The Child Maintenance and Enforcement Commission and the Child Support Agency's Operational Improvement Plan - Work and Pensions Committee Contents


2  Information Technology

10. Improving the effectiveness of the CSA's IT was one of the key features of the Operational Improvement Plan (OIP). By October 2005, the CSA had paid a total of £190 million to EDS for its work on the CSCS (the IT system for the old scheme) and CS2 (the IT system for the current scheme) IT systems.[9] However, in 2006 the National Audit Office (NAO) found that there were over 500 defects with the CS2 system "that were having a significant impact on staff productivity and maintenance outcomes".[10]

11. The OIP acknowledged "well documented problems with computer systems" contributing to the CSA's under performance and noted, given particular shortcomings in data held on the old computer system, that conversion of old scheme cases on to the new scheme would "carry substantial risks and be costly and complex".[11] However, it promised that

    The CSA Operational Improvement Plan while not incorporating bulk migration and conversion will bring many improvements. It is flexible enough to facilitate the re-design of future child support arrangements. It will deliver a much better level of service for clients and provide a stable base from which to move forward in the future.[12]

12. Over the course of the OIP, £107 million was spent on upgrades to the CS2 system (one third of the total spending on the OIP). In September 2008, the most significant IT upgrade, Productivity Release 1 was launched to support the restructured business and fix outstanding problems with CS2.

13. The NAO reported that the CSA had agreed a work programme with EDS to rectify 500 defects in the CS2 system over the course of the OIP and that

    The Commission reports that 350 of these defects were rectified over this period and reports that the rest were addressed by Productivity Release 1.[13]

14. However, the remaining defects in the CS2 system are still generating a large number of problems, many of which appear to be insoluble. The NAO reported that, as of October 2009, the CS2 system had over 1,000 reported problems, of which 400 had no known workaround and therefore resulted in cases being stuck in the system.[14]

15. We asked the Commission about these continuing IT problems and were told that it currently experienced around 3,000 IT incidents a week, 70% of which were caused by around 60 of the problems.[15] This was down from 7,000 incidents a week before the launch of Productivity Release 1, and was expected to fall below 2,000 by April 2010. The Commission anticipated fixing around 30 of the remaining defects in its IT systems, which was expected to remove some of the problems. Despite the progress made over the course of the OIP, there still remain a very large number of IT problems which have no workaround and are causing cases to get stuck.

16. We are concerned that the work conducted over the course of the Operational Improvement Plan to rectify the problems with the CS2 IT system have either not resolved the problems or have revealed new problems. More than 400 of these problems are sufficiently serious to cause new cases to get stuck in the system. We hope that our successor Committee will maintain a close interest in progress made in resolving the IT problems with the old and current systems. We request that the Commission supply our successor Committee with quarterly reports on progress in this respect.

Clerical cases

17. It is the persistent problems with the CS2 IT system that have resulted in a large number of cases getting stuck in the system, requiring them to be managed "clerically" (manually by staff). The Commission reported that it was only as a result of the Productivity Release 1 IT upgrade that it was able to identify that many of these cases had become stuck; previously it had been unable to deal with these cases clerically unless the customer notified them that there was a problem.[16] Although it is to be welcomed that the Commission is now systematically identifying cases that need to be managed clerically, and that this is a successful result of the IT upgrades under the OIP, this process seems to be throwing up an ever increasing number of these cases. Furthermore, the 400 IT problems with no work around, mentioned above, are also causing new cases to get stuck.

18. In March 2006, 19,000 cases were being managed clerically outside the IT system; this number had more than trebled to 60,000 by the end of the OIP in March 2009. The NAO report that this figure had risen yet higher to 75,000 by September 2009; it estimates that, at the current rate of increase, around 108,000 cases would be managed clerically by September 2010.[17] A graph of the number of current scheme cases being managed clerically since March 2005 is reproduced below:

Number of current-scheme cases being managed clerically

Source: National Audit Office, Ev 29

19. In March 2006, the CSA outsourced the management of clerical cases to Vertex Data Science Limited in an attempt to reduce the burden of these cases on CSA staff. However, the continuing increase in clerical cases has required the retention of 302 caseworkers to manage wholly clerical processes and 252 caseworkers to manage partly clerical cases within the Commission.

