Annex 1Chronology of the Deepwater
Horizon Incident
The Macondo Well in the Gulf
of Mexico
BP started drilling the Macondo well on 7 October
2009, using the Transocean owned Marianas platform. Hurricane
Ida damaged this platform on 9 November 2009, and so BP and Transocean
(who operated the platform under contract to BP) replaced the
Marianas with the Deepwater Horizon, which began drilling on 6
February 2010. Transocean charged BP approximately $500,000 per
day to lease the rig, plus contractor fees.[215]
BP aimed for the drilling to take 51 days, with an estimated cost
of $96 million. It was expected that the Deepwater Horizon would
be leaving as early as 8 March 2010, but the Macondo well took
longer to complete than anticipated. By 20 Aprilthe day
of the blowout that killed 11 workers and injured 17the
rig was 43 days late, which would have cost an extra $21million
in lease fees alone.
BP owns a 65% interest in the Macondo well. The US-based
company Anadarko Petroleum owns a 25% share, and the Japanese
company Mitsui owns 10%. The Deepwater Horizon drilling platform
(an exploration rig, not a production rig) was owned by Transocean,
who also operated it for BP. The objective of the drilling operation
was to "successfully evaluate any commercial hydrocarbon
[oil and gas] [...] discovered".[216]
The oil and gas reservoir was located at over 5,596m below the
seabed, with the wellhead at a water depth of over 1,500m.
The Macondo project yielded one of the largest finds
in the Gulf of Mexico, but the crew repeatedly struggled to maintain
control of the well against powerful "kicks" of surging
oil and gas. In evidence published by the US House of Representatives
Energy and Commerce Committee, BP staff described Macondo as "a
nightmare well that has everyone all over the place", just
six days before the Deepwater Horizon platform exploded.[217]
The Deepwater Horizon Drilling
Rig
The Deepwater Horizon was a semi-submersible, mobile
offshore drilling rig built for Transocean by Hyundai (South Korea)
in 2001. It flew a Marshallese Islands' flag of convenience. "Semi-submersible"
rigs are kept afloat and upright by watertight pontoons located
below the surface and beneath the waves, and are usually used
in water depths greater than 200m where floating fixed structures
are not practical. The Deepwater Horizon was dynamically positioned,
which meantrather than using chains or wire to anchor it
in place during drilling operationsthat its position was
computer controlled using underwater thrusters.
The drilling rig was capable of operating in harsh
environments and water depths of nearly 2,500m (upgradeable to
over 3,000m). While drilling the Macondo well it was operating
in just over 1,500m of water. In 2009, before work began on the
Macondo well, Transocean crews working with BP discovered oil
in the giant Tiber field in the Gulf of Mexico. At a total depth
of approximately 10,685m (in an ocean depth of 1,259m) it was
the deepest oil well in the world.
The Deepwater Horizon rig was due for a series of
extensive maintenance checks late in 2010, with records indicating
it was last checked thoroughly in 2005. Documents from Transocean's
maintenance department indicated various asset deficiencies including
"intermittent alarms [on the control panel] on unrelated
functions when opening [a valve on the blowout preventer]",
and "low pressure readings" in the hydraulic system.[218]
Blowout prevention devices are designed to handle
a range of well control problems, and often come fitted with several
different types of rams, giving engineers flexibility in their
response. The blind shear ram is described as the ultimate fail-safe
device, crushing and sealing the well pipe as a measure of last
resort. The Deepwater Horizon had a single blind shear ram located
inside the 15.5m tall blowout preventer stack at the wellhead
on the seafloor. With a single blind shear ram, there is a risk
that it could close on one of the extremely strong joints that
connect the sections of drilling pipe, and be unable to collapse
it. Such a risk is minimised by the use of two blind shear rams.
