6 Draft Budget 2011
(a)
(31644)
SEC(10) 473
(b)
(31998)
13644/10
SEC(10) 1064
| Statement of estimates of the European Commission for the financial year 2011 (Preparation of the 2011 Draft Budget)
Amending Letter No 1 to the draft General Budget 2011
|
Legal base | Article 314 TFEU; co-decision; QMV
|
Deposited in Parliament | (b) 6 October 2010
|
Department | HM Treasury
|
Basis of consideration | (a) Minister's letter of 16 September 2010
(b) EM of 30 September 2010
|
Previous Committee Report | (a) HC 428-i (2010-11), chapter 5 (8 September 2010)
(b) None
|
Discussion in Council | 15 July 2010
|
Committee's assessment | Politically important
|
Committee's decision | (a) For debate on the floor of the House (decision reported 8 September 2010, debate took place on 13 October 2010)[18]
(b) Cleared
|
Background
6.1 The Commission's Draft Budget (DB) is the first stage in the
annual process of establishing the EU's budget for the following
year. The 2011 DB sets out the Commission's proposals for EU expenditure
in 2011, together with bids for the other institutions, such as
the European Parliament. It provides the basis for negotiations
between the two arms of the Budgetary Authority (the Council and
the European Parliament), which will result in the adoption of
the General Budget by the end of 2010.
6.2 The 2011 Budget will be the first to be adopted
according to a new procedure introduced by the Lisbon Treaty.
The Council's first reading position on the DB was adopted on
12 August 2010 (the TFEU requires the Council to complete this
stage by 1 October), which was then forwarded to the European
Parliament. The European Parliament will in turn discuss and agree
its first reading position by mid-October 2010 (the TFEU deadline
is 42 days after the Council adopts its position). If it proposes
further amendments to those made by the Council, a conciliation
committee would be convened to meet over 21 days, largely in late
October and early November, with the aim of reaching agreement
on the 2011 Budget. This will be subject to separate approval
by both the Council and the European Parliament, after which the
EU's Budget for 2011 will be deemed to have been adopted. Between
the Commission's presentation of the DB and its final adoption
it issues a number of Amending Letters, most of which propose
technical adjustments, often arising from updated financial data.
6.3 The context for the DB is determined by the multi-annual
Financial Framework, which sets out annual ceilings for the five
permanent and one temporary headings of budget expenditure: sustainable
growth, preservation and management of natural resources, citizenship,
freedom, security and justice, the EU as a global player, administration
and compensation (temporary measures for Bulgaria and Romania
in their first years of accession, which no longer apply). The
DB for 2011 is the fifth of the 2007-2013 Financial Framework.
6.4 It is customary for the Government to supplement
its Explanatory Memorandum on the DB with reports on the significant
further stages of the negotiation of the Budget. Such reports
cover any Amending Letters that have issued, unless they are sufficiently
important to warrant separate deposit in Parliament for scrutiny.
6.5 We first considered the DB for 2011 on 8 September
2010, when we recommended it for debate on the Floor of the House.[19]
The Minister's letter
6.6 The Economic Secretary to the Treasury (Justine
Greening) first emphasises the Government's over-riding priority
for this annual budget negotiation. She says that:
- at a time of profound fiscal
consolidation across the EU it is not acceptable for the EU budget
to grow and especially not at the proposed rate of 6%;
- the budget cannot be immune to the economic and
financial pressures acting on Member States across the EU;
- it must contribute to fiscal consolidation efforts;
and so
- the Government has repeatedly called for the
budget to be frozen at its 2010 level and for greater value for
money within the budget.
