Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Memorandum from Transport for London (TfL) (UPP 06)

1.  INTRODUCTION

  1.1  Transport for London (TfL) welcomes the opportunity to comment on the Committee's update inquiry into the London Underground Public Private Partnership (PPP). Our response provides an update on performance of the PPP and significant developments since the submission of TfL's evidence to the Committee's previous inquiry in 2007.

2.  BACKGROUND

  2.1  TfL was created in 2000 as the integrated body responsible for the Capital's transport system. The primary role of TfL, which is a functional body of the Greater London Authority, is to implement the Mayor of London's Transport Strategy and manage transport services across the Capital. London Underground (LU) became part of TfL in 2003 and is responsible for operating the LU rail network. It serves 270 stations and operates services on 11 lines. Up to four million passenger journeys are made on the network on the busiest days.

2.2  Metronet was previously responsible for the maintenance and upgrading of eight of LU's 11 lines under two of the original three PPP contracts, for the BCV (Bakerloo, Central, Victoria, and Waterloo & City lines) and SSL ("sub-surface" or Circle, District, Hammersmith & City and Metropolitan lines) infracos. After Metronet collapsed and entered PPP Administration in July 2007, TfL emerged as the only bidder for the two Metronet companies, and they transferred to TfL ownership in May 2008. Subsequently all former Metronet staff transferred to LU in December 2008. An organisational review of central support functions across LU, designed to eliminate duplication and deliver the most efficient structure, was then carried out, and a new integrated LU structure was put in place with around 1,000 jobs removed.

  2.3  Tube Lines remains responsible for the maintenance and upgrading of the JNP (Jubilee, Northern and Piccadilly) lines under its PPP Contract. The first Periodic Review of this contract is currently in progress (see section 4 below).

  2.4  2008-09 was LU's best ever year in terms of operational performance and customer satisfaction ratings, despite also carrying more passengers than ever before—nearly 1.1 billion during the year, almost as many as the entire National Rail network. A table summarising operational performance in the past six years is at Appendix 1.

  2.5  The current economic downturn has since led to a reduction in ridership (around 5-6% so far this financial year) which has had an impact on LU's revenue. Overall, however, passenger numbers still remain higher than they were five years ago and demand is forecast to continue to grow by around 25% over the next 10 years or so. Delivery of the current investment programme, the largest seen on the Tube in decades, therefore remains essential, in order to deliver the capacity and reliability improvements needed to accommodate this growth. The line upgrades that are at the core of this investment programme will deliver approximately 30% more peak capacity by 2020.

  2.6  Given the constraints on funding that have resulted from reduced revenue and the financial legacy of Metronet (see section 3) it is also imperative that this investment is delivered efficiently and economically, providing fare payers and tax payers with the best possible value for money.

3.  THE COLLAPSE OF METRONET

  3.1  TfL's submission to the Committee's previous inquiry was made while Metronet was still in Administration, but even at that time it was possible to identify the root causes of its failure, which were a fatal flaw in Metronet's structure and its contracting strategy, which committed it to using its own shareholder companies.

3.2  The National Audit Office (NAO) report on the failure of Metronet, published in June 2009, confirmed TfL's long held view that Metronet's failure was the result of the failure of its management team and shareholders to properly plan, manage and execute its work. The NAO report also noted that Metronet was effectively managed by LU once it entered administration.

  3.3  Since Metronet transferred to TfL and was integrated into LU, maintenance performance has improved and good progress has been made with the two major line upgrades currently in progress on the ex-Metronet lines—the Victoria line upgrade (VLU) and the upgrade of the sub-surface lines (SSL upgrade).

  3.4  On the BCV lines in 2008-09, overall Availability—the key measure of day to day asset reliability under the PPP contracts—was 27% better than the contractual benchmark, with a 30% reduction in the total number of Lost Customer Hours (LCH)[17] compared to 2007-08. Further evidence of the turnaround in BCV performance since the administration is a 21% decline in the average number of LCH per period.

  3.5  On the SSL lines in 2008-09, overall Availability was 35% better than the contractual benchmark and 36% better than in 2003-04. Under LU's stewardship the SSL has continued the positive trend that started in 2006-07, with a 16% reduction in LCH since 2007-08. The average number of Lost Customer Hours per period was also 18% fewer post-administration. An example of the improvement in the delivery of maintenance and renewal works is that LU's recent delivery of ballasted track renewal works on the District line has set new records for the amount of track being replaced during a weekend possession—on 12-13 September 2009, 812 metres of track were replaced, more than has ever been achieved before.

