6 Appendix
1
Supplementary evidence submitted by the Department
for International Development on Procurement Information
The IDC asked two additional questions:
1. Can we have a breakdown of the £374m
paid to suppliers of technical assistance?
Breakdown of 2009/10 spending on Technical
Assistance:
Source is DFID ARIES 1660 Account Code
payments in 2009/10. Includes spending over £100k (OJEU procurement
limit), excludes spend on admin consultancy of £19.1m (not
Technical Assistance)
2) Which
suppliers are currently working on contracts worth more than £10m,
how much the contract is worth, what its purpose is and in which
country it operates?
Details of current supplier contracts with a value
greater than £10m:
/cont.
/continued:
Source DFID Alito database: live contracts with
value over £10m
|