The draft National Policy Statement (NPS) on Waste Water - Environment, Food and Rural Affairs Committee Contents


Examination of Witnesses (Questions 71-104)

RICHARD AYLARD AND PHIL STRIDE

25 JANUARY 2011

Q71   Chair: Good morning and welcome. Just for the record, Mr Aylard, could I ask you to introduce your colleague, for the record?

Richard Aylard: I'm Richard Aylard. I'm the External Affairs and Sustainability Director at Thames Water, and my colleague, Phil Stride, is the Head of the London Tideway Tunnels.

Q72   Chair: You're both very welcome. We're most grateful to you for being here with us today, and also for the informal briefing you gave us last week. One question I had at the outset: you gave us an indication last week of what the total cost was going to be. We understood from Ofwat afterwards that the cost projections had already gone up over what had originally been proposed. What reassurance can you give the Committee this morning that these costs—mindful of inflation and possible delays—will remain at the current projected figures?

Richard Aylard: The initial cost was given to the Government in March 2007, when Ian Pearson, the then Water Minister, announced that he wanted us to proceed with a solution. That figure was worked out on the basis of a small team of about six people doing a desktop study to see what was needed, and what the cost was likely to be. At that stage we couldn't justify spending the millions of pounds that were required to work the scheme up in detail, because we didn't know whether we would be required to go ahead with it. Once we got the go-ahead from Ian Pearson, we then commissioned a large team, including international experts, of experts in funding, risk, infrastructure, planning—all the disciplines—and it was that process, over a period of more than a year, that produced the latest figure. I'm going to hand over to my colleague, Phil, to talk about exactly what's in that number and how certain we are we can achieve it.

Phil Stride: The main thing to state is that at the period that Richard mentioned in 2006 it was a high-level estimate looking at unit costs—for instance, the length of tunnel and number and diameter of shafts. The team of over 100 people that worked on that two years were very much able to understand the design of the project and understand all the component parts that would make up the project, so we were obviously able to provide a better estimate, understanding what all those component parts were. We've got a very robust risk management process that was able to consider all the risks involved in the project, and have been able to analyse how much we should allow in our estimate for those risks. On top of that, we've also used the HM Treasury Green Book on Optimism Bias, to include an amount of optimism bias that would normally be put into a project of this scale and complexity at this time of its development. That's why we feel that we have, now, a robust estimate for the project, which we feel confident the project can be delivered for.

Q73   Chair: Just for the record, what does that amount to, per household and per property?

Phil Stride: £3.6 billion is the estimate for the project. We have estimated that the customer bill impact would be just over £1 per week per household on the average bill, so just over £50 per year per customer.

Q74   George Eustice: Do you think that the current Waste Water NPS—the draft one—provides a sufficiently clear framework to help decision-makers make their decisions on key applications?

Richard Aylard: It is clear, but we think it could be clearer. It talks about need, specifically in terms of whether a project is included in either the Environment Agency's National Environmental Plan, or a company's Asset Management Plan. Those aren't primary sources, however. The real need comes from one of four drivers. First of all, there is a statutory requirement that we, as a company, have to meet, or it is because there is population growth that's going to occur that we need to address. It may be, thirdly, because of ageing infrastructure that needs to be replaced, otherwise it will become more expensive to run and a poor deal for customers. The fourth thing is whether it's to achieve a level of service that customers want, and are willing to pay for. In the two projects included in this NPS, they are clearly both legislative drivers, so we'd like to see a clear reference to what those legislative drivers are, and also the timescale within which the work has to be met. We'd like to see a clearer link established between the fact that a solution to a problem is needed, and needed urgently, or on a specific timetable, and that the identified project is the best way of addressing that need. That is there in the NPS, but we think it could be clearer, and specifically a reference to the individual legislation and the timescales, we believe, would help the Major Infrastructure Planning Unit in reaching their decisions.

