was unable to monitor costs or have work performed economically and efficiently.

  7.  Tube Lines agrees that a structure where shareholders are tied suppliers cannot work. The NAO Report rightly criticised a corporate arrangement where the shareholders "adopted governance and management structures which gave power to the suppliers rather than the management of the business" (p 8, NAO Report). Future PPP arrangements with the characteristics of the PPP Agreement[14] should be brokered with the Metronet example in mind, along with the NAO Report's recommendation that "contracts should be awarded to bodies which have clear leadership, a credible corporate governance structure and an approach to securing suppliers which can be demonstrated to be value for money" (p 8, NAO Report).

  8.  The NAO Report also identified a number of issues specific to the PPP Agreement. These include the need for accurate, up-to-date reporting, the need to involve the PPP Arbiter more in the oversight of the whole upgrade programme, and London Underground's attitude to partnership as demonstrated by its working relationship with Metronet.

  9.  It is vital for the achievement of the PPP Agreement's objectives that all those involved in it follow clear, accurate, transparent, and relevant reporting procedures. This does not mean that there should be an increase in bureaucratic reporting, oversight, or control demands; rather, there should be better quality and more appropriately targeted reporting. It also means, as was recognised by the TSC, that there is a clear need for a reporting process that is "neutral and is designed to provide the information that both the Infracos and London Underground require to address performance issues" (p 19, TSC).

  10.  The role of the PPP Arbiter needs to be considered in light of the changes that have taken place within the PPP Agreement. The NAO Report clearly recommends that "effective independent scrutiny and evaluation of London Underground's management of major infrastructure projects, on behalf of both [Transport for London] and [the Department for Transport], could provide greater assurance on value for money" (p 8, NAO Report). The Arbiter could play a role in overseeing London Underground's operation of the lines previously run by Metronet, which is now the subject of no express scrutiny, as well as London Underground's role in relation to the lines run by Tube Lines, in addition to his current role.

  11.  We also agree with this Committee's recommendation that the Arbiter should "[report on] the effectiveness of London Underground as client during the modernisation of the Tube network" (p 35, TSC). The environment created by the PPP Agreement is unique, and requires extensive reporting and administrative burdens, not imposed on other asset management companies around the world. Tube Lines considers that the structure of London Underground makes the operation of these reporting and administrative burdens challenging. As was highlighted in the NAO Report, "both Tube Lines and Metronet found that London Underground's horizontal organisation, with several overlapping authorities, led to a number of different approaches being required". The NAO report refers to "90 individuals" identified within London Underground "who held authority in the scope approval process". The impact of this structure was then exacerbated by London Underground's behaviour: Metronet contended that London Underground's approach and behaviour contributed to the difficulties it found itself in, blaming "cost overruns on a wasteful approach to job specification by London Underground" (p 20, TSC).

Are these lessons being applied to the London Underground PPP Agreement with Tube Lines?

  12.  The lessons learned from the failure of Metronet are, as far as possible, being borne in mind in terms of the way in which Tube Lines operates. However, as set out below, there are limitations on the extent to which changes as a result of the lessons learned from Metronet are both required to be implemented by Tube Lines, due to the fundamental differences between the structure and characteristics of Metronet and Tube Lines, and are able to be implemented, due to the constraints that Tube Lines faces, as Metronet did, in relation to the nature of London Underground.

TUBE LINES' CORPORATE STRUCTURE AND PROCUREMENT

  13.  Tube Lines is not the same as Metronet. Tube Lines was set up with a very different corporate structure and, as such, its corporate governance structure and policies ensure that it is not impeded by the inflexibility that affected Metronet's day-to-day management or the impact that conflicts of interest between Metronet's shareholders had on preventing effective leadership. Unlike Metronet, Tube Lines has a number of independent members on its board, who are not tied to the consortium partners. This means that the board is able to, and does, make decisions in the best interests of Tube Lines, as it is obliged to do. Additionally, decisions by the board are required to be passed by a simple majority, rather than unanimously, unless the matter to which the decision relates was not included on the meeting agenda or it is a matter reserved for consideration by Tube Lines (Holding) Limited ("TLH"). Even where decisions are required to be made by TLH, there are conflict of interest provisions that effectively disenfranchise the shareholders in respect of decisions in relation to contracts with affiliates of the shareholders.

14.  Additionally, and by contrast to Metronet, Tube Lines' lenders play an additional governance role in that they ensure that Tube Lines' decision making on major issues is conducted properly. In this sense they provide an additional check. The Technical Adviser to the lenders is fully informed on all relevant matters and takes an active role in this process.

