Update on the London Underground and the public-private (PPP) partnership agreements - Transport Committee Contents


Memorandum from the Department for Transport (DfT) (UPP 07)

Q1.  What lessons can be learned from the collapse of the London Underground PPP Agreement with Metronet?

  The collapse of Metronet was a major disappointment for both farepayers and taxpayers. Some essential capacity enhancements and improvements in maintenance, promised through the PPP contract arrangements, will now be late in arriving on the ex-Metronet lines.

There are many lessons to be learned from Metronet's failure. But it would be wrong to conclude that one is that the concept of the PPP itself is flawed. The National Audit Office's June 2009 report "The failure of Metronet" was clear that the main cause of Metronet's failure was poor corporate governance and leadership rather than the PPP contract mechanism.

The interim Managing Director of London Underground Ltd (LUL), Richard Parry confirmed at the London Assembly Transport Committee on 3 September 2009 that Tube Lines has so far delivered largely to time and budget. It has done so by managing higher costs in some areas (stations) by securing efficiencies in others (escalators). Tube Lines continue to work closely with LUL within the contract structure to actively manage delivery challenges, such as the upgrade of the Jubilee line. Where key deadlines or outcomes fail to materialise, Tube Lines will bear the cost of this through reductions in Infrastructure Service Charge. Despite Metronet's failure, PPP contracts have the capacity to deliver when parties engage constructively within the contract framework.

  Furthermore, while the performance of Metronet was clearly unacceptable, its failings should be considered against the background of previous experiences of cost overruns and delivery slippage on the London Underground. The Jubilee line extension and Central line upgrade both presented the taxpayer with cost overruns of 30% and were significantly behind schedule, some six years in the case of the Central line upgrade. By comparison, and using the NAO's own methodology, the cost to the taxpayer generated by Metronet's failure lies somewhere in the range of 4-10% against the total value of the investment.

  The Department remains committed to a process of continuous review and improvement. Lessons learned from the establishment and implementation of the PPP and other PFI contracts have fed a continuous process of development in DfT and across Whitehall.

  Central standardised PFI contract terms are now mandated for departmental use. This has enhanced and systematised the rights of contracting bodies with regard to:

    — contract monitoring;

    — changes in project documents and financial arrangements;

    — maintenance and access to contractor's records—extending rights to access sub-contract details and information provided to Senior Lenders; and

    — managing contractor distress.

  The application of these lessons to the recent M25 Widening PFI translate into:

    — a Secretary of State right to appoint an observer to the DBFO Co (decision making) Board and therefore has the ability to monitor the financial performance of the company on an ongoing basis;

    — the provision of an annual certificate of compliance to the Secretary of State;

    — a requirement for a detailed quality management system for the whole supply chain;

    — a mandatory value for money criteria for all maintenance works (with any over £10 million requiring a competitive tender);

    — detailed record keeping based on open book accounting principles;

    — a specified range of events triggering Expanded Interim Project Reporting (potential default, cost overruns, distress indicators, profit warning, etc);

    — a Secretary of State right to require the DBFO Co to prepare and implement a Remedial Action Plan on any area which he believes is inadequate, unsatisfactory or failing;

    — payments are made to the DBFO co based on the performance of the motorway. These payments increase as key stages of the widening are delivered. Hence if the contractor does not deliver according to the contract the payment is withheld; and

    — in addition, the absence of underpinning of the debt financing by the Department during the construction period means that the bank lending is fully at the lenders risk for delivery failure.

  Turning to the particulars of Metronet, it is clear from the company's demise that one of the chief problems facing interested parties—Metronet itself, shareholders, lenders, LUL, the Arbiter and the Government—was the lack of, or the poor quality of, information flowing between them. This meant that the scale and nature of the problems confronting Metronet became known too late in the day for effective remedial action to be taken.

  We are, therefore, taking steps to ensure that, across the Underground investment programme, information on progress of projects and economy and efficiency is available early enough for problems to be picked up and addressed.