Transocean hired West Engineering to carry out a
physical assessment of Deepwater Horizon's well control system,
but they were unable to access the blowout preventer (BOP) as
it was on the seafloor. This meant they were unable to verify
whether the blind shear ram on Deepwater Horizon's BOP could shear
through drill pipe and seal off the well while in deepwater. A
2009 industry study entitled Pull Your BOP Stack - Or Not?
calculated the price of stopping operations to pull up a blowout
preventer for repairs at $700 per minute.[219]
BP's internal investigation of the Gulf of Mexico
oil spill culminated in the Deepwater Horizon Accident Investigation
Report (the Bly Report), published 8 September 2010. The full
details are not yet known, but it appears that gas and oil rushed
up to the wellhead on the sea floor, and the blowout preventer
(BOP) device was unable to contain the pressure. According to
Dr Tony Hayward, Group Chief Executive of BP: "[the Deepwater
Horizon incident] arose from an interlinked series of mechanical
failures, human judgments, engineering design, operational implementation
and team interfaces".[220]
Factors Identified as Contributing
to the Incident
CASING
Deepwater wells are drilled in sections. The basic
process involves drilling through rock, installing and cementing
casing into placecasing lines the wellto secure
the wellbore (well hole), and then drilling deeper and repeating
this process. One day before the blowoutwhile preparing
the well for future production at a later dateBP decided
to install a single long-string casing from the top of the well
to the bottom, rather than multiple individual casings with a
seal (known as a "liner" with a "tieback").
Mr Richard Cohagan, Managing Director of the oil and gas exploration
company Chevron UK, told us: "BP was designing the well so
that they could use it as a production well and that's one reason
that they had a long string in the well [...] We tend to have
larger [...] and multiple physical barriers".[221]
Mr Cohagan went on to argue that: "BP was trying to design
the right well for their conditions".[222]
Multiple individual casings would have provided more
barriers to the flow of gas up the well in the event of a blowout,
but would have taken longer to install and been more expensive.
A BP-plan review in mid-April recommended against the single casing
as it would make the seal at the wellhead the "only barrier"
in the event of a failure.[223]
Dr Hayward told us: "The decision to run the long-string
was actually based on long-term integrity [...] a liner with a
tieback [...] is subject, over time, to degradation and can leak".[224]
When the final string of this single casing was installed,
one key challenge was making sure the casing ran down the centre
of the well bore. If this is not done properly, it becomes difficult
to displace drilling fluid from the narrow open space around the
casing, which in turn will lead to an inability to cement the
casing in place properly. In such an instance, it is possible
that channels will form in the cement that allow gas to flow up
the open space around the casing. Centralisers are attachments
that go around the casing to centre it in the borehole. Halliburton,
the cementers, recommended using 21 centralisers on this final
string of casing, but BP decided to use six. The Bly Report makes
the case in Key Finding 2 that this decision is unlikely to have
contributed to the incident.
BP aimed for the drilling of the Macondo well to
take 51 days, at an estimated cost of $96 million. It was expected
that the Deepwater Horizon would be leaving as early as 8 March
2010, but the Macondo well took longer to complete than anticipated.
By 20 Aprilthe day of the blowout that killed 11 workersthe
rig was 43 days late, which would have cost an extra $21 million
in lease fees alone.[225]
CEMENT
Despite Halliburton's and BP's own predictions of
a gas flow problem caused by an incomplete cement job, BP decided
not to run a 9-12 hour procedure known as a "cement bond
log" to assess the integrity of the cement seal, dismissing
the Schlumberger contractors who had been hired to undertake the
test.[226] This acoustic
test would have determined whether the cement had bonded to the
casing and surrounding formations. If a channel that allows gas
to flow up is found, the casing can be perforated and additional
cement injected into the annular space to repair the cement job.
Key Finding 1 of the Bly report discusses BP's belief that the
cement mix designed by Halliburton was unfit for purpose. We were
told by Dr Hayward: "we know the cement was not good because
we had influx into the well".[227]
Dr Hayward added: "I think we need to be cautious until we
can complete [...] [an] analysis [of the cement] to understand
why the cement failed".[228]
As Halliburton refused to provide samples for testing,
the BP investigators had an independent laboratory analyse the
design of the cement slurry.[229]
BP noted that there was a high percentage of nitrogen found in
the cement ingredients, making it difficult for the cement to
form a stable "foam slurry".[230]
The cement used was injected with nitrogen to make it into a lighter
"foam".[231]
This is done in order to avoid damaging the rock formation of
the reservoir, which would make it more difficult to produce oil
at a later date. BP says that when the independent laboratory
tried to produce a representative cement samplebased on
the slurry designthey could not demonstrate cement stability.