Q75   George Eustice: Obviously when the NPS was originally conceived, it was in the era when we were going to have an Infrastructure Planning Commission. Do you think that the fact that that has now gone back into the Department, and the Secretary of State is making these decisions, changes the role of the NPS and its scope?

Richard Aylard: Not as far as we're concerned. The idea that this would be a special planning procedure for nationally significant infrastructure projects, and that the Government's policy is there for everyone to see and plan to, remains the same with the change from IPC to the Major Infrastructure Planning Unit, although of course there is parliamentary oversight added, which can only be good for democratic accountability.

Q76   George Eustice: The other thing that quite a few people have criticised is the vagueness of some of the terminology in the NPS, talking about "relevant", you shouldn't do anything that's "unacceptable", or very subjective terminology in some places. Have you got a view there about whether that should be tightened up, perhaps, by giving clearer definitions to some of those terms?

Richard Aylard: We'd always like things to be as clear as possible. On the other hand, I can see it from the other point of view: these are things that have to be weighed in the balance by the decision-makers. It's very difficult to lay down absolute hard and fast rules for everything, because what they are trying to do is make judgments. We need to make the judgment as transparent as possible, give as much information as possible, but there's a limit to how much one can direct things in general, when you're looking at very specific local impacts.

Q77   George Eustice: But are there any where you might tighten it up? I can accept things like "reasonable" and "relevant"—that leaves an element of subjectivity in things. But the other one that's cited by some is this term, "associated development", which is used—

Richard Aylard: We don't have very strong views on that. We think it would be helpful if it were included within the policy statement. If not, we have to apply separately for it through the Town and Country Planning system. It would be easier if it were together, but not insuperable, if that's what we ended up with. On balance, yes, we'd like to see it there, but it's not one of our top priority issues.

Phil Stride: In terms of clarity, going on from what Richard said, I think it would also be advantageous if there was greater clarity on the benefits that the project provided. Particularly in terms of the Thames Tunnel, for instance, being clearer about the water quality benefits, the benefits to aesthetics that we talked about previously, health to river users, and also the sustainability of the tideway of the Thames. It would be better if those benefits came out more clearly in the NPS as well. In terms of clarity, one of the comments that we struggle with on good design is "as attractive as possible", which we feel is a very subjective term and one that might lead to some debate as to what that means when we put forward a design.

Q78   Mrs Glindon: Just going on from what you said, particularly in relation to need, would you say that, from the things that you think should be included, that perhaps the criteria for proof of need isn't as robust a basis for the IPC decision-making as it should be?

Richard Aylard: When you say the criteria for need, what do you mean?

Mrs Glindon: Inclusion in the Asset Management Plan, or the National Environment Programme.

Richard Aylard: Yes. That's a good start, to reference those, but the reason that a project is in one of those two documents lies elsewhere. In the case of really big projects, it's usually with a statutory driver—we have to do it, by law, so it's quite helpful to say what the law is, and what the timescale is, rather than just saying, "If it's in the National Environmental Plan, that's good enough." We think it could go further by referring back to where that comes from.

Q79   Mrs Glindon: Do you think that the criteria are robust enough for the IPC decision-making processes?

Richard Aylard: If a project is included in the National Policy Statement, that's a pretty clear statement that the Government wants it to be done. However, if the Government can spell out more why they want it to be done, and when they want it to be done, that would help the IPC in conducting their examination. Because that's got to be set against all the local impact statements that, of course, all the boroughs will naturally come up with.

Q80   Mrs Glindon: And the things that you've said. Thank you. So do you think that the NPS should give the IPC some flexibility in interpreting whether need for a project has been determined?

Richard Aylard: Not really. In fact, "No," I think, is the answer to the question. What we want to do is get a clear statement on need, so the Government should assess that. They should do their impact assessment. They should look at what the law says, and then once all that has been done and the draft NPS has been consulted on, the need therefore should be clear. What we're trying to get away from is the previous planning situations, where an awful long time was spent discussing need before we even got on to the local impacts. If you want a streamlined process, and I think we all do, then you don't want to have too much flexibility in there. It should be restricted to the planning issues that the IPC are supposed to be looking at, rather than the wider context of the project, which should be in the policy statement.

