Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Supplementary memorandum from Transport for London (TfL) (UPP 06a)

  I am writing further to the evidence that Richard Parry and I gave to your Committee on 9 December 2009. In the light of subsequent events and evidence from other witnesses, I think it is important to clarify and expand on a number of issues.

1.  TUBE LINES' COSTS

  It was suggested by a number of other witnesses that Tube Lines' costs for maintenance and upgrade work are, and will continue to be, less than those of London Underground (LU). However, this is not substantiated by any objective analysis of the available information.

  As Richard Parry pointed out on 9 December, it is important to make meaningful comparisons, taking into account amongst other things the position inherited from Metronet and the nature and condition of the assets. I enclose a paper considered on 10 December 2009 by the TfL Board which sets out a more detailed analysis of this issue. You will note the conclusion that, notwithstanding the legacy of Metronet's inefficiencies, LU has subsequently achieved significant efficiencies and costs reductions, and that its projected costs going forward are comparable with or better than Tube Lines.

  The latter point is salient. Since your Committee met, the PPP Arbiter has published his Draft Directions on Tube Lines' costs for the second contract period. He effectively rejected Tube Lines' evaluation of the costs; his draft determination is that the economic and efficient price for improving the Tube over the seven and a half years from mid-2010 to 2017 should be £4.4 billion, rather than the £6.8 billion originally sought by Tube Lines, or the £5.75 billion they subsequently reduced their evaluation to.

  The Arbiter's determination is much closer to LU's evaluation of £4.0 billion.

  Clearly LU will be working with the relevant parties ahead of the Arbiter's confirmation of his directions in March 2010 in order to address any funding shortfall that remains at that time. However, I remain of the view that any additional cost to LU over and above its budgeted costs should be met by Government, who imposed the PPP structure on London, in order to ensure the vital improvements in Tube reliability and capacity promised by the PPP can be delivered in full.

2.  JUBILEE LINE UPGRADE

  The TfL Board also considered a PPP Update paper on 10 December 2009, which among other issues sets out the latest position on the Jubilee line upgrade. This is enclosed.

  You will see that the paper highlights the importance of Tube Lines setting out, and then adhering to, a credible programme for completion of the upgrade. We have agreed a further closure programme up to Easter 2010, which was published on 11 December—the press release is enclosed. However, Tube Lines require further closures beyond that, and have recently indicated that they will not complete the upgrade until October 2010.

  Tube Lines originally predicted a requirement for around 50 weekend closures to deliver the upgrade. To date, they have required around 120 weekend or part-weekend closures and have still been unable to complete the work. Repeatedly last year we were assured that granting a further 12, then a further six, closures was all that was needed. They have now confirmed they need 13 more weekends up to and including Easter and that this will still not be enough.

  Tube Lines also need to make clearer what the impact of the delay will be on the programme for the Northern line upgrade, which is intrinsically linked to that of the Jubilee line.

  The reasons for the delay to the Jubilee line upgrade are, I know, not the subject of this inquiry. However, I would re-iterate the point made by Richard Parry on 9 December, and echoed by Chris Bolt on 6 January, that the Bechtel secondment arrangements put in place by Tube Lines to manage delivery of the upgrade do not appear to have been effective in this instance.

  It was suggested by some of the witnesses that LU's own staff training needs could mean further delays to the Jubilee line upgrade delivery date and it was also suggested that LU's staff training programme was not satisfactory. I would like to place on the record that neither of these allegations has any substance. Training of staff has always been an integral part of the upgrade programme and was factored in to the original overall timetable for delivery. It is not the cause of any delay, nor is it the principal reason for further closures in 2010. It is being carried out comprehensively for all staff, in accordance with industry best practice. LU will ensure that all of its staff receive appropriate training within Tube Lines' delivery timeframe, as was always envisaged when the PPP contracts were put in place.

3.  LU'S APPROACH TO THE CONTRACT

  It is false to suggest, as some have, that Tube Lines' inability to deliver on the Jubilee line upgrade and its inflated cost demands for the second period have anything to do with LU's behaviour as a client. The Arbiter made clear in his evidence to the Committee that he has, in some areas, taken the nature of the relationship between LU and Tube Lines into account. Yet the simple fact is that his draft direction has still rejected Tube Lines' view of what the costs for the second period should be.

  There were some specific allegations about access and scope made on 9 December. The bottom line on access is that LU has at all times complied with the access code in the contract, and indeed has gone beyond it—witness the recent granting of many weekend closures at short notice. The root of the problem has been that, despite having had more than double the number of closures they originally estimated they would need, Tube Lines is still not anywhere close to delivering on its obligations to upgrade the Jubilee line.

  Dean Finch also noted that the allegation that LU had sought to unilaterally vary the scope of some projects, particularly to provide step free access to stations, was not representative of the current situation. I am grateful for that, but in fact it is incorrect to state that LU has ever sought to "not pay" for work done. This is a misrepresentation of what are simply normal contractual negotiations around the scope of works, which would happen under any contract between a responsible public sector client and a private sector contractor. Taking step-free access as an example, obligations were set out in the contract and any work beyond that, such as the current lift construction at Kingsbury and Green Park, is paid for entirely separately as additional work.

4.  THE ROLE OF THE PPP ARBITER

  It was suggested on 9 December 2009 that we have rejected a suggestion that the Arbiter should have a stronger role, and indeed that Tube Lines are seeking this. Neither of those contentions is correct.

  Any contractual change to the Arbiter's remit, to encompass an annual review of Tube Lines' programme, would require Tube Lines' consent. It is arguable in any event whether an annual review would assist in identifying issues at a time when there is still a chance to rectify them. When the Arbiter was asked to give his Guidance last year on notional costs for the second contract period, it might reasonably have been expected that the information provided by Tube Lines about its costs for the second period would reveal the current position on the Jubilee line upgrade. It did not.

  On the issue of the Arbiter conducting "Periodic Reviews" of the BCV and SSR infracos in parallel with that of the Tube Lines contract, this is not something which either Tube Lines or the Arbiter has sought during the current process. In any event, it is not clear what the benefits of such an exercise would be. LU's costs are (unlike Tube Lines') published in four weekly reports—see www.tfl.gov.uk/pppreport—and crucially, subject to the same governance and scrutiny mechanisms that cover all of TfL's activities. Additionally, I have recently agreed with the Secretary of State that, going forward, there will be scrutiny of the whole TfL investment programme by a new panel of expert independent advisers—see http://www.tfl.gov.uk/assets/downloads/management-of-tfl-investment-programme.pdf for more details. This will give added assurance to me and to the Government.

  In the light of this, an academic and costly review process by the Arbiter is neither a necessary nor an efficient measure.

  In effect, the Arbiter already has wide information powers and preparatory powers that enable him to monitor and examine both Tube Lines' and LU's programmes—we undertake joint benchmarking and the Arbiter's reporters will be reviewing LU and Tube Lines data to assess it for accuracy and consistency.

  I hope this information is helpful and I look forward to reading the Committee's report.

January 2010





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010