6.7 The Minister then tells us that:
- the process for agreeing the
Council's first reading position this year varied from the norm;
- a Budget ECOFIN Council was not held, after the
position was agreed at official level in Council's Budget Committee
and at COREPER;
- adoption of the first reading position was completed
by written procedure on 12 August 2010, rather than at a Ministerial
Council;
- this unusual process was necessary this year
to ensure that national parliaments were allowed the due eight
weeks to conduct scrutiny of the Commission's DB before the Council
agreed its first reading position (the Commission formally deposited
the DB in all parliaments only in late June 2010); and
- UK officials in Brussels pushed hard to ensure
that this period was preserved, contrary to the institutions'
original plans.
6.8 Of the Council's first reading position itself
the Minister says that:
- It was agreed by a qualified
majority;
- the UK and six other Member States voted against
it all others supported it;
- those that joined the UK in opposing the position
were Austria, the Czech Republic, Denmark, Finland, the Netherlands
and Sweden.
6.9 She continues that the Government opposed the
Council's first reading position because it did not sufficiently
reflect the objectives of achieving a cash freeze in the 2011
Budget, greater value for money in EU expenditure and adequate
margins below the Financial Framework ceilings.
6.10 The Minister explains that:
- the first reading position
reduced payment appropriation levels by 3,609 million (£2,977
million), or 2.77%, from the Commission's DB;
- payment appropriation levels nevertheless remained
3,571 million (£2,945 million), or 2.91%, higher than
in the 2010 Budget, at 126,527 million (£104,359 million);
- the first reading position also reduced commitment
appropriation levels by 788 million (£650 million),
or 0.55%, from the DB;
- this resulted in an overall commitment appropriation
figure of 141,777 million (£116,938 million)
285 million (£235 million), or 0.22%, higher than in
the 2010 Budget;
- the Council reduced commitment and payment appropriation
levels in some areas of spend that the Government assesses as
poor value for money, including administration and agricultural
market interventions under the Common Agricultural Policy;
- the Government's view was that the Council did
not go far enough in targeting both these areas, as well as those
where very large increases had been proposed without full justification
and those where a poor implementation rate in the past meant that
the budget proposed for 2011 seemed unrealistic; and
- at the same time, the Government's view was that
Council went too far in reducing appropriations for some areas
of high value for money spend within the budget, for which increases
were duly justified and implementation is historically strong
this included, for example, some programmes under the
competitiveness for growth and employment heading.
6.11 The Minister encloses with her letter tables
summarising overall commitment and payment appropriation levels
in the Council's first reading position, which we annex. She also
gives us a heading-by-heading breakdown.
Sub-Heading 1a (Competitiveness for growth and
employment)
6.12 On this Sub-Heading the Minister says that the
Council's position reduces commitment and payment appropriations
by 47 million (£39 million) and 891 million (£735
million) respectively, compared to the Commission's DB, that the
margin under the Financial Framework ceiling for commitment appropriations
was increased to 97m (£80m) and that the decreases
reflect reductions in a number of areas, including:
- a 7.40 million (£6.10
million) reduction in commitment appropriations and a 217
million (£179 million) reduction in payment appropriations
on the "Co-operation" budget lines of the 7th Research
Framework Programme;
- other reductions in that programme 67.20
million (£55.40 million) in payment appropriations on the
"Capacities" budget lines, 100 million (£82
million) in payment appropriations on the "Ideas" budget
line and 100 million (£82 million) in payments on the
"People" budget line;
- a 100 million (£82 million) reduction
in payment appropriations for financial support for projects of
common interest in the Trans-European Transport Network;
- a 0.90 million (£0.70 million) reduction
in commitment appropriations and a 85.90 million (£70.90
million) reduction in payment appropriations for the Competitiveness
and Innovation Programme; and
- a 10.10 million (£8.30 million) reduction
in payment and commitment appropriations for administrative management
and staff costs.
