5 Security of the current investment programme
42. Network Rail will be investing £35 billion
on the railway network during Control Period 4, 2009 to 2014"an
investment programme that is bigger than any seen for a generation",
it says.[72] Of this
amount:
- £11.7bn is to enhance the network, including
projects to relieve crowding by lengthening platforms and to increase
capacity to enable more and longer trains to run on busy lines;
- £11.5bn is for renewalsreplacing
older parts of the network (including track, signalling and bridges)
with new, and
- £9.2bn is for day-to-day maintenance and
the costs of operating and running the network.[73]
The Department for Transport will contribute £16
billion in the form of direct payments.[74]
The remaining funding comes from other sources including the Scottish
government, passenger train operators, freight operators, retail
and property. Network Rail is also allowed to access further funding
by borrowing.
43. Network Rail's investment priority for the
2009-2014 period, set by the Government, is to increase capacity
on the network to accommodate a 22.5% increase in passenger demand.
The Thameslink and Crossrail projects will greatly increase capacity
in the capital.[75] A
total of 1,300 extra carriages will also be provided to increase
rail capacity across the country, adding 12% to the fleet (see
paragraphs 49-50).[76]
Other projects undertaken by Network Rail in the control period
include the £1.5 billion redevelopment of Reading and Birmingham
New Street stations, the development of a Strategic Freight Network,
and electrification of the Great Western Main Line and the Manchester-Liverpool
line.
The current investment programme
44. Most witnesses were positive about the scale
of the funding committed between 2009 and 2014 but several expressed
concern that the current financial situation could result in the
deferral or cancellation of some CP4 projects, particularly those
to increase capacity. The Association of Train Operating Companies
told us it was "essential" that existing CP4 investment
commitments were honoured to relieve current capacity constraints
on the network, a view shared by many others.[77]
Several witnesses noted the fact that passenger numbers were forecast
to double over the next 30 years, and passenger growth had still
increased over the past year despite the recession, albeit at
a slower rate than previously.[78]
National Express pointed out that it was "very inefficient
and expensive to stop and start projects".[79]
Several organisations argued that the timescales of rail investment
were far longer than those of an economic cycle, and the recession
should have ended by the time much of the investment came on stream.[80]
45. We questioned both the Office of Rail Regulation
(ORR) and the Department for Transport about the security of the
billions of pounds committed to the network until 2014. The ORR
assured us that the CP4 settlement was a binding commitment by
Government: "the Government has not got an automatic easy
way through to requiring or removing the commitment it has made
to finance the railway to meet the outputs it set out in 2007.
[
] To change it materially would require primary legislation
unless there was agreement between the parties".[81]
The Department told us that "substantial" changes
to the CP4 settlementparticularly changes which would see
a significant alteration to the level of funding provided by Governmentcould
only be implemented via an "interim review process".
The power to initiate such a review rested with the ORR; the Government
said it was not aware of any plans for such a review. Smaller
changes to planned enhancement projects that did not substantially
affect the overall settlement could be made via Network Rail's
"change control process", which would require a formal
proposal from Network Rail, and agreement from sponsors and the
ORR.[82]
46. Ministers' public pronouncements on this
matter have been clear. The DfT Minister for National Networks,
Chris Mole MP, told us the Government had no plans to change any
of the funding for Crossrail or Thameslink, and he said any changes
in the contractually committed Control Period 4 settlement were
"extremely unlikely".[83]
The Secretary of State also assured us that there were no changes
in the status of any of the Government's commitments.[84]
In the Pre-Budget Report in December 2009, the Chancellor affirmed
his support for a series of key transport projects, including
Crossrail, Thameslink and the electrification proposals.[85]
47. Given current levels of
overcrowding on parts of the network along with passenger demand
forecasts, it is vital that current and planned projects to increase
capacity continue to the present timescale.