  15.  Tube Lines' corporate structure also ensures that the company's management has access to the information that it needs in order to run Tube Lines in an efficient manner. This is substantially because, while the Tube Lines Board retains overall responsibility for the running of Tube Lines, it is assisted by a number of committees, each made up of experts in the subject for which that committee has responsibility. The Tube Lines' board delegates to the committees the responsibility for conducting internal reviews and analysis of specified matters in order that they can then make recommendations to the Board. This structure ensures that decisions are taken at the appropriate level, on the basis of the necessary information, without the need for overly-onerous procedures in relation to decision making and approvals.

  16.  By contrast to Metronet, [during the course of the PPP Agreement, there has been a low turnover of Board members: indeed, since the start of the PPP in January 2003, Tube Lines has had a low turnover of board members and only two CEOs and two Chairmen, which has enabled stable and consistent management.

  17.  As emphasised in the NAO Report, there is a distinction to be drawn between the Metronet tied supply chain approach and Tube Lines' approach, which is described by the report as a "shopping around approach based on procuring goods and services through open competition". Tube Lines' operating model relies on a combination of internal resources and external subcontractors selected through competitive tendering to deliver the obligations under the PPP Agreement. Tube Lines has developed, and follows, a detailed procurement process to be used when resources are not available internally, or where to use such internal resources would not be the most appropriate way to proceed. The procurement process ensures that Tube Lines is able to establish and manage robust contractual relationships which meet the requirements under the PPP Agreement and deliver value for money.

  18.  As such, the lessons from Metronet's failure that arise out of Metronet's corporate structure and procurement arrangements do not need to be applied to the PPP Agreement with Tube Lines because they are not relevant to it.

LESSONS TO BE LEARNED BY LONDON UNDERGROUND

  19.  There are, however, other lessons from Metronet's failure that, based on our experience to date, are not being applied to the PPP Agreement but which should be. In particular, these lessons relate to the administrative burden created by, and the approach of, London Underground. Both of these factors were highlighted by Metronet as significantly contributing to the difficulties it faced and they continue to this day. Echoing the experience of Metronet, Tube Lines has found that London Underground continues to refuse to see the PPP Agreement for what it is; a fixed price contract for a fixed scope of work, with no general variation or change provision built into it. It remains the case that the lessons that should have been taken from London Underground's approach to the PPP agreement with Metronet have yet to be fully taken on board.

20.  London Underground has constantly sought to depart from the contractual structure established under the PPP Agreement. It has repeatedly sought changes to the scope and/or manner in which the works are carried out and has repeatedly departed from contractual procedures. In other words, the level of involvement and interference by London Underground gives rise to considerable additional time requirements and costs but it also undermines progress towards achieving the upgrade of the Jubilee, Northern and Piccadilly lines.

  21.  As was seen from Metronet's experience, London Underground has sought to expand the scope of work agreed in the PPP Agreement. It would appear that certain areas of London Underground have not understood how the PPP arrangements should work. Consequently they have repeatedly sought additional work to be carried out that falls outside the scope of the project and in some instances have made Tube Lines completion of tasks conditional on our acceptance of these out of scope works. Some examples of the approach taken by some parts of London Underground to the PPP Agreement include:

    (a) Requirements to change the "off the shelf" signalling system for the Jubilee line by adding bespoke elements unique to London Underground, led to a new bespoke system, after the PPP Agreement had been signed. Instead of using the proven "off the shelf" moving block system that is currently being used in Hong Kong as well as on the DLR and elsewhere around the world,, which had been selected in the original tendering process, these requirements meant that Tube Lines had to have the system significantly redesigned. This has resulted in a one-of-a-kind system, untried and untested on other metros, being installed on the Jubilee line. The introduction of new requirements has resulted in substantial additional complexity and therefore substantial additional work for the Jubilee and Northern line upgrades with a consequential increase in the original time frame and an increase in the costs.

    (b) Regular use of the standards process by some parts of London Underground to oblige Tube Lines to change, expand or alter works being carried out. An example is the use of standards to require Tube Lines to introduce features to improve mobility within stations. Over a period of time, London Underground introduced, changed and withdrew a number of standards and imposed requirements for additional double and lower handrails on stairways, contrasting stair treads highlighting and coloured bands on columns within stations. Although it was clear that the requirements for these features were in addition to the original scope of the work, London Underground insisted that they were required. Tube Lines referred the issue to an adjudicator who determined that Tube Lines was entitled to additional payment for these features. However by the time this decision was made significant time and resources had been lost on this particular piece of work.