Sub-Heading 1b (Cohesion for growth and employment)
6.13 The Minister says that the Council's position
here reduces payment appropriations by 1,075 million (£887
million) compared to the DB and that there were no changes to
commitment appropriations the margin under the Financial
Framework ceiling for commitment appropriations therefore remains
17 million (£14 million). She continues that reductions
in payment appropriations were made largely through:
- a decrease of 551 million
(£454 million) for the European Regional Development Fund,
including a reduction of 165 million (£136 million)
for completion of 2000-2006 programmes;
- a decrease of 249 million (£205 million)
for the European Social Fund, including a reduction of 120
million (£99 million) for completion of 2000-2006 programmes;
and
- reduction of 275 million (£227 million)
for completion of pre-2007 projects under the Cohesion Fund.
Heading 2 (Preservation and management of natural
resources)
6.14 Here the Minister tells us that the Council's
position reduces commitment and payment appropriations by 475
million (£392 million) and 821 million (£677 million)
respectively compared to the DB, that the margin under the Financial
Framework ceiling for commitment appropriations was increased
to 1,326 million (£1,094 million) and that these decreases
largely reflect targeted reductions in the following areas:
- a 420 million (£346
million) decrease in payment and commitment appropriations for
the accounting clearance of previous years' accounts with regard
to shared management expenditure under the European Agriculture
Guidance and Guarantee Fund and the European Agriculture Guarantee
Fund;
- a decrease of 98 million (£81million)
in payment appropriations in rural development programmes on the
basis of anticipated implementation rates;
- a decrease of 95 million (£78 million)
in payment appropriations for the convergence objective under
the European Fisheries Fund;
- a decrease of 39 million (£32 million)
in both payment and commitment appropriations in relation to market
interventions; and
- a decrease of 38 million (£31 million)
in payment appropriations for Life+ (financial instrument for
the environment, 2007-2013).
Sub-Heading 3a (Freedom, security and justice)
6.15 In relation to this Sub-Heading the Minister
tells us that the Council's position reduces commitment and payment
appropriations by 10.90 million (£9 million) and 49.60
million (£40.90 million) respectively, compared to the DB,
that the margin under the Financial Framework ceiling for commitment
appropriations was increased to 81.70 million (£67.40
million) and that the decreases largely reflect targeted reductions
in the following areas, in some cases decreasing substantial proposed
increases so as to bring appropriations levels more into line
with likely implementation:
- a reduction of 9.50 million
(£7.80 million) in payment appropriations for the European
Fund for the Integration of Third Country Nationals;
- a reduction of 9.10 million (£7.50
million) in payment appropriations for the European Return Fund;
- a reduction of 8.40 million (£6.90
million) in payments for the External Borders Fund;
- a reduction of 4.30 million (£3.50
million) for the "prevention and fight against crime"
programme; and
- a reduction of 4 million (£3.30 million)
for criminal and civil justice budget lines.
Sub-Heading 3b (Citizenship)
6.16 In this connection the Minister says that the
Council's position increases commitment appropriations by 0.16
million (£0.13 million), that this is due to inclusion of
4 million (£3.30 million) in commitment appropriations
and 1 million (£0.80 million) in payment appropriations
for preparatory action for preservation of commemorative sites
in Europe, intended to cover costs related to long-term conservation
works of sites such as the Auschwitz-Birkenau concentration camp,
which is currently facing serious deterioration due to climatic
conditions and its age, that this increase is offset by a reduction
in commitment appropriations of 1.49 million (£1.22
million) for the decentralised agencies under this Sub-Heading,
that the position reduces payment appropriations by 19.30
million (£15.90 million), compared to the DB, that the margin
under the Financial Framework ceiling for commitment appropriations
was decreased to 15 million (£12 million) and that
the decreases comprise reductions in the following areas, aligning
appropriations levels more closely with anticipated needs and
implementation rates:
- a decrease of 8.10 million
(£6.7 million) in payment appropriations for EU action in
the field of health;
- a decrease of 3.90 million (£3.20
million) in payment appropriations for the Culture Programme 2007-2013;
and
- a decrease of 2 million (£1.60 million)
in commitment appropriations and 6 million (£4.90 million)
in payment appropriations for civil protection within the EU.