Therefore, BP concluded that the foam slurry likely experienced
"nitrogen breakout" resulting in channels forming that
would have allowed oil and gas to flow through it.[232]
While drilling into high-pressure, high-temperature
fields like the Macondo, the well is usually filled with heavy
drilling fluid (known as "mud") while drilling to compensate
for the upwards pressure of the oil and gas in the reservoir.
It is recommended that this drilling mud is fully circulated from
the top to the bottom before commencing the cementing process.
This allows the mud to be conditionedby removing any pockets
of gas and other debris safelyso that the cement is not
contaminated. BP decided against the full 12-hour procedure and
only partially circulated the mud.[233]
The choice to use a single string of casing meant
the Macondo well had just two barriers to gas flow up the annular
space around the final string of casing: the cement at the bottom
of the well and the seal at the wellhead on the sea floor. Insufficient
centralisers also meant that there was a severe risk that the
cement job would fail, and the lack of a cement bond log meant
that BP were unable to check this. Finally, BP did not deploy
the casing "lockdown sleeve" that would have prevented
the seal from being blown out from below.[234]
Even when cemented in the wellhead, under certain pressure conditions
the casing can become buoyant and rise up, creating an opportunity
for oil and gas to break through the wellhead seal and enter the
riser to the surface. The lockdown sleeve prevents this.
NEGATIVE PRESSURE TEST
One of the Bly Report's key findings was that readings
taken during the "negative pressure test" to determine
well integrity indicated that there was a flow of oil and gas
from the reservoir into the well even though the "Transocean
rig crew and BP well site leaders" thought the test was a
success and well integrity had been established.[235]
Dr Hayward told us: "we know that with the benefit of hindsight
that the negative test was erroneously interpreted".[236]
This test simulates the temporary abandonment of the well after
drilling and prior to production, when a proportion of the well
is displaced to sea water. BP's Group Head of Safety and Operations,
Mr Bly, added: "There are records of the information that
would have been available, so we know that [information on the
drill pipe pressure increasing, when it should have been decreasing]
was there. We can't explain why they didn't see it".[237]
This series of decisions may have been driven by
expense and time, as by 20 Aprilthe day of the blowoutthe
rig was 43 days late, and would have cost BP at least an extra
£21 million in lease fees alone. However, each decision and
failure increased the risk of a blowout.
Exemplifying the industry's inability to take account
of high-consequence, low probability events, Dr Hayward told us:
"we weren't prepared".[238]
Mr Cohagan, of Chevron UK, told us: "Deepwater Horizon gave
us a new perspective on how bad things could be".[239]
We are concerned that the offshore oil and gas industry has failed
to prepare for what they had previously classified as worst-case
scenarios.
BP's Attempts to Kill the Macondo
Well
On 22 April, two days after the blowout and subsequent
explosion that killed 11 workers, the Deepwater Horizon drilling
rig sank. This bent the 1,500m "riser" pipe connecting
the rig to the wellhead on the sea floor. Submersible robots discovered
two leaks close to the seabed. Over the next few days, BP attempted
to activate the single blind shear ram in the blowout preventer
(BOP), a device located at the wellhead on the sea floor. The
blind shear ram would have severed and sealed the pipe, but attempts
to activate it failed.
On 2 May, BP began drilling relief wells, intending
to intersect the existing well in order to send down heavy drilling
mud and cement to stop the leak. By 7 May BP had constructed a
12m tall containment dome, known as "top hat". They
attempted to lower the dome on to one of the largest leaks from
the bent pipe, but it became clogged with an icy mix of gas and
water (called gas hydrates). After several unsuccessful attempts,
BP inserted a mile-long tube into one of the leaks on the broken
riser pipe on 16 May, and succeeded in siphoning off some of the
oil to a ship on the surface, collecting an estimated 22,000 barrels
a day, over nine days. This siphon was cut off on 26 May as BP
attempted its "top kill" and "junk shot" operations.