    (c) Station supervisors regularly prevented Tube Lines from gaining access to which they were entitled, resulting in successful claims for over £12 million. They have also made unreasonable demands in return for access. For example, Tube Lines' workers were denied the use of the station's car park to facilitate upgrade work being carried out at the station. The station manager only agreed to the use of the car park on the condition that Tube Lines provided:

(i)an air conditioning unit and blinds to his office;

(ii)new double gates to the main car park entrance; and

(iii)two posts in the car part to prevent cars reversing into the wall mounted air conditioning unit.

    Since Tube Lines could not undertake the work at the station without a place to receive delivery of materials it had little choice but to give in to these out-of-scope demands.

  22.  These are just a few examples of approach taken in parts of London Underground, which has not significantly changed since the collapse of Metronet. This does not mean the PPP Agreement cannot work; despite these instances, which do make it more difficult for Tube Lines to meet its contractual obligations on time and within budget, it is still delivering its commitments at a lower cost than Metronet (see attached tables).

How has the upgrade work progressed since the demise of Metronet?

  23.  Since the demise of Metronet, Tube Lines has continued to make significant progress on upgrade work, such as track refurbishment, station refurbishment, escalators, lifts, signalling, train performance and fleet reliability. However, London Underground has repeatedly required Tube Lines to carry out additional upgrade work beyond the scope of the PPP Agreement, prevented Tube Lines from carrying out works according to its plans, and hindered Tube Lines from executing the delivery of work which it is contractually obliged to do. Tube Lines believes that there are a number of London Underground issues in terms of their role which are detrimental in relation to upgrade work, including their approach to granting necessary closures, their requirement for bespoke software system features, and the difficulties encountered by Tube Lines in working with London Underground operational and assurance procedures, all of which have significantly extended the time that projects take, as well as the costs involved.

ACHIEVEMENTS TO DATE

  24.  Since the start of the PPP Agreement, Tube Lines has completed the upgrade and refurbishment of 72 of the 96 stations along the Jubilee, Northern and Piccadilly lines it is responsible for under the PPP Agreement. 13 stations are currently being worked on with work on the remaining 11 due to start later this year. Tube Lines has completed 76 lift and escalator refurbishments across the three lines. Seven refurbishments have been done on the Jubilee line. 31 have been completed on the Northern line and 15 on the Piccadilly line. A further 23 have been undertaken at three stations which straddle more than one of the three lines. Step-free access work has been completed at nine stations and is currently underway at a further four stations. During this time Tube Lines has been able to further improve its safety injury rate from 1.40 in 2003 to 0.04 in 2009.

25.  These achievements also, however, involved material additional expense as a result of London Underground's having increased the scope of the works that it required and changing the way in which it required Tube Lines to carry out the work, in spite of the fact that the PPP Agreement contained a fixed scope of works albeit one that was loosely defined, thereby allowing London Underground to add additional requirements, at a cost, once it had been agreed. In addition, London Underground hindered Tube Lines' ability to carry out the works required by the stations programme by failing to comply with its own obligations under the PPP Agreement.

  26.  Despite the Northern Line being in a worse state than anticipated at transfer, Tube Lines has replaced track, upgraded stations and signalling, used predictive maintenance techniques, improved train management systems and overhauled train doors. These changes have resulted in a 49% reduction in delays caused by infrastructure, a 10% increase in customer satisfaction levels and enabled the line to operate 98% of its 12 million scheduled kilometres annually as opposed to less than 90% when the line was at its worst. London Underground worked closely with Tube Lines on this improvement, in particular, implementing improvements to the timetable. This is a really good example of what can be achieved when both parties work in partnership as the PPP Contract envisaged.

  27.  Since the demise of Metronet, Tube Lines has continue to focus its efforts on delivering its work on time and within budget, with a particular emphasis on completing the Jubilee line upgrade and leveraging the experience gained on that project to start the Northern line upgrade. Significant progress has been made on the Jubilee line. Although Tube Lines will now not meet the 31 December 2009 deadline to deliver the project, the level of progress that has been achieved to date is such that the overrun in the project will be limited in time and the costs of any delay will be carried by Tube Lines and not passed to the taxpayer.

