Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Memorandum from the National Union of Rail, Maritime and Transport Workers (RMT) (UPP 05)

  The National Union of Rail, Maritime and Transport Workers (RMT) welcome the opportunity to respond to the Transport Select Committee inquiry: Update on the London Underground and the Public Private Partnership (PPP) agreements. The RMT is the largest of the unions on the London Underground; our opposition to the PPP is well documented.

The PPP lurches from crisis to crisis, as report after report is published highlighting the structural and operational problems with the scheme. Without exception all of the reports and their recommendations are ignored by Government Ministers who continue to blithely insist, in the best Panglossian fashion, that all will be for the best, in the best of all possible worlds.

  In all the discussions about the PPP, it is often forgotten that London Underground's (LU) infrastructure is groaning under the weight of record passenger numbers and is in desperate need of renovation. Despite recent falls in ridership due to the recession, London's population will increase by around 500,000 over the next decade. Many of these people will use the Tube. In addition the 2012 Olympic and Parlaympic Games will place the network under huge strain.

  It is therefore essential that the right lessons are learnt from the disastrous PPP experiment and a competent public sector structure put in place to provide the basis for clear lines of management accountability, effective strategic planning and sustained investment streams to deliver the necessary upgrade of the infrastructure. As part of the process by which engineering functions are returned to the public sector, RMT believes that Transport for London should create a major works department that could be utilised in their subsidiary organisations including London Underground, London Overground and work on the Crossrail project.

LESSONS OF THE METRONET COLLAPSE, THE FAILURE OF PRIVATE SECTOR INVOLVEMENT AND THE JUBILEE LINE

  In the summer of 2008, Metronet collapsed under the weight of its own inefficiency. At that time PPP defenders rushed to explain the scheme was still structurally sound. Metronet was simply an inefficiently run organisation with an inappropriate governance structure and Tube Lines performance vindicated the sell-off of engineering functions to the private sector. Giving verbal evidence to your committee in the wake of Metronet entering administration, the then Secretary of State for Transport, Ruth Kelly, said she believed that the PPP structure could deliver value for money.[15]

However, RMT believes that experiences both before and after the introduction of the PPP brings into serious question the assertion made by the Secretary of State. The current mess on the Jubilee Line illustrates our view.

  In the late 1990s, PPP supporters argued that the cost overruns experienced in the Jubilee Line Extension (JLE) project confirmed the inherent failures of public sector project management and provided the rationale for outsourcing the Underground's engineering functions. In fact, RMT believes the difficulties the project ran into indicates precisely the opposite and demonstrates the financial and operational failings the private sector has caused on the London Underground over the past decade or so.

  The signalling contractor working on the extension, convinced London Underground Limited (LUL) management to install a technologically unproven, `moving block' signalling system onto the Jubilee Line. When it became apparent to the contractor that the moving block system would not work and would therefore have to be abandoned, they delayed telling LUL of the engineering problems the project had encountered. The failure of the private contractor was confirmed by the then Deputy Prime Minister (DPM), John Prescott, who explained to the House of Commons on 20 March 1998 "... but, to be fair, London Transport was not to blame for the failure in the signalling system; it was the fault of a private company that did not live up to its contract to produce on time".

  Bizarrely, the DPM identified the failure of the private contractor to fulfil its obligations during the same Commons debate in which he launched the Public Private Partnership. RMT maintains the failure of the signalling contractor should have alerted the Government, at that time, to the potential dangers of wider private sector involvement in London Underground's engineering functions. That the Government failed to learn the appropriate lesson has led to the waste of billions of pounds in public money and delayed work to upgrade the infrastructure.

  Work to resolve the signalling problems caused by the abandonment of the moving block system is now being undertaken by Tube Lines. However, the project is not progressing at all well and once again indicates to the RMT that lessons that should have been learnt after the collapse of Metronet, are simply not being taken on board. Indeed, the recently published 2008-09 Transport for London (TfL) document London Underground and the PPP explains:

    "Over the past year the work has advanced and the scale of disruption to customers at weekends has expanded significantly, but progress has been slower than planned. This is evident in the growing requests for additional weekend closures that resulted, in April, with a separate Jubilee Closures Agreement, that provided 12 additional weekends at short notice. This hunger for more closures has stretched stakeholder and customer patience to breaking point, and it is vital that Tube Lines meet their commitment to deliver the upgrade by 31 December 2009. Their reputation—and that of their shareholder Bechtel who is delivering this project—hinges on meeting this commitment".

  To the RMT these comments are all too reminiscent of TfL remarks made in their annual 2005-06 review of the PPP with regard to the upgrade of the Waterloo and City Line. TfL explained at that time "The current closure of the Waterloo & City line for works connected with the upgrade is an acid test of Metronet's capability to manage major projects".

  As the Committee will know the Waterloo and City Line upgrade re-opened over a week late, exposing Metronet to fines for the late completion of works. The line was subsequently closed twice following the late completion of works due to dust and dirt caused by on-going engineering works which led to train operators experiencing visibility problems.

  For the Jubilee Line, RMT understands that the first phase of the current work will not be completed until March 2010 with the whole project overrunning to Quarter 2 of next year. One impact of the delay will be that LUL will have to pay penalties to the Canary Wharf Group caused by the failure of the private contractor to deliver the work on time. No doubt, there will be clauses in the PPP contracts enabling LUL to claw back the money from Tube Lines. However, at the same time as this contractual absurdity is being played out, RMT also understands that Tube Lines has submitted a multi-million pound claim against LUL for "additional works" that were not specified in the original contract. This is precisely what happened with Metronet who claimed that their cost overruns were in part the result of non-contract specified, additional works, LUL had instructed them to carry out.