  3.6  Additionally, both the VLU and the SSL upgrade are progressing well—the first of the Victoria line's new trains is now running in service, having done so for the first time in July 2009, while the first of the new "S-stock" air-conditioned trains for the sub surface lines is currently in the final stages of testing at LU's test track at Old Dalby and is due to be delivered to London in October 2009. LU has also initiated the tender process for the vital new signalling system on the sub-surface lines, adopting a fresh approach to the procurement process that seeks to utilise the knowledge of the supply market to deliver the best possible value for money. This will offer savings of hundreds of millions of pounds compared to the contract that previously existed prior to Metronet's collapse and which was terminated prior to transfer to TfL.

  3.7  LU has also had to deal with the financial legacy of Metronet's collapse—the result of poor programme management and system integration, ineffective cost control, a lack of forward planning and inefficient fiscal management. Although initial estimates from the NAO report put the loss to the taxpayer of Metronet's failure at between £170 million and £410 million, this does not take into account work left undone by Metronet which LU has addressed since transfer or which still needs to be completed by LU in the future.

  3.8  Through rigorous review of the Metronet businesses, LU has been able, through renegotiation of contracts, improved procurement, operational efficiencies and a revised work programme, to remove approximately £2.5 billion of projected costs from the budget to 2018, compared with the costs that Metronet would have incurred.[18] As part of this, LU is currently making further savings in maintenance operations designed to deliver £60 million of efficiencies per year, on top of the savings made as a result of the organisational review mentioned in paragraph 2.2 above.

  3.9  After Metronet exited from Administration, TfL worked closely with the Government under the auspices of the Joint Steering Committee (JSC) which was set up to examine and make recommendations on options for a long term structure to deliver Metronet's former contractual obligations. The JSC's report is currently the subject of discussions between the Secretary of State for Transport and the Mayor of London.

  3.10  A more detailed analysis of all these issues is contained in LU's PPP Report 2007-08 and PPP & Performance Report 2008-09, both of which are available on TfL's website at www.tfl.gov.uk/pppreport. LU remains committed to regular and transparent reporting of performance and has recently commenced publication, at the same website address, of a four-weekly digest of performance data that complements the annual reports. Other material is also presented publicly to the TfL Board.

4.  TUBE LINES AND PERIODIC REVIEW

  4.1  TfL's previous submission in 2007 noted some of the achievements of Tube Lines' renewal programmes at that time, and it has continued to show some success since then, particularly in its stations programme which is on course to deliver, by the end of the first contract period next year, modernisation or refurbishment of all its stations as envisaged in the contract. It has also showed more consistency in day to day maintenance performance, and has turned around the performance of the Northern line after early difficulties, although the intrusive upgrade programme on the Jubilee line is reflected in a decline in Availability scores on the line in the past two years.

4.2  It is, however, in the delivery of that upgrade of the Jubilee line that Tube Lines faces its biggest challenge. Currently, it is failing to meet that challenge. This is the first of the major line upgrades, and will deliver a 33% increase in capacity as a result of the installation of a new signalling system. TfL has recently expressed its grave doubts about Tube Lines' ability to deliver the upgrade by the contracted date of 31 December 2009. Tube Lines Chief Executive has also indicated that "we don't think we will quite get there in December". At time of writing, the outcome of the independent review of Tube Lines' programme (which they agreed to undertake after being urged to do so by LU) is urgently awaited, but it seems likely to indicate not only that delivery will be delayed, but also that more weekend closures will be needed.

  4.3  Tube Lines' lack of progress is particularly disappointing given the extent of closures that have been necessary—part of the line has been closed on every weekend in 2009 and the number of closures has been significantly more than the number originally planned for at the start of Tube Lines' programme. These closures are causing considerable disruption to passengers and to businesses who depend upon the line.

  4.4  The first Periodic Review of Tube Lines' 30 year contract is currently in progress. This will determine the scope and the price of Tube Lines' work programme for the second 7½ year contract period commencing in July 2010.

  4.5  In 2008 LU requested initial Guidance from the PPP Arbiter as to the likely cost of the works for the second period based on the original PPP contract terms. The PPP Arbiter's Guidance issued in September 2008 (and therefore in 2008 prices) estimated that the total funding required in the second period should be in the range £5.1 billion to £5.5 billion compared with Tube Lines' estimate of £7.2 billion and LU's estimate of £4.1 billion.