  The National Audit Office report on the failure of Metronet suggested that LUL should not have had to go to the Arbiter to get hold of cost/performance information and that it should have been able to request it directly from the infraco. There will have been some commercially confidential information, which it would not be appropriate for the infraco to share directly with LUL—that is why the Arbiter is there as an impartial source of expertise and guidance. Whilst under the Metronet contracts it was for LUL to manage and request any information it thought necessary, the option of asking the Arbiter for guidance on any matter relating to the PPP agreement was always open to them. It is, therefore, important that each party uses the information that is freely available to them, including the DfT, so that each party can manage the risk to which they are exposed.

  The Arbiter, for example, is able to request the infraco to provide any such information as he considers relevant and in that sense the Arbiter does provide assurance on whether the work performed is affordable and value for money and can work with LUL and both parties in analysing the information. He is able to use his powers to the full extent he considers appropriate, such as conduct as detailed an investigation as he thinks appropriate.

  With regard to the incentives in place for project funders to ensure contract delivery, we review the approach for each contract based on the nature of that agreement. It should be noted that the circumstances prevailing at the time that the PPP contracts were let meant that the provision of a significant degree of underpinning to the lenders to Metronet was necessary.

  Since the award of Metronet contracts, the Department has not provided any similar guarantees to lenders on its PFI contracts and has sought to ensure that the incentives on both equity and debt providers are real and substantive in order to support delivery of project objectives.

  As part of the evaluation of PFI contracts, the Department is considering the robustness of the corporate governance arrangements for each contract in the context of the particular contract. The nature of the PPP contracts—in particular the Periodic and Extraordinary Review mechanisms—allowed for significantly greater revisions to contract prices than exist in standard PFI contracts. In the recently awarded M25 contract, there was specific requirement for a detailed Governance Statement that set out the role of the Special Purpose Vehicle and nature of its decision making processes.

Q2.  Are these lessons being applied to the London Underground PPP Agreement with Tube Lines?

  Tube Lines has so far delivered largely to time and to budget and has had to find innovative ways to do so. For example, while Tube Lines also incurred higher costs in delivering their PPP station programme, they ultimately managed these pressures using contingency funds and by finding offsetting efficiencies in other areas.

Tube Lines greatest challenge to date has been the delivery of the Jubilee Line Upgrade. Complex technical challenges have obliged the company to revise delivery plans and timetables. While disappointing—for LUL if the upgrade is delivered late and at the cost of additional closures, and for the company who face significant abatements to ISC payments—these challenges are now being addressed. Tube Lines are also confident that the lessons now being learned will realise benefits when signalling upgrades on the Northern Line and the Piccadilly line are delivered. While real delivery challenges remain, therefore, the Department's view is that the PPP agreement with Tube Lines is working in the manner envisaged.

  Although the DfT is not party to the PPP Contract between LUL and Tube Lines, with large amounts of government money being invested Ministers and Officials will continue to meet regularly with LUL, Tube Lines and the Office of the PPP Arbiter to monitor progress.

  We are also taking steps to ensure that the Review for 2010-17 runs as smoothly as possible and that (within the bounds of propriety and commercial confidentiality, and in view of the fact we are not a party to the agreement) we are kept fully informed by both parties as to developments. The Arbiter set out his proposed timetable for receiving and responding to a reference on cost, and any further references on financing. We indicated to the parties that we considered this a sensible timetable and encouraged the parties to move to an early reference to ensure clarity on costs in good time for the start of Period 2, to minimise cost to LUL and disruption to passengers. We are therefore pleased that a reference has been made at an early stage (23 September). Our liaison with the parties is geared to identifying and understanding where the risks to the taxpayer may be and doing as much as we can (within the constraints of the devolution framework for London, and without being a party ourselves) to ensure these are effectively managed by the contracting and other interested parties.

  In the context of the second period review, the Department acknowledges the recommendation in the NAO Report that the Arbiter should be able to highlight issues affecting the taxpayer's interest. We have, therefore asked both Tube Lines and LUL to consider how the Arbiter's role can be strengthened and improved to protect the wider public interests. These changes might include increasing the Arbiter's rights to undertake reviews of PPP programme delivery, economy or efficiency without formal reference by one of the contracting parties. Such changes must, however, as the NAO Report recognises, be agreed by the parties themselves and cannot be applied retrospectively by Government.