20. The Commission estimated the cost of managing clerical cases in September 2009 at around £3.7 million per month, including the cost both of the contract with Vertex Data Science Limited and of its own staff doing the work in-house.[18] However, as the number of clerical cases rises, the cost of managing them will also rise. The NAO has estimated that the annual cost of managing each clerical case is £967 compared to £312 per case administered through the IT systems.

21. The Commission acknowledged that there would be a continued increase in the number of clerical cases "for a couple of years".[19] It has also explored a number of ways of reloading clerical cases back on to the CSCS and CS2 systems but has concluded that it is "too risky" to try and do this.[20]

22. We are concerned at the almost exponential rise in the number of clerical cases caused by shortcomings in information technology. The additional costs of clerical administration of cases are mounting alarmingly. We are concerned that this does not represent the "stable base" that the Operational Improvement Plan set out to establish for introduction of the future scheme.

Development of a new IT system for the Commission

23. The Commission is now procuring a new IT system for the operation of the future scheme. It went out to tender in August 2008 for the contract for the system and signed a £45 million contract with Tata Consultancy Services on 30 March 2009. It informed us that

    The new system will utilise commercial 'off-the-shelf' software packages already widely used in the financial services industry, which will ensure better customer service and greater value for the taxpayer.[21]

It explained the rationale for this approach, noting that "the bespoke nature of the current CS2 system contributed to many historic and current problems and made the system expensive to operate and improve."[22]

24. In its 2006 report, the NAO also found that a number of aspects of the CSA's contract with EDS for the IT system for the current scheme (CS2) did not represent good practice. The Commission believes that it has taken adequate steps to address the concerns identified by the NAO in their 2006 assessment, by

  • improving clarity about the functionality required of the system;
  • improving clarity about its responsibilities in the contract;
  • improving clarity about managing changes in the contract;
  • improving clarity about term, termination and exit management rights - the Commission will not own the intellectual property rights to the IT but will have rights for perpetual use;
  • ensuring that the contract will operate on a pay as you go basis, with full payment only released after it has been ensured that progress is in line with the implementation plan; and
  • improving certainty about what constitutes delivery.[23]

25. Stephen Geraghty estimated that "the putting in place cost, the development cost and the lifetime licences for the future scheme" including three years of running costs would amount to around £120 million.[24] He was confident that the future scheme system, utilising existing off-the-shelf packages, including one used by the National Bank of China, would be more efficient to run than the current (CS2) and old scheme (CSCS) systems. Janet Paraskeva added

    We are effectively […] a bank—we take money in, we give money out—so a banking system. We manage cases; so there is a case management system on the front of it. So, actually, the costs are really only in the integration of those and the relatively small amount of customisation that would be needed for our people to actually interact with our customers.[25]

Stephen Geraghty added that the development work required of TCS to adapt the packages would amount to around £10 million.[26]

26. We welcome the steps that the Commission has taken to learn from the disastrous mistakes made in commissioning the CS2 IT system. We are encouraged by the organisation's confidence that the IT system to administer the future scheme will be more efficient to run and we note the strong case that has been made for using off-the-shelf packages.

27. However, it is often the process of making different packages work together that creates IT problems. We ask the Commission to keep our successor Committee up to date with the progress of development of the future scheme system and we therefore request that it make six-monthly reports to our successor Committee on its work in this area.


9   Ev 29 Back

10   Ev 28 Back

11   Child Support Agency, Operational Improvement Plan 2006-09, paragraphs 12-13. Back

12   Child Support Agency, Operational Improvement Plan 2006-09, paragraph 14. Back

13   Ev 28 Back

14   Ev 28 Back

15   Q21 Back

16   Q26 Back

17   Ev 29 Back

18   Ev 29 Back

19   Q22 Back

20   Q26 Back

21   Ev 48 Back

22   Ev 48 Back

23   Ev 30 Back

24   Q24 Back

25   Q25 Back

26   Q25 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 24 February 2010