Q81   Chair: Looking at alternatives: perhaps your project is not the best one to choose, but in other areas, are there other alternatives that, perhaps, if they had been spelled out more fully in the National Policy Statement, would have made a better contribution to the debate?

Richard Aylard: I'll leave Phil to come on to the Thames Tunnel in a minute, but if we look at Deephams Sewage Treatment Works, that's the ninth largest works in England, and it treats the waste of more than 800,000 people every day. The works is very old. It's hard to keep it working at its proper standards, and it won't meet the new standards coming in in 2017. The range of options we have is pretty limited. We don't have capacity in any of London's other sewage works to take 800,000 people's waste there, so we are faced with either redeveloping on the existing site and an adjacent site, or moving the works altogether. Therefore, the range of options is pretty limited, and they are spelled out in the NPS, although I think they could be a little bit clearer about what we actually have in mind. Our original proposals for this site were put together long before National Policy Statements were even thought of, so we will now have to have a robust site selection methodology and a proper consultation process. The point about the works at Deephams, however, is that the waste from 800,000 people converges there. If you want to build something on a different site, you are going to have to take that waste, which amounts to 200,000 tonnes of waste per day, in a pipe, and pump it somewhere else and build a new works. In terms of what alternatives you have, there isn't a great deal, other than looking at potential adjacent sites where you could do more with what's there. Do you want to talk about the alternatives for the Thames Tunnel?

Phil Stride: In terms of the Thames Tunnel, although there is reference to the other alternatives that were considered, I think it could be clearer as to what those alternatives were and how viable they were. It could also record the fact that a significant amount of work went into evaluating those various options between 2000 and 2006, and a clarity that that information was presented to the Minister at the time, who wrote to Thames Water requesting us to proceed with the tunnel option. This again was reinforced by Caroline Spelman in September last year.

Q82   Chair: My question was a more general one in other, smaller scale schemes. I'm particularly keen on looking at sustainable drainage systems, but Water UK have been quite critical, in the sense that the assumptions underlying the National Policy Statement perhaps are overly optimistic. Is that a fair comment?

Richard Aylard: We have to first of all look at the extent to which the National Policy Statement is designed to address projects that are not nationally significant infrastructure projects. By implication, it's a relevant policy consideration for works that are below the threshold, and it would be useful if that was spelled out. Certainly, in looking at any project, it's always worth looking at the alternatives. Sustainable urban drainage has certainly got a very large part to play in London, in stopping the existing problem getting worse as London grows. But given how densely populated London is, and given the nature of the geology, it's not going to play a very significant part, at least in the short and medium term, in dealing with the existing programme. You've got to have both a short-term and a longer-term solution. If the NPS were pointed at smaller projects in guidance terms, as well as the nationally significant ones, that would help to make it clearer what's to be looked at.

Q83   Neil Parish: Is the National Policy Statement strong enough on the specific sites of both Deephams and the Tunnel? Do you consider it lays out the specific needs for the project to have those sites in place, or would you prefer it to be stronger? Or am I leading you on there?

Richard Aylard: It does lay out the need for the schemes, but we then need the flexibility to, through the consultation process with local people, work out where the best sites are for actually developing the Tunnel. We need to know roughly where it needs to start, roughly where it needs to finish, and which bits we have to pick up along the way. However, exactly where those sites are is not something that should be in the policy statement. That's a matter for us to work on with local councils and local people and put our proposals to the IPC, or its successor body, to sort out.

Q84   Neil Parish: When it comes to applying for planning permission, then, you are relatively happy with where the National Policy Statement is at the moment?