Q3.  How has the upgrade work progressed since the demise of Metronet?

  Since the TSC Inquiry into the PPP Agreements in the autumn of 2007 there has been a considerable progress on line upgrade programmes.

It is LUL's and TfL's responsibility to ensure that the former Metronet upgrade programme is delivered to time and budget and that they meet the outcomes in terms of increased passenger capacity and reduced journey time that were specified in the original PPP Contracts.

  Examples of progress so far include:

    — The TfL run Metronet BCV business is progressing the Victoria line upgrade, which has seen the first new train enter passenger service on 21 July 2009 during limited late night operations in order to grow system reliability. In parallel the new automatic train control and signalling system is being installed.

    — The TfL run Metronet SSL business has seen new trains with air conditioning being tested at the Old Dalby test track facility during the summer in order to grow system reliability of the train interface with the upgraded signalling system. The first train is due to be tested on the Metropolitan line in December 2009 with the first train expected to enter passenger service in May 2010. Signalling upgrade works on the Metropolitan line is progressing to schedule.

  Metronet's failure to deliver its station programme has meant that LUL has had to recast the programme and scope of the work and we look to LUL to ensure that this revised programme is delivered in a timely and cost effective manner. Nevertheless work on 124 stations has now been completed, which is a further 33 since the TSC Inquiry of autumn 2007 meaning that 48% of the total has now been completed.

  Delivering the upgrades is only part of the story. For passengers using the tube on a daily basis having a reliable journey is key. Perhaps the most important indication on the improved performance of the Network is the availability indicator as recorded in "Lost Customer Hours", which has been published in "London Underground PPP & Performance Report 2008-09" on the TfL website at http://www.tfl.gov.uk/corporate/modesoftransport/londonunderground/management/1582.aspx. By comparing previous reports we can see that there have been some substantial improvements since Metronet administration and since the PPP commenced as indicated in the table below:


PPP company/line
2003-042004-05 2005-062006-07 2007-082008-09
Lost Customer Hours against benchmark
Tube Lines
Jubilee33% worse1% better 8% better20% better0% 9% worse
Northern32% worse95% worse 62% worse23% worse25% worse 31% better
Piccadilly8% better52% better 63% better51% better 49% better54% better

Metronet SSL
Metropolitan, Circle, Hammersmith & City 21% better50% better 39% better37% better44% better 48% better
District43% better35% better 16% better19% worse53% worse 14% better
East London4% better2% better 34% better29% better 20% betterLine closed

Metronet BCV
Bakerloo15% better34% better 13% better10.7% worse 3% better34% better
Central16% worse2% better 14% better24% better 33% worse33% better
Victoria16% worse9% worse 11% worse26.7% worse 40% worse23% better
Waterloo & City58% worse 12% worse66% worse29.2% worse 66% worse219% worse



  For 2008-09 the Jubilee line is just below benchmark for the reasons explained above in the problems encountered in the delivery of the signalling upgrade, but all other lines are performing well above benchmark with the exception of the Waterloo & City line, which was due to train defects and signalling issues causing train cancellations. LUL are addressing this with a "hit squad" and already seen substantial improvements so far in 2009-10. One of the most significant improvements can be seen on the Northern line where Tube Lines has spent much of the first period making the infrastructure more reliable, through track replacement and improving the signalling. For the former Metronet lines we can see that for many their performance dipped during the lead up (2006-07) and period in administration (2007-08) as Metronet's problems crystallised.

  Tube Lines are now close to completing the Jubilee line upgrade. The project has presented real delivery challenges and the need for additional closures has been disappointing. We are aware that it has been frustrating for LUL. We have received reassurances from Tube Lines that lessons learned from this project will be applied to upgrades of both the Northern and Piccadilly lines. We look to both parties to agree to innovative solutions to minimise inconvenience to the public in the future.

Q4.  What contractual arrangements are appropriate for the future?