We welcome the strong assurances from the Government and the
Office of Rail Regulation that the Control Period 4 funding settlement
for the next four years is secure. Cuts in transport investment
are easy to make, but are costly in the long term, undermining
future growth prospects and depriving future generations of a
lasting legacy of good transport services. Investment in
improving transport infrastructure should be based on the long-term
needs of the economy and society, not directed by the need for
immediate public expenditure savings.
48. We are aware, however, that those projects
not directly funded within the CP4 settlementsuch as Crossrailare
more vulnerable to funding pressures.
Rolling stock
49. The Government committed within the HLOS
to invest in 1,300 extra carriages to increase rail capacity across
the country, particularly in and around big cities.[86]
In our Report on the Government's 2007 Rail White Paper, we said
the 1,300 carriages were "much needed and very welcome",
although we noted that due to the growth in rail patronage, the
new stock was unlikely to relieve overcrowding significantly.[87]
The Government's subsequent announcement, in July 2009, that it
would electrify the Great Western Main Line and the Manchester-Liverpool
line has led to a review of the 2007 rolling stock commitment.
The electrification programme alters the requirements for train
rolling stock over the next decade, as there is less need for
diesel trains and a greater requirement for electric trains.
50. The Government initially said it would publish
its revised rolling stock plan in the autumn of 2009 to take account
of these changed circumstances, although this was later postponed.
The Government now says it must complete commercial negotiations
on Thameslink before it can update the plan. By early February
2010, the revised plan has still not been published.[88]
Ministers have confirmed, however, that the Government remains
committed to delivering 1,300 additional carriages by mid-2014
and about 230 of those carriages are already in service.[89]
Several witnesses giving evidence to our inquiry were confused
about the current state of affairs.[90]
The Government was right
to revise its rolling stock plans in light of its electrification
announcement. We are concerned, however, by the postponements
in issuing the plan and by the uncertainty and confusion caused
by the delay within the industry. Rolling stock is required urgently
in several parts of the country. We urge the Government to set
out its revised rolling stock proposals as soon as possible to
provide the industry with certainty about future capabilities
and to improve the travelling experience of passengers on overcrowded
parts of the network.
72 Network Rail, Control Period 4 Delivery Plan
2009: Summary, March 2009. £28.5 billion has been allocated
through the 2008 Periodic Review for Control Period 4. Back
73
Ev 121 Back
74
ibid. Back
75
Crossrail is expected to increase London's capacity by 10%. Back
76
Ev 203 Back
77
Ev 203. For example, Network Rail [Ev 116]; Unite [Ev 64]; North
West Rail Campaign [Ev 112]; Freight Transport Association [Ev
125]; Skipton East Lancashire Rail Action Partnership [Ev 127];
West Northamptonshire Development Cooperation [Ev 142]; pteg [Ev
170]; London TravelWatch [Ev 174]. Back
78
Railfuture North East branch [Ev 71]; Office of Rail Regulation
[Ev 160]; Passenger Focus [Ev 136]; Cogitare [Ev 147] Back
79
PIR 29. Passenger Focus made a similar point [Ev 136]. Back
80
Royal Borough of Kensington and Chelsea [Ev 80]; Rail Engineers
Forum [Ev 99]; South Yorkshire Passenger Transport Executive [Ev
107]; National Express [Ev 144]; Cogitare [Ev 147]; The Northern
Way [Ev 163]; London Borough of Croydon [Ev 167]; London TravelWatch
[Ev 174] Back
81
Qq 81, 93 Back
82
Ev 181 Back
83
Qq 306-322 Back
84
Q 36 Back
85
HC Deb, 9 December 2009, col 366 Back
86
Department for Transport, Britain's Transport Infrastructure:
High Speed Two, January 2009, p 4 Back
87
Transport Committee, Tenth Report of Session 2007-08, Delivering
a sustainable railway: a 30-year strategy for the railways?,
HC 219, para 107 Back
88
Department for Transport, Britain's Transport Infrastructure:
Rail Electrification, July 2009, p 4 Back
89
HC Deb, 14 December 2009, col 65WS Back
90
For example, the Association of Train Operating Companies [Q 165],
pteg [Q 3]. Back
|