Richard Aylard: In terms of the geography, yes. It does talk about the options available at Deephams, and it talks about the potential to develop an adjacent site. Again, that could be a bit clearer, but as I was saying earlier, there aren't too many options for Deephams, because of the fact that it's part of a fixed network that's been there for a very long time. We're not going to be able to rebuild the whole thing in any cost-effective way. As far as the Thames Tunnel is concerned, we know the broad route, and the individual sites are not something that should be in the Policy Statement, because it will evolve through the consultation process. Indeed, it is evolving as we speak.

Q85   Neil Parish: Is there sufficient discussion on how the IPC should balance the short-term local impacts with long-term benefits in relation to the Tunnel and Deephams?

Richard Aylard: Again it's a question of how much direction is to be given to the IPC, and how much they're to be left to make their own judgments. If the whole task is about balancing Government policy for these projects with local impacts, then they need to be left the discretion to make those trade-offs in their own way, having heard evidence from both sides. I'm not sure it's possible to give them very much clearer direction from the outset, except in general terms: The Policy Statement could talk, as it does, about the need to make sure that anything that is proposed is sustainable. There's a sustainability assessment in the National Policy Statement, which is helpful, and we welcome it.

Q86   Neil Parish: Okay, you've reinforced that. Does the Generic Impacts section of the NPS provide adequate guidance for decision-makers on the relative weight they should give to the specific impacts of the schemes?

Richard Aylard: It certainly records what the potential impacts are, the things that the IPC should be looking at—although of course they'll get very strong input from local councils through the local impact statements. The extent to which you can weight different factors depends very much on the individual locality. If you've got housing development right up to the edge of a sewage treatment works, odour is going to be a bigger factor than if you're fortunate enough to have a barrier between you and the nearest local people. The same would apply with noise. Therefore, some of those things can be looked at through a sustainability appraisal. Otherwise they have to be interpreted in a local context, and that's really the job of the IPC to do that when they have the input from the boroughs, which we think is very important.

Phil Stride: Definitely. Obviously that's been done based on the level of information there is currently—or there was a while ago, when this was done. As the scheme develops you'll be able to make those judgments in the context of more detailed information in relation to the sites. That's why, for both projects, it's been difficult to make a judgment at this stage.

Q87   Neil Parish: So when this goes to planning, you are relatively happy that, as far as you are concerned, the National Policy Statement will back up what you want to do?

Richard Aylard: Yes. It's a clear statement of policy. As I say, we thought that the need could be spelled out more clearly. There are areas where the language could be tightened up, and we're going to comment on some of those in detail in our response to Defra. But in principle, the Statement of Policy, our planning application, which will have been developed through two full stages of public consultation, and the local impact statements from the borough, give the decision-makers what they need to weigh up the proposal.

Q88   George Eustice: What you say is entirely logical, but isn't there a danger there that by not ascribing some kind of weight to these various factors, you will end up with a situation where there will be a great deal of variance in terms of how the NPS is interpreted locally, and that that therefore almost undermines the purpose of the NPS? Saying that you should take account of odour is not exactly a revelation to most people. A normal planning committee would do just that, without an NPS.

Richard Aylard: Yes, but I think they would give it a different weighting, depending on how close people were living to the site. They'd look at prevailing wind. There are a range of different local factors. Noise is a good one. If we've got people within 100 metres of a sewage works, then a noisy plant going late at night is a big problem. If we're talking about something out in the country, we wouldn't want to spend an awful lot of money on noise suppression, because there's no-one there to hear it, or no-one close enough to hear it. We have to accept that the local factors are important, but there is some pretty good guidance in there. The odour standard is one thing that we think needs to be looked at. The odour standard that's been suggested is much tighter than is in the existing Defra guidance. Existing Defra guidance talks about the need for flexibility, depending on local circumstances. There's a mismatch there that needs to be sorted out. For example, Mogden Sewage Works literally has housing development all around, and is right next to Tesco's and Twickenham rugby ground. Odour is a bigger issue there than for some of our smaller, more rural sites, which are literally out in the country.