  28.  The upgrade work on the Jubilee line has been carefully planned with a need for it to be carried out in a particular order over the life of the project. To facilitate this Tube Lines has asked for a total of 118 partial or whole line closures since 2002. Although Tube Lines was granted 113 closures, only half of these were at the times and locations we asked for and needed to carry out the work according to plan. While it was possible to undertake work during the closures we were given, it was not possible to do the work according to the long-term plan with the resulting need to reorganise, reschedule and review at short notice, which has not allowed us work as efficiently or effectively as we can.

  29.  It is difficult to tell how this upgrade work compares to work being undertaken on the Metronet parts of the network. While Tube Lines' reporting and information provision (both to London Underground and to the Arbiter) on the projects is clear, no comparable, independently-verified, evidence is available showing the progress that London Underground is making on the lines it now has responsibility for. Tube Lines considers that such information should be made available.

  30.  Tube Lines' and its costs have been independently benchmarked and are costs across the board have been demonstrated to be between 20-50% less than Metronet's during 2008-09 when it was under the direct control of London Underground. (charts are included as appendices).

What contractual arrangements are appropriate for the future?

  31.  One of the primary purposes of a PPP arrangement is the injection of private sector due diligence, management and risk management. Treasury studies have shown that, while there are inevitably some exceptions, such as Metronet, the vast majority of such projects perform better than traditional government procurement in terms of on-time and on-budget delivery. In essence, the PPP model is a robust and flexible one, which, when run effectively, continues to be an efficient approach to delivering the much needed upgrade to the network.

32.  Under the PPP Agreement, Tube Lines is obliged to meet particular service output targets (including journey time capability and service consistency and service control) and in doing so upgrade and enhance the network to make sure that these key targets are met. In order for the PPP Agreement to operate as effectively as possible, it is also necessary for London Underground to adopt an approach that is consistent with the scheme of the PPP Agreement and its output-based nature under which Tube Lines' obligations are based on output targets which give flexibility for Tube Lines to determine the methods of achieving those targets, subject only to overriding criteria governing safety. Such a scheme, in combination with Tube Lines' structure of independent management and no tied supply chain, gives rise to the economic and efficient day-to-day performance of the company.

  33.  The NAO report clearly states that Tube Lines' project management has delivered results. Appendix Five, section C. which compares Metronet and Tube Lines' differing approaches to addressing problems clearly shows that Tube Lines' strong stand enforcing its interpretation of the contract and its proactive approach to project management and to reducing the complexity of its own organisation, has improved efficiency and output and resulted in an operation that it is better placed to deliver results. This Committee also recognised this fact, stating that Tube Lines "provides an example of private sector innovation and efficiency".

  34.  While the PPP Agreement is not perfect, Tube Lines' delivery under it demonstrates that it can offer an example of a contractual arrangement that can deliver what is contractually required on time, to budget and to the quality levels one would expect if given real and meaningful support by London Underground.

  35.  Tube Lines believes that an alternative model for the management of risk is possible which would benefit all parties including London Underground and the taxpayer and it has, therefore proposed an alternative approach to the PPP Arbiter and to London Underground.

What risks, if any, are associated with the PPP Agreement with Tube Lines?

  36.  We believe that the PPP agreement is robust and is delivering a good value service for London. This is because of a robust corporate governance structure and management of risk. Greater acceptance of the structure of the PPP and wider take adoption of the approach taken on the Northern line would only enhance this.

What impact is the current economic situation having on transport PPP and PFI schemes and what are the financial implications for other transport schemes?

37.  Current financial market conditions have deteriorated significantly since the summer of 2007. There are few transactions that have closed in the last year that can be considered appropriate for comparative purposes. However, financing costs even for simpler and smaller PPP projects than represented by Tube Lines are significantly higher than the levels that applied at the time of either Tube Lines' initial financing in 2002 or its refinancing in 2004.

38.  In the current financial market, the complexity that was introduced in the 2004 refinancing, combined with the general complexity of the PPP Agreement itself, would result in a "complexity premium" as it would be likely to deter investors who would not be willing to spend the time required to understand the project and the financing structure.

  39.  Therefore, any financing raised in the current market would be likely to be substantially more expensive than the existing financing that Tube Lines has in place.

October 2009

BENCHMARKED COST COMPARISON CHARTS TUBE LINES AND METRONET 2008-09






14   There are numerous "PFI model DBFO" PPPs for (say) a single site hospital project, where the fixed supply chain model works very well. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010