"Top kill" attempted to overcome the pressure of the
rising oil by pumping drilling mud into the top of the well, while
"junk shot" attempted to clog up the BOP by injecting
objects such as golf balls. These attempts failed.
On 31 May BP cut the damaged pipe away from the BOP
and lowered a domeconnected to the surface by a new riseron
to the blowout preventer. Methanol and warm seawater pumped down
the riser prevented the formation of icy gas crystals, and oil
and gas were funnelled to a ship on the surface. An additional
siphon supplemented the system on 16 June, pumping more oil to
surface vessels. By mid-July BP had four vessels on site to collect
and process retrieved oil and gas, collecting 62,000 barrels per
day. On 10 July, BP removed this cap and replaced it with a new
device, containing many of the same features as a BOP. The hydraulic
rams on the new cap were closed on 14 July, and pressure sensors
indicated that oil was not leaking from elsewhere on the seafloor.
BP began its "static kill" operation to
plug the well on 4 August 2010. Drilling mud pumped from the surface
forced the oil back down the well, and cement was then sent in
through the top of the well to seal it off. The final "bottom
kill" procedurewhere cement was pumped through relief
wells into the Macondotook place successfully on 18 September.
BP's Gulf of Mexico Clean-up
Operations
A team of experts assembled by the US National Incident
Command (NIC) announced on 2 August that an estimated total of
4.9 million barrels of oil had been released from the Macondo
well. The National Oceanic and Atmospheric Administration (NOAA)
then determined what had happened to the oil. It is estimated
that burning (5%), skimming (3%) and direct recovery from the
well (17%) removed a quarter of the oil released. Another
quarter naturally evaporated or dissolved, and just under a quarter
was naturally (16%) or chemically (8%) dispersed. Dissolution
is the process by which the oil dissolves into the water, whereas
dispersion is the process by which larger volumes are broken down
into smaller droplets. Residual oil made up just over a quarter
of the oil spilt. Residual oil is a combination of categories
all of which are difficult to measure or estimate, and includes
oil: that is on or just below the surface as "light sheen"
and "tar balls"; has been washed ashore or collected
from the shore; or is buried in sand and sediments. It is thought
that dispersed and residual oil will be naturally degraded. Response
efforts addressed 33% of the oil spilled.
Dispersants are chemicals that can be used to break
up and speed the natural degradation of oil on the surface. It
is argued that they are less harmful than oil and biodegrade more
quickly than untreated oil. In the Deepwater Horizon spill the
dispersants were used underwater to prevent more oil from reaching
the vulnerable marshes, wetlands and coastlines of the US Gulf
states. BP was pre-authorised to use approved dispersants, according
to the US Environmental Protection Agency, on spills no closer
than three miles from the shore, but was required to get daily
permission from the U.S. Coast Guard during the clean-up operations
for this incident. Dispersants are usually used on the surface,
but BP injected them into the oil as it flowed from the well.
BP began by using the dispersant Corexit 9527a, and then switched
to Corexit 9500. Both of these products were removed from the
UK Marine Management Organisation's approved list in 1998, as
they proved too toxic in instances where they might end up on
rocky shorelines (although existing stocks could be used).[240]
Booms are temporary floating barriers used to contain
oil by concentrating it into thicker surface layers. Exclusion
booming is used to keep oil away from sensitive areas, while diversion
booming is used to direct the flow of oil elsewhere. Containment
booms are deployed in a "u" or "v" shape to
direct the flow of oil to a recovery resource, such as a skimmer.
"Skimmer" is a common name for any device (usually attached
to a ship) used to remove oil (or an oil/water mixture) from the
surface without using chemicals. In-situ burning is a method of
burning freshly-spilled oil while it is floating on the water.