Q89   Thomas Docherty: I understand what you're saying about smaller projects. Regarding the specifics of the two London projects that have been notified in the NPS, could you usefully have a discussion under the Generic Impacts section of the NPS about both the likely impact for the area, and what possible ameliorations would be available? My very brief reading of it is that it's quite a dry, factual section that doesn't put much flesh on as a discussion. Or do you think that's better left to the planning application itself?

Richard Aylard: To be honest, it's something that is central to the consultation process. We've just done a first phase consultation with local communities up and down the route of the proposed Thames Tunnel. We'll be doing another full phase of consultation from September, all before we submit our planning application. Local impacts are being identified by that process, and they're being addressed—in some cases we're moving sites completely. To try and spell that out in a policy statement would be too early and too prescriptive. The NPS should state that local impacts are really important. It should give a very strong emphasis on the role of the boroughs and their local impact statements, which I know some of the boroughs have concerns about. I'm sure you'll hear about those later on. We think they're important, but they're being addressed through the consultation process. There are big, big changes going on, and I think will do with any project of this scale.

Q90   Thomas Docherty: You've led me very nicely on to my next question. What impacts have been identified so far as being of particular concern from the consultations that you've had? There is possibly a difference here between what the local planning team is concerned about, and what the local residents, or resident groups, are concerned about.

Phil Stride: The main concerns are obviously where we're proposing to build on open space or recreational areas. That's been the greatest amount of push-back that we've had, currently, in people's concerns. That's followed by traffic movements taking materials to site and taking materials away, potentially. People are very concerned about traffic movements. They're also concerned about noise from the site during the construction phase, and other issues that probably aren't as prominent as that, such as light nuisance from the sites, and certainly odour as well. In that sort of order, those are the main points that people have been concerned about.

Q91   Thomas Docherty: You'll appreciate that we've had some submissions—I don't know whether you've seen them yet—from some of the local groups. It's not our job to get into the specifics of that, but could I ask a policy question? What would be your assessment of the likely cost and the impact on the project if you were to use brownfield sites—you've mentioned playing fields and so on before—rather than some of the greenfield sites you're looking at?

Richard Aylard: We're looking at very few greenfield sites.

Phil Stride: Of the 22 sites that we've currently identified as being required by the Thames Tunnel, only three of those construction sites are on greenfield sites, if you like.

Q92   Thomas Docherty: Can you just confirm which ones they are?

Phil Stride: I will go on to another category in a minute, but the main greenfield sites are Barn Elms in the London Borough of Richmond, King's Stairs Gardens in the London Borough of Southwark, and King George Park, which is in Wandsworth. Those are the three sites where we propose a construction site in a park or recreational area. There are also a couple of sites where we've proposed an access way through a park, in two cases: one in Chelsea and one in Tower Hamlets. I think you mentioned that previously. Those are the areas where we've proposed to build in a park area.

Q93   Thomas Docherty: What's the impact?

Richard Aylard: The point is that we've been out and consulted. We've got a lot of feedback. We're now assessing all of that. We're looking at what local people are suggesting. In some cases it's clear we'll be going to entirely different sites. In other cases it's clear we'll be able to propose some mitigation. Exactly what we can do is still being worked through, and will be in our consultation response, which comes out at the end of March. The costs are being worked through. In general, there is always a trade-off on costs. Communities up and down the river would like us to use the river for 100% of materials—taking the excavated material out, and bringing materials in. We can't do 100%, because that would undoubtedly be ridiculous in terms of cost. We can, however, go a long way. Exactly how far we can go, and exactly what we can do at each site, is being worked out, and will be part of the phase two consultation. Where we've had to go for greenfield sites at the moment, it's because we simply haven't been able to identify brownfield sites that are suitable where we need them. Again, in some cases that's being reworked, and there will be some different proposals in some areas when we come back with the second phase in September. It's not for want of trying. We're very clear that greenfields would be a last resort. In some cases we are currently at last resort, but we can back-check and see if we can move things in a more positive direction.