Heading 4 (EU as a global player)
6.17 On this Heading the Minister says that the Council's
position reduces commitment and payment appropriations by 93.70
million (£77.30 million) and 590.90 million (£487.40
million) respectively, that the margin under the Financial Framework
ceiling for commitment appropriations was increased to 164.10
million (£135.30 million) and that the decrease in payment
appropriations is partly due to removal of 203 million (£167
million) for the Emergency Aid Reserve. On the last point she
comments that the commitment appropriations level of the Reserve
every year is set in the Inter-Institutional Agreement, that appropriate
payment appropriations are made available for it throughout the
year, as needed to respond to emergency needs and that, therefore,
the Council considers that payment appropriations do not need
to be presented in its first reading position. The Minister continues
that the remaining reductions largely reflect targeted decreases
in the following areas, often bringing appropriations levels closer
into line with implementation rates:
- a reduction of 52 million
(£43 million) in commitment appropriations and 191.20
million (£157.70 million) in payment appropriations for the
Instrument for Pre-Accession;
- a reduction of 44 million (£36 million)
in payment appropriations for the Instrument for Stability;
- a reduction of 45 million (£37 million)
in payment appropriations for the Development and Cooperation
Instrument, including 40 million (£33 million) on the
budget line "environment and sustainable management of natural
resources, including energy";
- a reduction of 30 million (£25 million)
in payment appropriations for the European Instrument for Democracy
and Human Rights; and
- a reduction of 24.70 million (£20.40
million) in both commitment and payment appropriations for expenditure
on administrative management.
Heading 5 (Administration)
6.18 Here the Minister says that the Council's position
reduces commitment and payment appropriations by 162.20
million (£133.80 million) compared to the DB, that the margin
for commitment appropriations under the Financial Framework ceiling
is increased to 322.80 million (£266.20 million) and
that the reduction in the Heading was established by:
- limiting the increase in administrative
expenditure of the institutions, apart from the European Parliament,
by setting budgets based on each institution's specificities and
real and justified needs;
- making targeted reductions on certain budget
lines for the institutions, taking into account actual spend in
2009 and real needs;
- accepting only part of the appropriations requested
in relation to Croatia's accession, on the basis of accession
in 2012;
- not accepting the institutions' budgeting for
an additional 1.85% salary increase relating to the 2009-2010
budget period, pending a decision on this issue by the European
Court of Justice;
- increasing the standard flat rate abatement on
salaries for most of the institutions, taking into account their
current vacancy rate;
- not accepting any new posts requested by the
institutions, with the exception of 11 posts for the European
Council, because it is a new institution; and
- reducing the levels of budgets for the decentralised
agencies, with the aim of bringing budgets closer into line with
real needs the approach was to limit budget increases
for agencies at "cruising speed" to a maximum of 1.5%;
and to a maximum of 3% for agencies with new tasks to perform,
allowing for half of the new posts requested by the agencies to
be established.
6.19 The Minister adds that the proposed budgets
of new agencies were left unchanged by the Council, with the exception
of the agency for operational management of large-scale IT systems
under Sub-Heading 3a for this new agency appropriations
for six months were granted and the staff posts proposed were
accepted.
6.20 The Minister says that the Council's first reading
position was accompanied by two draft declarations:
- the first, as is customary,
calls on the Commission to submit draft amending budgets throughout
next year if the appropriations entered in the 2011 Budget prove
insufficient to meet needs under Headings 1, 2 and 4; and
- the second deals more specifically with Sub-Heading
1b, urging the Commission to present latest figures and estimates
by the end of September 2011, as well as a draft amending budget,
if required.
6.21 Finally the Minister tells us that:
- the European Parliament is
considering the DB and the Council's amendments and will form
its own position on the 2011 Budget;
- the Council and European Parliament will then
meet in a three-week conciliation committee from the end of October
2011, to agree the final budget;
- the Government's objectives during this process
will remain consistent with its approach so far; and
- it will be working very hard with other Member
States and with the European Parliament to secure the best possible
outcome for British taxpayers.