  A Joint Steering Committee consisting of LUL, TfL, DfT and HMT was tasked with considering a range of options for the permanent structure of the Metronet contracts, with the objective of:

    — providing a stable and safe operational framework for the Tube;

    — delivering the modernisation, upgrade and maintenance of the Tube infrastructure;

    — being affordable; and

    — delivering Value for Money for the taxpayer.

  The Joint Steering Committee has now reported and the Mayor and Secretary of State have accepted its recommendation that the existing Metronet contracts should remain under the direct control of LUL on a permanent basis. LUL will remain responsible for all asset management decisions, but there will continue to be substantial private sector involvement with much of the work carried out through contracts managed by LUL. In detail:

    — Existing contracts for the Victoria line upgrade (signalling and rolling stock) and for the Sub-Surface line upgrade (rolling stock) will continue—these contracts were inherited from Metronet (and have been varied).

    — A new contract will be awarded for the Sub-Surface line signalling upgrade—an Invitation to Tender was issued this summer.

    — The Bakerloo line upgrade is not due to start until 2020. A decision on the most appropriate contracting arrangement will be taken nearer the time, reflecting lessons learnt from both the Jubilee and the Victoria line upgrades.

    — Track renewal and civil engineering work (bridges, tunnels, embankments etc) will be carried out through direct procurement with the appropriate form of contract.

    — For station refurbishment, LUL will award a new framework contract based on a detailed client specification—offering a degree of risk transfer whilst retaining budgetary control at LUL.

    — LUL will retain safety critical maintenance and inspections, among other things, with other line maintenance and station cleaning/facilities management carried out via bundled service contracts.

  In awarding new contracts, LUL will include robust performance incentives and transfer risk where appropriate.

  The JSC rejected the option of new long-term performance based contracts for the Victoria and Sub-Surface line upgrades as prohibitively expensive. In both cases major contracts for elements of the upgrades are already underway and would either need to be unpicked at great cost of time and money, or passed on to a new delivery partner, limiting their flexibility to innovate and achieve efficiencies and again resulting in a high risk premium. This is not the case for the Bakerloo line upgrade which is still some years off. A long-term performance based contract may therefore be more appropriate for the Bakerloo line upgrade.

  The JSC concluded that longer term value for money will turn on LUL's ability to deliver on time and within budget. LUL has not had direct responsibility for upgrades of this magnitude since the PPP began, and will need to build its capability if it is to improve on its pre-PPP record and deliver major upgrade projects successfully. The Mayor and Secretary of State are considering the most appropriate way to scrutinise the delivery of the ex-Metronet (and other) works in order to protect the public interest.

Q5.  What risks, if any, are associated with the PPP Agreement with Tube Lines?

  The Government is fully aware that the involvement of the private sector cannot always guarantee success, nor that it will deliver innovation, efficiency and economy. However there are also examples when the public sector management of major projects, including LUL in the 1990s, has also been unsuccessful. It is clear that there is no single procurement model or formula for success in delivering major and complex projects, and the appropriate structure must be adopted in each case.

As noted by the PPP Arbiter's evidence at the TSC in 2007, the private sector can successfully deliver projects when there are clear outcomes specified in the contract and the company is free to decide the approach that it should take to deliver those outcomes. Tube Lines to date has had reasonable success working to the same contract that was applied to Metronet, though with different materiality thresholds, ie the point at which an Extraordinary Review can be triggered with the Arbiter to give a direction on costs.

  It is clear that the private sector will continue to be the major force in delivering improvements to the London Underground, whether the contracting mechanism is through the intermediary of the PPP agreement with Tube Lines, or direct with LUL now that they have taken over the contracts with private suppliers that were once Metronet's.

  Under the permanent structure which replaces the Metronet PPPs, LUL intends to continue public reporting of performance and will maintain the PPP performance measures to provide a basis for performance assessment and comparison with Tube Lines. Moreover, LUL undertakes that it and (to the extent practicable) its sub-contractors will make available to the statutory PPP Arbiter such level of information as he requests and requires to assess the performance of Tube Lines.