Phil Stride: Yes. We have followed our site selection methodology, which we agreed with all the London boroughs, to the letter. It clearly states in there that we would obviously prefer to use brownfield sites. We've followed that, and another point in relation to cost is that the cost difference between purchasing a brownfield site and a recreational park area isn't as great as it may appear, because although we would need 100% of the area we purchased for the construction phase of the project, we would probably only need something in the order of 15% to 20% of that area for the permanent operational site. So we would be able to sell on a large part of what we'd purchased after the scheme had been commissioned, which would obviously be netted off against the cost that we paid for it initially. So that cost differential isn't as great as it may appear.

Q94   Neil Parish: Can I follow you up on this? There is an argument that since you first put the plan through, the recession has hit, and there could well be some brownfield sites that may be available and may be available at a competitive price. I think you are saying that you are re-looking, as far as King's Stairs Gardens is concerned, or whatever. You are still looking for alternatives, are you? Is that fair to say?

Phil Stride: The key thing is that when we went out, we were sharing our proposed scheme. We'd done a certain amount of work to be able to describe to everyone involved what we planned to do. A key part of that was that we were keen for local feedback, to understand whether there was information we'd missed, things that we hadn't perhaps looked at that would have been possible. Certainly, in the case in point, the feedback we had from the residents of King's Stairs Gardens was that there was a piece of land, a brownfield site, not that far from the gardens. The developers, when we'd approached them 12 months previously, had said that by the time we got to October/November 2010, they would probably be three storeys out of the ground and the residential development would be well under way, and part of our site selection methodology was that we wouldn't, as part of this scheme, knock down residential development. Where that's occurred, we have been very proactive in understanding what that opportunity was, who was selling it, and whether there was an opportunity for Thames Water to acquire that land so that we had a brownfield site rather than a greenfield site. Certainly, whilst that situation on this particular area is commercially sensitive, we are vigorously pursuing that opportunity.

Q95   George Eustice: I wanted to get your view on the issue of how you balance out the economic costs and benefits. When we had evidence from Ofwat last week, one of the concerns they had was that, as currently drafted, the NPS envisages that the very fact that a project is listed on a project plan—business plan—signed off by Ofwat gives the impression that it's the best value option, and they were very keen to stress that that's not their role. They suggested that perhaps we needed more clarity and should include a requirement for applicants to demonstrate, within the NPS, that it was the most cost-effective option. Have you got a view on that?

Richard Aylard: Cost comes into this in two ways. The first is the base cost of delivering the project, which is something that's looked at for nationally significant infrastructure projects, by the Government, when they look at the legislation, and when they do the impact assessments. If you've got a legislative requirement, then your aim is to meet that legislative requirement at least cost, so options appraisal comes into that. That's the first stage. That should be done before the NPS is finalised. Once the NPS is finalised, cost then comes into it when you're looking at what might be done in terms of mitigation for local impacts—the kind of things that might otherwise have been done through a Section 106 agreement with councils, and things that might add to cost, such as particular design elements. We think because those things are local impacts they should be looked at in the discussions with the IPC, with the company's proposals on one hand, and the local impact statements from the councils on the other. Clearly we recognise that big projects can have big impacts, and often big localised impacts, and that those need to be mitigated, and that there's a cost to doing that. However, there is equally a reasonable limit to what that cost should be. We see it as part of the role of the IPC to establish what that cost is. In terms of whether a particular option is a cost-effective way of dealing with the need, which is driven by a legislative driver in the two cases we're talking about, we think that should be done before the NPS is finalised, rather than revisiting all of that when we get to planning.

Q96   George Eustice: So you don't think it necessarily requires some sort of benefit-to-costs ratio to be—?

