The draft National Policy Statement (NPS) on Waste Water - Environment, Food and Rural Affairs Committee Contents


5  Value for money

38. A number of witnesses recommended that the impacts on water customers' bills from the construction of new waste water projects should be considered by those tasked with examining planning applications for Nationally Significant Infrastructure Projects. For example, Isabel Dedring, the Mayor's Advisor on the Environment at the GLA, told us that, while it was good for the costs of a project to be lower than the benefits, the real question to ask was "is it the best value thing that you could have done?"[71] In reference to the Thames Tunnel, she considered that it was important for the IPC to look at alternative means of developing the project that brought down costs while "still delivering everything it needs to deliver." She added that this information should be publicly presented.[72] The project costs for the Thames Tunnel have increased from an estimated £2 billion when the scheme was originally proposed to some £3.6 billion now.[73] Thames Water told us that the original figure provided to Ministers in 2007 was only a "high-level estimate" based on initial work, and that they were "confident" that the project could be delivered within the current estimate.[74] Nevertheless, the scale of these cost increases is a matter of concern and there is no certainty that costs will not rise still further in response to as yet unforeseen problems that may arise during construction.

39. The Consumer Council for Water (CC Water) wanted customers, who would ultimately pay for projects, to be involved in the decision making process for new infrastructure and for a full cost-benefit analysis of the options to be set out.[75] Ofwat also noted that customers have to pay for the improvements and therefore the full costs of any investment should be carefully considered, particularly where the planning process specified requirements above the minimum, such as for 'good design' purposes.[76] Ofwat's Chief Executive, Regina Finn, told us that there was a lack of clarity in the draft NPS and that a transparent "cost-benefit assessment process or methodology" should be put at its heart. This would take into account social and environmental costs and benefits and give a clearer framework to allow impacts to be considered holistically.[77] Defra's Deputy Director for Water Supply, John Bourne, said that Ministers had considered such an approach but that the NPS was not intended to be part of a business-case system and Defra did not therefore intend to pursue this "very complicated" approach at present.[78]

40. Ofwat did not provide us with sufficiently detailed evidence on which to assess the extent to which it would be practicable to incorporate cost-benefit assessments of specific projects without adding lengthy processes to what is intended to be a streamlined spatial planning system. Approval of the costs which can be passed on to water and sewerage company customers is rightfully a core Ofwat function under its current regulatory remit and it is hard to see the benefits to be gained from duplicating this activity within the spatial planning process. In view of the alarming increases in estimated costs, Ofwat must fully utilise its regulatory powers to scrutinise the economic case for the Thames Tunnel project and be rigorous in determining which costs should be passed on to Thames Water's customers.

Cost-benefits of impact standards

41. The draft NPS specifies standards for certain impacts which are to be achieved by any waste water NSIP regardless of the costs and benefits of meeting these standards in the local circumstances of an individual project. Many witnesses, including Water UK, challenged the standards proposed for odour since the costs of achieving the specified standard would be "disproportional to the benefit". The standard should be "open to discussion and based on cost benefit analysis and customers' willingness to pay".[79] Southern Water Services considered that any standard on odour should be site-specific, should be based on modelling for odour dispersion in the locality of a proposed development, and should take into account the willingness of customers to pay.[80] Additionally, many technical submissions to Defra focussed on whether the proposed odour standards were correct.[81]

42. The Planning Act requires an NPS to set out criteria to be taken into account in the design of projects but some witnesses questioned the unqualified requirement that applicants should design infrastructure to be "as attractive ... as they can be," including visually.[82] Many witnesses wished to see this requirement for good design balanced with the costs of achieving it. For example, Ofwat noted that while the benefits of good design would accrue to those living and working in the immediate vicinity of projects, it was the whole customer base of the relevant water company which would bear the cost in the form of higher bills. The regulator argued that the draft NPS's reference in paragraph 5.5.2 should more strongly reflect the need for other constraints to be taken into account and recommended that the IPC should be required explicitly to "have regard to the affordability of the design driven by aesthetics and to weigh the associated costs against the benefits".[83] It expected companies to challenge any stringent planning requirements, including on design, if they wished to have costs of projects allowed in regulatory price limits. The regulator permitted only "reasonable net additional costs associated with the Secretary of State's final decision" to be passed on to customers. It cited examples of excessive costs such as the £50 million green roof imposed in 2008 on the Brighton sewage works and a 50% increase in project costs arising from a planning requirement to enclose a new sewage treatment works in the Anglian Region in 2002.[84] In contrast some organisations, such as the GLA, considered that the draft NPS wording should be strengthened since some developers would "not try hard enough to design infrastructure to minimise its visual and other impacts".[85]

43. It is in the interests of water and sewerage company customers as well as project applicants that the NPS should not impede the IPC's use of its own skills and experience in judging the standards to apply to projects. We recommend that Ministers clarify that the NPS does not fetter the IPC or other decision makers' ability to apply their judgement so as to impose the standards most appropriate to the local circumstances of specific projects.


71   Q 118 Back

72   Q 119 Back

73   "Thames Tunnel sewer costs could double", Water Briefing, 23 September 2010. www.waterbriefing.org Back

74   Q 72 Back

75   Ev w4 Back

76   Ev 45  Back

77   Q 7 Back

78   Q 206  Back

79   Ev w7 Back

80   Southern Water Services, Submission to Defra NPS Consultation, February 2011.  Back

81   For example submissions from Thames Water, Chartered Institute for Environmental Health, Ofwat. Back

82   Draft NPS, p 30, paras 5.5.2 and 5.5.3. Back

83   Ev 46  Back

84   Ev 45  Back

85   Ev 57  Back


 
previous page contents next page


© Parliamentary copyright 2011
Prepared 5 April 2011