Delivering Multi-Role Tanker Aircraft Capability - Public Accounts Committee Contents


Supplementary memorandum from HM Treasury

Delivering Multi-Role Tanker Aircraft Capability

  During its hearing on "Delivering Multi-Role Tanker Aircraft Capability" on Monday 26 July, the Committee of Public Accounts asked HM Treasury to send it further information on three points.

  Firstly, HM Treasury was asked whether it considered it acceptable to use PFI as a procurement method for defence projects in general.

  There is no reason why PFI should not be considered for defence projects. The Ministry of Defence has assigned 54 PFI projects and of these has a current portfolio of 45 operational PFI projects, the majority of which are operating successfully. Although less widely adopted than in the United Kingdom, several countries (such as The Netherlands, the United States and Australia) have used PFI/PPP as a procurement route for defence infrastructure such as headquarters and accommodation.

  In general, there is increased scope for benefits in equipment based PPPs, as the linkages between design and long-term operation, and between build and maintenance, are much greater for equipment-based projects. Although operational and security related issues tend to narrow the potential for PFI in relation to defence equipment projects, these issues are not insurmountable in every case. So, whereas it is correct to suppose that PFI is inappropriate for tanks, attack aircraft and warships which need to be deployed flexibly and are operated and maintained (at least in part) by service personnel, PFI can be appropriate in areas such as training (for example, helicopter simulators), support tasks (for example, the Heavy Equipment Transporter and strategic sealift/roll on-roll off ferries deals) and ancillary services (for example, dockyard tenders). Overseas, France and Greece have delivered defence equipment PPPs for training helicopters and simulators.

  The Committee secondly asked whether the Treasury considers that the approximately 10% added to the cost of the project as the premium to be paid for increased risk transfer in PFI is reasonable.

  Finance can be considered in the same way as other project inputs; for example, the increased cost of utilising better building materials needs to be considered against the benefits in terms of reduced whole life running costs. The scale of the benefits that are delivered by the risk transfer enabled by private financing depend on the nature of the project. (The aim of the qualitative assessment of value for money prior to launching a PFI project (see attached copy guidance issued by HM Treasury in November 2006)[26] is to ascertain those aspects of a project which could deliver benefits that would outweigh the increased financing costs). Delivering benefits of greater than 10% of the total project costs is considered reasonable.

  For example, a review of business cases presented to the Treasury's Project Review Group for allocation of PFI credits show that local authorities estimate a net value for money position (ie the benefits in terms of reduced whole life costs of the project when offset by the increased cost of financing, discounted at 3.5%) of better than 10% is not uncommon. As mentioned above, there is usually an increased scope for benefits in equipment based PFIs such as the Future Strategic Tanker Aircraft (FSTA).

  The Treasury was thirdly asked to clarify whether the Ministry of Defence was given an exemption from the 3.5% discount factor outlined in the updated Green Book rules of 2003, and instead allowed to calculate net present values based on a 6% discount factor.

  In 2003, the Green Book guidance on assessing public sector spending and investment was updated. The previous 6% discount rate provided not only the net present value of the options but also included the risk figures for the project. Under the new guidance the risk assessment is separated out into a separate assessment, and the discount rate has been reduced to reflect this. Projects that were started under previous Green Book guidance were allowed to continue using the 6% discount factor as their value for money benchmark. This was true for all departments who had PFI projects that had issued their Invitation to Tender prior to 2003. See paragraph 9 of the attached copy of Treasury guidance letter of 26 April 2003 to all departments.[27]

  It was appropriate to use this policy for the FSTA project. The project was started in 1999 when the old guidance was still in place, and the 6% discount factor had been used at the time of formal engagement with industry in the issuance of the Invitation to Tender—the key value for money point for deciding whether or not to pursue PFI as the procurement route. Value for money comparisons were re-conducted later at both the 6% and the 3.5% discount factor rates and the National Audit Office report makes clear that deal was favourable on all but one value for money comparison (of eight).

Alternate Treasury Officer of Accounts

HM Treasury

3 September 2010







26   Not printed here. Back

27   Not printed here. Back


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2010
Prepared 16 September 2010