Richard Aylard: Not within the discussions that take place once the NPS has been finalised. That should be done before you get to that stage. I point out again that it is very difficult to talk about whether the cost is reasonable; if you have to meet a particular legislative requirement it's a question of how cheaply that can be done effectively. The test you go through is that whatever we build has got to work, it's got to be safe, reliable, and deliver the standards. It has to be as cost-effective as possible in order to keep bills down for customers. Then there are factors like mitigation, local impacts, and design, which come into the equation as well.

Q97   George Eustice: I'm going to move on to the issue of the economic impacts on customers. As it's currently drafted, the NPS very much looks at things through the prism of the planning system, and it's all about impacts on the local economy and the economic benefits that might be delivered by an infrastructure improvement. As someone who represents a South West seat, I'm very conscious of the way that this can have an impact on water customers. Do you think that there needs to be a more explicit recognition of the impact on water customers? You mentioned the £50 increase in your bills. Does that need to be more explicitly recognised within the NPS?

Richard Aylard: It is in there, and I think it is something that needs to be looked at for each individual project. The nationally significant projects, as I say, tend to be driven by a legislative driver, so you haven't got too much flexibility there. For some of the smaller projects—in fact, for all of the smaller projects where the National Policy Statement is seen as guidance—there is already a value-for-money test before anything is included in a company's Asset Management Plan with the regulator. It's Ofwat's job to make sure that bills are as high as they need to be and no higher. There are pretty strong constraints on us as a business from going around spending customers' money that doesn't need to be spent.

Q98   George Eustice: You don't think there's a danger of future conflict between the water regulator, who set the cap about what an acceptable water bill is, and the NPS, which has a slightly different focus in the economic benefits that it weighs up?

Richard Aylard: There's always going to be that tension where you have legislative requirements that have to be met by a water company, with a system that says the costs will be borne by customers. But the existing balance in the system between Ofwat and the quality regulators, the EA and the DWI, with the Government setting policy, works as well as the system can be devised. The other question, of course, is the affordability factors, which I know the Government is looking at with the Walker Review: things like a social tariff, which we at Thames Water have been pushing, as the Chair knows, for some time, because we think there is a need to protect our least well-off customers, and I'm sure that would apply in the South West as well, although of course I don't know that area.

George Eustice: I'm sure the Chair would rather not talk about South West Water bills again, having covered it in detail previously.

Chair: The Chair remains completely impartial.

Q99   Mrs Glindon: Just going on from that, you've already mentioned design and cost. Do you think that the NPS should be specifically amended to take into account the need to balance the benefits of good design with costs? If so, would you think of any principles that the NPS should include in guiding the IPC on weighing costs against benefits?

Phil Stride: The main thing on the design element is that in terms of the design of the Thames Tunnel, which I know best, as with any design, we're trying to make sure that the project is the optimum project to deliver the scheme objectives and deliver proper value for money. That's the key objective. In terms of the engineering aspects of it, we need to make sure it delivers the function, its functionality is right, and it delivers the output that's required. Obviously a subset of that is aesthetics. It is just how you judge those and balance those together. Also, it could be reinforced to pick up operational issues. A design has to be functional—as a company, we need to be able to operate the plant once it is installed. It needs to be operated in a safe way and obviously it needs to be secure. There are lots of aspects of design that it could be clearer on, in terms of how you balance all those different parameters.

Q100   Thomas Docherty: There's always a bit of a discussion about what is consultation, and what is sharing of information. Having worked for companies that used to do consultations, I understand that there can be a difference between the two. Specifically on consultation, rather than providing information to the public, how effective do you think the consultation and dialogue has been on the preparation of the NPS with the public—specifically with the London focus on the major projects?