  In the past week, London Underground (LU) seems to have finally lost patience with Tube Lines. Exasperated by the overrun of works on the Jubilee Line acting managing director, Richard Parry has called into question "everything about the PPP" and made a referral to the PPP in an attempt to resolve the on-going dispute over the Tube Lines funding settlement for the next 7½ year PPP period. Given both the experience with Metronet and the evident problems on the Jubilee Line we are extremely concerned that it has taken London Underground so long to act.

  The referral further highlights one of the many problems with the PPP. The scheme's contracts are rightly known as being both extremely complex and shrouded in commercial confidentiality. In our view, complex, multi-billion pound contracts should be subject to the widest possible public scrutiny. RMT therefore shares the view of your Committee's January 2008 report: the London Underground and the Public Private Partnership Agreements that a mechanism should have been put in place, by amending the Greater London Authority Act 1999 if necessary, to allow the PPP Arbiter to report annually on Infraco performance whether or not one of the parties had called on him to do so. Government should have taken this step in the immediate wake of Metronet's administration; their failure to do so has made public scrutiny and discussion about Tube Lines performance, in the run up to TfL's referral, more difficult than should have been the case.

  Additionally, the structurally flawed nature of the PPP contracts causes unnecessary operational tensions and confusion between LU and the remaining private Infraco. One example is that of a new signalling standard that Tube Lines will not recognise because it was not the standard applied at the time the contracts were signed off. For the Infraco to hold this position is utterly bizarre. The PPP was designed to last for 30 years. During that time virtually every operational and technical standard is likely to be subject to change. Tube Lines' strict formal adherence to what was originally written down indicates to the RMT that they are more interested in providing technical solutions to meet financially beneficial capacity, accessibility and ambience targets rather than being committed to running an underground network.

THE TRANSFER OF RISK AND THE IMPACT ON THE UPGRADE OF THE INFRASTRUCTURE

  We have consistently made the point that the transfer of revenue risk to the private sector on both the national rail network and the London Underground is wholly inadequate. That the public purse was left to pick up 95% of Metronet debt is unacceptable and brings the London Underground Limited (LUL) management team responsible for signing off the contracts into disrepute. We are extremely concerned that the public purse could also be exposed to Tube Lines debt should they abandon, for whatever reason, their PPP contracts.

The effects of the 95% clause are already being felt on the ex-Metronet contracts. LUL is struggling with the debt inherited from administration and is therefore seeking to reduce costs. In June 2009, RMT revealed that maintenance work on the ex-Metronet lines was being cut by around £60 million, made up of £26.2 million in track and signal work, £18.9 million from fleet and trains and £18.5 million from the station upgrade budget.[16] The result of Metronet's failure is that the travelling public and the public purse is being forced to pay twice; firstly by having to pick the huge debt and secondly by facing cuts to vital upgrade work owing to budgetary constraints caused by the debt inheritance.

EFFECTS OF THE RECESSION ON OTHER TRANSPORT SCHEMES

  RMT warmly welcomed the Government announcement to electrify the Great Western Main Line. Contained within the announcement was the good news that the Crossrail project would proceed as planned. There had been speculation that funding for the scheme was becoming problematic and that a future Conservative administration might scrap the scheme altogether. Funding now appears to be more secure given the announcement in late September that the Mayor of London has secured a £1billion loan from the European Investment Bank to pay for the scheme. RMT supports the Crossrail project and believes once it begins operations, passenger services should be run in the public sector. We have already mentioned in this submission the creation by Transport for London of a major works department to work on schemes such as Crossrail.

September 2009 saw stations from the South Central franchise transfer to Transport for London as part of the East London Line extension project. The ELL will re-open next June. In order to complete the orbital London Overground network we are keen to see work begin on Phase 2 of the project at the earliest possible time.

THE ROLE OF GOVERNMENT

  Government has not played a positive role during the history of the PPP. Ignoring the opposition of the rail unions, the then mayor of London, your committee and the vast majority of passengers, it pressed ahead with the scheme; a decision that has proved to be disastrous. The best course of action the Government can now take is to bring forward legislation at the earliest possible time to return all privatised services, including out-sourced cleaning services, back under London Underground control. Such a move would restore a clear line of management accountability, enable strategic planning across the whole network and provide the basis for sustained investment to deliver the necessary upgrade of the infrastructure.

CONCLUSION

  As stated above a number of independent reports have emphasised the failings of the Public Private Partnership. Sadly these have not been heeded by Government and the taxpayer has been forced to account for 95% of the cost of the failure of Metronet to fulfil its obligations under the PPP contract. This has resulted in important maintenance work being cut back which ultimately will see a deterioration in service at the expense of ordinary passengers.

It is of real concern that similar problems with the upgrade of infrastructure have started to occur with Tubelines in respect of the Jubilee Line. The difficulties being experienced with Tubelines, and in particular Tubelines insistence that work in the next funding period will cost far more than London Underground consider reasonable, has resulted in London Underground losing patience and making a referral to the PPP Arbiter over funding.

  This is not a sound basis for moving forward with the essential upgrade of the infrastructure, especially with the numbers of people using the tube expected to grow significantly in the next 10 years. RMT believe that the upgrade of the infrastructure should be returned to London Underground and public control and accountability. As we have demonstrated this will be the most cost effective solution and will end any further contractual disputes with Tubelines, and the consequent waste of resources that this involves.

October 2009







15   Ruth Kelly verbal evidence to Transport Select Committee 7 November 2007. Back

16   RMT press release 17 June 2009. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010