The new document
6.22 The Commission's Amending Letter No 1, document
(b), proposes amendments to its DB for 2011, specifically to the
establishment plans and budgets of three institutions in Heading
5 (Administration) the Commission, the Council and the
European External Action Service (EEAS) to reflect the
latter's establishment this year. It was not possible to include
these figures in the Commission's original DB, as the Council
Decision establishing the EEAS was not adopted until 26 July 2010.
6.23 In the Amending Letter the Commission:
- says that an effective EEAS
is important to allow the EU to strengthen its role on the world
stage, giving it more profile and increasing its capacity to communicate
its interests and values more efficiently;
- continues that it can add value through combining
the financing instruments available and bringing together expertise
from the Commission, the Council and Member States' diplomatic
services;
- summarises the financing requested for the EEAS
in 2010, as set out in Draft Amending Budget No 6 for the 2010
EU Budget;[20]
- requests the budgetary resources needed to allow
a viable and efficient start-up for the EEAS in 2011;
- says that the service's establishment must be
guided by the principles of cost efficiency, budget neutrality
and sound and efficient management and must bear in mind the impact
of the current economic crisis on national public finances and
the necessary fiscal consolidation efforts in Member States;
- says the EEAS will be built up gradually and
through transitional arrangements unnecessary duplication
of tasks, functions and resources with other structures must be
avoided and all opportunities for rationalisation and streamlining
used;
- explains that departments and functions of the
Council and Commission will be transferred to the EEAS, as detailed
in the Annex to the July 2010 Decision and each official transferring
will be allocated to a post in the function group corresponding
to their grade;
- says that the 2011 draft budgets and the establishment
plans of the Commission and Council are reduced accordingly; and
- says that service level agreements (for example
for IT services or translation) will be concluded between the
EEAS and the Commission and Council Secretariat, to be reviewed
and adjusted if needed once the EEAS is fully up and running.
6.24 The Amending Letter shows total administrative
expenditure for the EEAS in 2011 as 475.80 million (£392.4
million), including 184.90 million (£152.50 million)
in Brussels and 290.90 million (£239.90 million) in
delegations around the world. The breakdown of this expenditure
follows.
Establishment plan and related remuneration cost
6.25 The total number of staff in the EEAS establishment
plan is 1,643, with total remuneration expenditure estimated at
211.90 million (£174.80 million). This includes 1,114
posts transferred from the Commission and 411 from the Council.
675 Commission and 386 Council posts are transferring from headquarters
in Brussels, with an associated cost of 74 million (£61
million) and 37 million (£30.50 million) respectively.
439 Commission and 25 Council posts are transferring from delegations,
with associated costs of 78.40 million (£64.70 million)
and 3.90 million (£3.20 million) respectively.
6.26 In addition, the EEAS establishment plan includes
new posts. 100 new posts were requested in 2010, 20 for headquarters
and 80 in delegations, with a full-year cost in 2011 of 17.40
million (£14.40 million). The Commission also requests an
additional ten Administrator posts for nine months and eight Assistant
posts for six months, with a cost in 2011 of 1.20 million
(£0.99 million), saying that these additional posts will
handle the increased workload derived from the EEAS taking on
tasks previously carried out by the rotating Presidency and flowing
from the Lisbon Treaty and strengthen the EEAS' capacity to function
autonomously.
Other human resources
6.27 The Commission says that that the EEAS will
also have an estimated 2,077 full-time equivalent (FTE) human
resources, including seconded national experts, contract agents,
agency staff and local agents in delegations. The associated spend
is 70.40 million (£58.10 million), of which 58.30
million (£48.10 million) is transferred from the Commission
budget and 9.60 million (£7.90 million) from the Council.