Richard Aylard: Regarding the NPS specifically, the Government has been consulting. We've just put a link on our Thames Tunnel consultation website to the NPS consultation. It's on the front page and it is flagged up, to try to direct people there. We've seen that you've had good input from London Councils, the GLA, the EA and others, but I'd be surprised if very many communities and individuals have been reached by it. I don't know whether that was the aim or not. It may be that this is the kind of consultation that is particularly aimed at, for want of a better word, the specialists and the statutory bodies, rather than local communities. Local communities have certainly responded in their droves to our consultation on the specific project. I think we need a different level of consultation for the NPS than for the projects that are covered within it.

Q101   Thomas Docherty: I think that's probably a fair assessment. Do you think that there are lessons, therefore, that the Government can learn, either from yourself or other organisations, about engagement with the public?

Richard Aylard: I suspect that there are. We've certainly been working very closely with the Defra officials. They came to some of our consultation exhibitions, and they've been talking to us about ways in which the two consultations can feed into each other. Consultation isn't easy. First of all there is a trade-off between starting it very early, when people say, "You haven't even thought this through yet, so why have you come to us to consult?" or leaving it too late, and then they say, "This is all decided, it isn't consultation." You have to find somewhere along the way to do it, and we've erred on the side of caution with our consultation, and started quite early. The other thing is just finding a way of reaching the individual customer, or citizen, from the Government's perspective. People tend not to read things that come through the letterbox, whatever you put on the outside of the envelope. Even when we do radio advertising, newspapers, and television interviews, a remarkable number of people say, "This is the first I've heard of it." I'm afraid this is an issue where I don't have any magic answers other than to say that Defra are working with us, and we'll continue working with them on this.

Q102   Thomas Docherty: This was my area of specialty before I came here. There's obviously a concern that the public will be surprised at the NPS, because it doesn't have an engagement. I accept the point about the statutories, and that the professional consultees are being consulted. Do you think that that is a realistic danger that we face—that we'll get to a situation in three or six months' time where there will be something of an outcry amongst the public that they haven't been adequately engaged and consulted in the NPS?

Richard Aylard: Personally I don't think so, because people will still have a very real opportunity to be consulted on the individual projects within the NPS. A lot of the content of the NPS is the thing that you'd expect the boroughs and representative bodies to be making their views known on. Perhaps you'd expect some technical organisations too. I don't think it's the stuff of individual community groups. That's just a personal view. Phil, would you agree with that?

Phil Stride: Richard and I have done over 200 external presentations over a period of time, so obviously that's helped in our getting the message out about the Thames Tunnel. The key thing that I would add to that, which perhaps has surprised us over the last six months, is particularly that when we've gone out to do public meetings and the like, we've had very little push-back about the need for the project. Of the comments that people have, comments about the need for the project have been in the low percentages. The vast majority, in the 90% area, has been about the local impact of the project. Even if you take the residents at King's Stairs Gardens, or residents of Barn Elms, they support the need for the project, but they're just very concerned about their local park. Relating that to the NPS, the NPS is about describing the need for the project, which we've had very little push-back on. Hopefully that would relate to whether there would be a public outcry about the need. I don't think there would. I think Nick Raynsford at one meeting called it "universal support" for the need for the project. In my view, having gone to many, many groups, there is heavy buy-in for the need to do the project.

Q103   Chair: Just before we release you, can I ask when you expect to do the environmental impact assessment?

Richard Aylard: Work on that has started. In order to get a sensible environmental impact assessment it has to be done over more than one season, so that work is ongoing now and it will ramp up. It will be there to accompany the planning application in the middle of next year.

Phil Stride: Yes indeed, and we'll have some initial outputs from it when we start the public consultation phase two on 5 September this year.

Q104   Chair: Is that the same for the Habitats Regulations Assessment?

Phil Stride: Yes. That work's also ongoing.

Chair: We're very grateful to you for being with us, and I'm sure we'll have other opportunities to discuss this and other matters with you in future. Thank you very much.


 
previous page contents next page


© Parliamentary copyright 2011
Prepared 5 April 2011