  4.6  LU broadly accepted the PPP Arbiter's Guidance and then, in finalising its Restated Contract Terms, made a number of further adjustments to reduce the costs of the second period whilst ensuring that the full upgrade programme can be delivered. The re-stated terms did not therefore substantially change the work to deliver major increases in capacity and reliability through new trains and new signalling. However, projected costs have been reduced significantly by LU by, for example, proposing station refurbishment broadly every 10 years as opposed to the seven and a half year cycle in the current contract. The restated terms also reflected changes that had occurred in the economic situation since the request for Guidance.

  4.7  LU's revised evaluation of costs was £4.2 billion. This is not directly comparable to the previous valuation of £4.1 billion—it is coincidence that, after the process of making revisions to scope, and other adjustments as described above, these figures are similar.

  4.8  LU issued its Restated Contract Terms to Tube Lines in December 2008. Tube Lines responded to the restated terms in June 2009 but its price was significantly in excess of LU's evaluation and also still much higher than the price indicated by the PPP Arbiter in his initial guidance last year, which Tube Lines appears not to have taken into account.

  4.9  Since receipt of Tube Lines' response, LU and Tube Lines have made someprogress in determining the future work programme and in reducing some costs accordingly. However, Tube Lines' costs still remain unacceptably high in some areas and LU therefore referred the issue to the PPP Arbiter on 23 September 2009, asking him to set a fair price for the works. LU intends to continue its constructive discussions with Tube Lines, alongside the PPP Arbiter process. It is anticipated that the Arbiter will publish his draft conclusion on second period costs in December 2009.

  4.10  Tube Lines has also produced an "alternative proposal", outside of the Periodic Review process.

  4.11  This alternative proposal, currently only at a very outline stage, has been reported as offering a price of around £4.3 billion. However, it is important to make clear that this figure is not directly comparable to LU's evaluation of £4.2 billion. Tube Lines' proposal excludes some very significant elements of the work programme for the second contract period, yet still remains above LU's view of the costs. It also specifically removes the requirement for Tube Lines to remain "economic and efficient" in that LU would become liable for bearing the larger proportion of cost overruns on Tube Lines' programme, however these were incurred. In effect the proposal seeks to re-engineer the PPP structure which would create significant legal and practical issues. Even if these could be resolved, such fundamental changes would be likely to take significant time and resource to implement.

  4.12  Although LU will actively engage with Tube Lines on this, and on any other proposals that may reduce costs, LU's priority is to see that Tube Lines delivers all the improvements it has promised on time, and that it offers a fair price for the scope of works that LU has specified for the second contract period, such that it delivers value for money for fare payers and taxpayers.

5.  CONCLUSIONS

  5.1  Metronet's failure was largely the result of its own inefficiency rather than a consequence of the PPP structure. However, the legacy of Metronet's collapse, and the improved performance delivered since its activities were integrated into LU, has inevitably raised questions about whether an alternative model may be more effective at delivering the improvements and, crucially, may offer greater efficiency and value for money than the PPP was able to deliver.

5.2  As the one remaining PPP contractor, it is on Tube Lines' shoulders that the case for the PPP model now rests. If the case is to be made, then Tube Lines must resolve the delays to the Jubilee line upgrade and complete that work promptly; and deliver a proposition with costs that offer value for money for the second contract period.

  5.3  TfL's objectives in relation to the former Metronet activities now under LU's control are reliable day-to-day performance and efficient delivery of the upgrade works, in order that the service and future capacity that London depends upon is achieved for the best possible value for money. LU has so far demonstrated it has the capability to achieve that, and it is committed to continue to ensure that its activities are transparent and open to scrutiny so that its ongoing performance in this respect can be assessed.

APPENDIX 1

LU OPERATIONAL PERFORMANCE 2008-09
2008-09 2007-082006-072005-06 2004-052003-04
Passenger journeysmillions 1,0891,0731,014 971976948
Kilometres operatedmillions 70.670.569.8 68.869.467.7
Percentage of schedule% 96.494.894.5 93.695.393.1
Excess journey timeminutes 6.67.88.1 7.57.27.4
Customer satisfactionscore 797776 787876


October 2009




http://www.tfl.gov.uk/assets/downloads/corporate/Item08-_Metronet-Integration-Budget-Implications.pdf


17   Lost Customer Hours (LCH): The total additional journey time measured in hours, applying Nominal Accumulated Customer Hours (NACHS), experienced by Customers using the Underground Network as a result of Service Disruptions. Back

18   More detail is available in the report considered by the TfL Board on 24 June 2009, and published on the TfL website at Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010