These resources cover an estimated 80 FTE in Commission headquarters
and 1,664 in delegations. As foreseen in the EEAS agreement, none
of the Commission delegation staff working on development cooperation
will transfer into the EEAS. From the Council side, staff working
on Common Foreign and Security Policy and European Security and
Defence Policy are covered an estimated 260 FTE
and an estimated three FTE working in the liaison offices in New
York and Geneva. The Draft Amending Budget No 6 for 2010 requested
an additional ten contract agents in headquarters and 60 local
agents in delegations, with an associated cost in 2011 of 2.50
million (£2.10 million).
Other administrative expenditure
6.28 A total of 193.5 million (£159.6
million) in other administrative expenditure, comprising 148.50
million (£122.50 million) from the Commission budget, 31.60
million (£26.10 million) from the Council's, 9.40 million
(£7.80 million) resulting from Draft Amending Budget No 6
to the 2010 budget and 4.00 million (£3.30 million)
entirely new expenditure in 2011, is requested:
- 36.20 million (£29.90
million) for other staff-related expenditure, including training,
medical services and travel of this, 29.60 million
(£24.40 million) is transferred from the Commission budget
and 5.00 million (£4.10 million) from the Council;
- 1.30 million (£1.10
million) to cover needs arising from recruitment of additional
staff in 2010 and 0.30 million (£0.20 million) to cover
needs related to the 18 additional posts requested for 2011;
- 157.30 million (£129.70 million) for
buildings, equipment and other operating expenditure, including
IT;
- buildings and related expenditure in the EEAS
budget for 2011 amounts to 112.70 million (£93.00 million)
the High Representative is expected to take a decision
on the EEAS premises by the end of October 2010, which will have
an impact on current estimates and may lead to a request for further
appropriations next year;
- the Commission budget transfers 91.2 million
(£75.20 million) to the EEAS 12.30 million
(£10.10 million) for headquarters and 78.90 million
(£65.10 million) for delegations and the Council budget transfers
12.10 million (£10.00 million) to the EEAS
6.90 million (£5.70 million) at headquarters and 5.20
million (£4.30 million) for the liaison offices). In addition,
6.00 million (£4.90 million) is to cover needs for
buildings related to additional posts created in 2010
0.40 million (£0.30 million) at headquarters and 5.60
million (£4.60 million) in delegations) and 0.10 million
(£0.08 million) to cover corresponding needs for the additional
18 posts requested for 2011 and 3.30 million (£2.70
million) to cover urgent needs for upgrading the security in some
premises; and
- 44.60 million (£36.80 million) for
IT, equipment and other operating expenditure. 27.70 million
(£22.80 million) of this is transferred from the Commission
budget, 5.80 million (£4.80 million) for headquarters
and 21.90 million (£18.10 million) for delegations
and 14.50 million (£12.00 million) is transferred from
the Council budget 14.30 million (£11.80 million)
at headquarters and 21.90 million (£18.10 million)
for delegations. 2.10 million (£1.70 million) is to
cover needs related to the additional posts created in 2010
0.20 million (£0.16 million) at headquarters and 1.90
million (£1.60 million) for staff in delegations and 0.30
million (£0.20 million) is to cover needs associated with
the additional 18 posts proposed for 2011.
6.29 In the context of a gradual build up the Commission
recalls the senior management structure set out in the Decision
of July 2010 an Executive Secretary General, two Deputy
Secretaries General and a very senior official responsible for
budget and administration and there will also be senior posts
responsible for thematic and geographical areas. It says that:
- ultimately the senior management
structure will cover the full range of the High Representative's
responsibilities;
- while some of the additional resource demands
of the EEAS (stemming, for example, from taking over the rotating
Presidency tasks) will be absorbed by efficiency gains of merging
existing Commission and Council units, there may be further resource
demands in future;
- the EEAS has a target of 10% efficiency savings
in headquarters spending, by eliminating duplication, exploiting
synergies and modernising working methods this will help
to achieve budget neutrality once the initial start-up phase,
with associated costs, has been completed;
- in order to achieve the target of one third of
EEAS posts filled by Member States' diplomats by 2013, it might
be necessary to convert some of the existing seconded national
experts, and Assistant posts, into Administrator posts;
- over time the functions of the EU Special Representatives,
currently funded under the Common Foreign and Security Policy,
will be integrated into the EEAS;
- the High Representative will work up a detailed
EEAS organisational structure with the senior management team,
once appointed, on the basis of these principles;
- once the initial transition of units and new
posts into the EEAS has been completed, there may be possible
additional requests for funding in the course of 2011.