Environmental Impacts in the
Gulf of Mexico
The Macondo well is estimated to have leaked 4.9
million barrels of oil, making it the largest marine spill in
US history. The full extent of the impact on the environment is
not yet known. As of 16 August 2010, more than 7,000 birds, sea
turtles and dolphins have been found dead or debilitated in the
Gulf of Mexico since the oil spill began.[241]
While a majority of the dead were not visibly oiled, scientists
have yet to determine why they died. However, it has been confirmed
that more animals are dying than during the same time in previous
years. Not all injuries or deaths were necessarily caused by the
oil spill, and some of those found dead may have been oiled after
death. The higher than expected numbers of animals found dead
may have been an artefact of the increased monitoring of the area.
More than twice the number of stranded sea turtles
have been found than normal at this time of year.[242]
Of the nearly 500 found visibly-oiled, the majority were found
alive. Of the nearly 600 found not-visibly-oiled, the majority
were found dead. Some suspect that shrimp fishermen may be causing
the increased deaths by not using devices that prevent turtles
trapped in nets from drowning (whilst the federal agencies are
distracted). More than 50% of one batch of turtle corpses analysed
showed evidence of drowning.[243]
Of the more than 2,300 birds (mostly pelicans) found
not-visibly-oiled, all were dead, compared to about half of the
3,800 found visibly-oiled.[244]
When ingested or inhaled, oil can cause brain lesions, pneumonia,
kidney damage, stress and death. There have also been reports
of dolphins acting as if they were drunk, and it is suspected
that disorientation caused by oil exposure is making them more
susceptible to boat strikes.
215 Fleet Status Report, Transocean, 13 April
2010, www.deepwater.com Back
216
BP Macondo Prospect Well Information, September 2009, http://energycommerce.house.gov Back
217
BP Email, 14 April 2010, http://energycommerce.house.gov Back
218
Deepwater Horizon Rig Assessment, http://documents.nytimes.com/documents-on-the-oil-spill?ref=us#document/p19 Back
219 Jeff
Sattler (West Engineering Services), "Pull Your BOP Stack
- Or Not? A systematic method to making this multi-million dollar
decision", SPE/IADC Drilling Conference and Exhibition
- Amsterdam, 17-19 March 2009 Back
220
Q 89 (Hayward) Back
221
Q 251 Back
222
Q 252 Back
223 Letter
to Tony Hayward, US House
of Representatives, 14 June 2010 http://energycommerce.house.gov Back
224
Q 98 Back
225
Fleet Status Report, Transocean, 13 April 2010, www.deepwater.com
Back
226
Letter to Tony Hayward, US House of Representatives Energy
and Commerce Committee,14 June 2010 Back
227
Q 108 Back
228
Q 109 Back
229
Deepwater Horizon-Accident Investigation Report, BP, 8
September 2010, www.bp.com Back
230
Deepwater Horizon-Accident Investigation Report, BP, 8
September 2010, www.bp.com Back
231
Deepwater Horizon-Accident Investigation Report, BP, 8
September 2010, www.bp.com Back
232
Deepwater Horizon-Accident Investigation Report, BP, 8
September 2010, www.bp.com Back
233
Letter to Tony Hayward, US House of Representatives Energy
and Commerce Committee,14 June 2010 Back
234
Letter to Tony Hayward, US House of Representatives Energy
and Commerce Committee,14 June 2010 Back
235
Deepwater Horizon-Accident Investigation Report, BP, 8
September 2010, www.bp.com Back
236
Q 98 Back
237
Q 117 Back
238
Q 186 Back
239
Q 236 Back
240
"Oil spill treatment products approved for use in the United
Kingdom", UK MMO, 8 October 2010 Back
241
"The Oil Spill's Effects on Wildlife",16 August 2010,
www.nytimes.com Back
242
"The Oil Spill's Effects
on Wildlife",16 August 2010, www.nytimes.com Back
243
"The Oil Spill's Effects on Wildlife",16 August 2010,
www.nytimes.com Back
244
"The Oil Spill's Effects on Wildlife",16 August 2010,
www.nytimes.com Back
|