  Part of the Secretary of State and Mayors' consideration of any new arrangements will be the extent that scrutiny applies across TfL's investment programme, including management of the former Metronet business, other private sector contracts and those elements of the investment programme delivered in-house (such as some types of maintenance).

Q6.  What impact is the current economic situation having on transport PPP and PFI schemes and what are the financial implications for other transport schemes?

  The most relevant aspects of the economic situation for transport are falls in passenger numbers and the deterioration of the financial markets. It is also worth considering any potential decline in market interest in PPP schemes.

Fall in passenger numbers: The majority of transport PPP schemes do not include volume risk (ie payment is on delivery of services rather than linked to passenger numbers) and therefore the fall in passenger numbers observed across transport modes is not adversely affecting the performance of PPP deals which are already signed. This is true for the Tube Lines PPP scheme where the charges to LUL are based on infrastructure maintenance and delivery of upgrades.

  In a few transportation PPPs, such as the M6 Toll and Second Severn River Crossing, traffic risk has been passed to the private sector to manage. We are not aware of any transport PPPs in which the drop in passenger linked revenues is having sufficient impact to destabilise the concession.

  Deterioration in financial markets: The deterioration in financial markets has led to much tighter credit conditions and significantly more expensive funding terms. For PPP projects which have already closed, however, there is minimal impact.

  New transport PPP projects have managed to raise finance and close since the downturn, notably the M80 in [February], the M25 upgrade in May (which raised £1 billion from EIB and commercial banks) and the Carlisle Northern Development Route in July. Generally however progress to financial close has been slower and final costs have reflected higher funding terms. The higher financing costs have been partially offset by the reduction in underlying interest rates and no transport schemes have been cancelled due to unaffordability or inadequate value for money.

  A notable result of the recent financial upheaval has been the withdrawal of the capital (bond) markets from the infrastructure arena and a reduction in the number of banks prepared to commit large sums to long term loans. This has meant that whilst smaller deals can get done with relative ease, larger deals (£500 million plus) have required a combination of EIB and/or strong sponsor support.

  Market appetite: There is no evidence that the current economic conditions are having an adverse affect on market appetite for bidding for transport PPP schemes. For construction companies and operators, PPPs represent attractive opportunities in relatively quiet markets. This has been most recently demonstrated by the strong bidding field for the Sheffield Highways Maintenance scheme (with a capital value of over £500 million) which came to the market this summer. There equally does not appear to be a constraint in attracting the equity required to support the financing of PPPs. Over £200 million of contractor equity was raised for the M25 and strong equity bids have been received on the current Inter-city Express Programme and Thameslink rolling stock procurements.

Q7.  What role has Government played in these matters?

  Government has worked closely with TfL and LUL during the period of Metronet administration to expedite the smooth transfer out of administration of the Metronet companies and above all to ensure the continued safe operation of the tube. The process has also included engagement with the European Commission who needed to consider whether the restructuring (when Metronet's businesses were transferred to two TfL nominee companies in May 2008) was in compliance with our Treaty obligations. This was a critical step in putting the tube back on a stable footing while work to agree a permanent restructuring continued.

Over the course of 2008, DfT and HM Treasury, supported by Partnerships UK, worked with TfL and LUL to consider the full range of options for Metronet's permanent structure. Recommendations were then made to the Mayor and Secretary of State who have now accepted that the contracts should continue to be managed directly by LUL on a permanent basis—subject to compliance with our Treaty obligations in respect of state aid. The Government will continue with its discussions with the Commission accordingly.

  Alongside this the Mayor and Secretary of State will be considering ways of improving efficiency, effectiveness and economy in the delivery of TfL's obligations under the former Metronet and ancillary contracts.

  We have also considered the future role of the Arbiter who, under the PPP arrangements, will continue to have a pivotal role in driving Tube Lines towards being economic and efficient. While it is of course for London Underground and Tube Lines as contracting parties to manage the Periodic Review process to a successful outcome, DfT has been liaising with all parties to ensure that the process runs as smoothly as possible.

Department for Transport

October 2009





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 26 March 2010