6.30 The Commission also sets out in detailed tables
the changes to the establishment plans of the three institutions
concerned and, in an annex, the line-by-line changes to the institutions'
budgets to reflect the transfers of costs concerned.
The Government's view of the new document
6.31 On the Amending Letter, document (b) the Minister
says that:
- the Government wants to ensure
that the EEAS is able to deliver its objectives and work effectively
for the Member States;
- it acknowledges that some additional funding
is required in the EEAS' first full year, as the necessary rationalisation
and streamlining will not happen immediately in practical
terms some new staff posts must be created to handle new tasks
and there are physical moving costs as units from the existing
institutions merge;
- at a time, however, when governments throughout
the EU are taking difficult decisions to reduce their public spending,
including on their own national administrations, the Government
believes it is essential that the EEAS demonstrates value for
money, budget discipline in its funding bids and a firm commitment
to real and substantial cost efficiencies right from the start;
- the additional resources requested for the EEAS
make up 34.50 million (£28.50 million), or 7.3%, of
its total budget;
- the Government will be questioning closely the
rationale given for these additional funds, to ensure they are
properly justified in every case;
- more broadly it will push for cost and efficiency
savings throughout the EEAS, both in the 2011 Budget and in the
years immediately following;
- rather than highlighting the possible need for
further additional funds next year, the Government believes the
Amending Letter should be accompanied by a clear cost savings
plan, beginning from 2011, that demonstrates the means through
which the long-term budget neutrality referred to in the Decision
of 26 July 2010 will be reached;
- the Government will push both for immediate savings
on the 2011 Budget and for this long-term reassurance of savings
in the future in the course of negotiations on the EEAS budget
for next year;
- it will continue to highlight that policy objectives
leading to additional resource requirements by the EEAS must be
clearly elaborated and will recall throughout that these must
respect the role of national diplomatic services; and
- given that the Government is pushing for the
2011 EU Budget to be maintained at a cash level equivalent to
2010, it believes that additional funding for the EEAS should
be accommodated through reductions elsewhere in the 2011 DB
in line with its push to ensure cost savings and reduce low value
for money expenditure throughout the EU Budget.
6.32 As for the financial implications of the Amending
Letter the Minister, noting that of the total budget of the EEAS
in 2011 of 475.80 million (£392.40 million), that 34.50
million (£28.50 million) is additional expenditure and 441.30
million (£364 million) is the cost of Commission and Council
units transferring into the EEAS and that these costs are in both
commitment and payment appropriations, says that:
- Member States contribute to
the EU Budget as a whole, and not to single initiatives or institutions
within it;
- the UK contribution to the EU Budget in 2011
will therefore play a part in financing the EEAS, determined according
to the UK's GNI share next year;
- as an indicative guide only, the UK's GNI share
contribution to the 2010 budget is currently assessed at 13.8%;
and
- applying this to the EEAS budget would indicate
UK contributions pre-abatement of around 65.66 million (£54.20
million) to the total EEAS budget, of which 60.90 million
(£50.20 million) would be to the existing costs of the Commission
and Council and 4.76 million (£3.93 million) to the
additional EEAS costs.
Conclusion
6.33 We are grateful to the Minister for her account
of the Council's first consideration of the Draft Budget for 2011.
We applaud the Government's intentions in relation to limiting
budget increases and seeking value for money. We look forward
to hearing the outcome of the European Parliament's first reading
of the Draft Budget.
6.34 We note the Commission's Amending Letter
No 1, document (b), and the Government's robust view of it. As
it will be subsumed in the continuing discussions of the overall
budget, whilst drawing it to the attention of the House, we clear
it from scrutiny.
Annex
Draft Budget 2011 ( million)
Heading
| FF Ceiling1
| Commission's Draft Budget 2011
| Council's first reading position
| Difference between draft budget 2011 - Council's first reading
|
|
| CA2
| PA3
| CA
| PA
| CA
| PA
|
1a. Competitiveness for Growth and Employment
Margin4
1b. Cohesion for Growth and Employment
Margin
| 12,987
-
50,987
-
| 13,437
50
50,970
17
| 12,110
-
42,541
-
| 13,390
97
50,970
17
| 11,219
-
41,466
-
| -47
-
0
-
| -891
-
-1,075
-
|
2. Preservation and Management of Natural Resources
Margin
| 60,338
-
| 59,486
852
| 58,136
-
| 59,011
1,326
| 57,315
-
| -475
-
| -821 |
3a. Freedom, Security and Justice
Margin
3b. Citizenship
Margin
| 1,206
-
683
-
| 1,135
71
668
15
| 853
-
639
-
| 1,124
82
668
15
| 803
-
620
-
| -11
-
0.2
-
| -50
-
-19
-
|
4. European Union as a Global Player
Margin5
| 8,430
-
| 8,614
70
| 7,602
-
| 8,520
164
| 7,011
-
| -94
-
| -591
-
|
5. Administration
Margin6
| 8,334
-
| 8,255
161
| 8,256
-
| 8,093
323
| 8,094
-
| -162
-
| -162
-
|
TOTAL (1)
| 142,965 | 142,565
| 130,136 | 141,777
| 126,527 | -788
| -3,609 |
Due to rounding, figures in difference column may
not equal column differences, and sum of rows may not equal total.
Draft Budget 2011 (£ million)
Heading
| FF Ceiling1
| Commission's Draft Budget 2011
| Council's first reading position
| Difference between draft budget 2011 - Council's first reading
|
|
| CA2
| PA3
| CA
| PA
| CA
| PA
|
1a. Competitiveness for Growth and Employment
Margin4
1b. Cohesion for Growth and Employment
Margin
| 10,712
-
42,054
-
| 11,083
41
42,040
14
| 9,988
-
35,088
-
| 11,044
80
42,040
14
| 9,253
-
34,201
-
| -39
-
0
-
| -735
-
-887
-
|
2. Preservation and Management of Natural Resources
Margin
| 49,767
-
| 49,064
703
| 47,951
-
| 48,672
1,094
| 47,273
-
| -392
-
| -677
-
|
3a. Freedom, Security and Justice
Margin
3b. Citizenship
Margin
| 995
-
563
-
| 936
59
551
12
| 704
-
527
-
| 927
67
551
12
| 662
-
511
-
| -9
-
0.13
-
| -41
-
-16
-
|
4. European Union as a Global Player
Margin5
| 6,953
-
| 7,105
58
| 6,270
-
| 7,027
135
| 5,783
-
| -77
-
| -487
-
|
5. Administration
Margin6
| 6,874
-
| 6,809
133
| 6,810
-
| 6,675
266
| 6,676
-
| -134
-
| -134
-
|
TOTAL
| 117,918 | 117,588
| 107,336 | 116,938
| 104,359 | -650
| -2,977 |
Due to rounding, figures in difference column may
not equal column differences, and sum of rows may not equal total.
18 HC Deb, 13
October 2010, cols 409-59. Back
19
See headnote. Back
20
(31728) 11251/10: see HC 428-i (2010-11), chapter 17 (8 September
2010). Back
|