Examination of Witnesses (Questions 1-192)
ANDREW HUDSON, CHARLES LLOYD AND ANDY ROSE
26 OCTOBER 2010
Q1 Chair:
Welcome. We are a relatively new Committee, with, I think, only
two familiar faces to those of you who have appeared before, so
we look forward to hearing the evidence you have to give on this
really important topic. Can I start the ball rolling? Having
read the National Audit Office Report, one of the things that
struck me was that the banks stopped lending in 2008 and then
when they started again they very much raised their lending rates.
At that time the Government was propping up the banks, giving
them quite a lot of finance to keep them going and I can't really
understand whether or why there were not much tougher negotiations
with the banks to ensure that they kept their loan rates to these
PFI projects much lower than they have turned out to be. Did
you try? If you did, were you unsuccessful? If you didn't, why
didn't you?
Andrew Hudson:
What we were trying to do through this period in which loan rates,
following the global turmoil in financial markets, were rising
around the place, was to ensure that the projects that went forward
were still value for money and that certainly, I am sure, robust
negotiations would take place between the procuring authorities
and the banks, but this was in the context of, as I say, rising
loan rates right across the board. As the NAO Report brings out
on Figure 2 at page 6, while loan margins on PFI projects certainly
rose, that was true and was broadly in parallel with loan margins
on international projects' financed loans. So the discussions
that were taking place ensured that the margins were below the
going rates, so to speak, for international project finance.
Our job was also very importantly to ensure that these projects
remained value for money for the taxpayer and we took a number
of steps to ensure that.
Q2 Chair:
We will come to that. I would just really like a straight answer:
did the Treasury engage in discussions with the banks to say,
"We want to keep these infrastructure projects going because
of the macroeconomic impact that they would have, but we do not
expect you to charge these much higher loan rates that brought
into question the value for money of the projects at that time."
Did you engage in tough negotiations, saying to the banks to
whom we were lending pots and pots of money, "We expect the
PFI projects to have lower loan rates?"
Andrew Hudson:
Well, since Andy Rose was most closely involved at the time, I
will perhaps ask him to speak from his closer experience.
Andy Rose: There
were a number of discussions with the banks at the time about
how they were funding themselves, the cost that they were incurring
themselves and whether shorterterm lending or a structure
known as mini perm lending might have been appropriate. We
did not find a consensus among the banks that, to maintain
the market of banks that were supplying, there was a viable way
of reducing the costs, and this is largely due to the bank's own
funding costs, which went up during that period. As Andrew just
suggested, the chart in the NAO report has highlighted that this
was a global phenomenon, not PFI-specific.
Q3 Chair:
So you did attempt negotiations and you failed?
Andy Rose: We had
several discussions with the banks about different structures
that might be incorporated to reduce the cost of funding but because
what was actually driving this was their own cost of funding,
this would have required the banks to lend at a loss. In that
respect we were unable to persuade them to lend at a lower rate.
Q4 Chair:
It seems to me that at that time PFI projects were probably the
most secure projects to which the banks could lend. I cannot
even think of Derek Hatton ever refusing to pay any money that
was owing on project finance. We were the most secure, and I
cannot understand that in that context we found it impossible
to secure better loan rates, which would have made these much
more viable projects in terms of value for money. I just don't
get it. Either we were not tough enough or we were conned. I
don't know quite how we ended up with these much, much higher
loan rates.
Andy Rose:
The nature of the PFI contract is that, while Government are
backing the payment, it is a performancebased payment and
the borrower in a PFI contract is actually the private sector
and these are on the verge of investmentgrade rating. So
while the payment is sourced from the public sector, it is quite
a complex project financing that the private sector is undertaking
and these, as I say, are typically structured around or just above
investment grade, so it is quite a complex financing and that
is why the NAO's comparison to international global project finance
is, from our point of view, the correct one.
Q5 Stephen Barclay:
Could I just take you away from the general to the specific and
turn to Appendix 4 please and the case of the Greater Manchester
Waste Disposal Authority, which was the key one, I think, taken
forward by TIFU. There it says that one of the key drivers of
the deal was not the issue of value for money but the EU Land
Directive; the need to reduce waste by 50% on 1995 levels by 2013
and that this scheme was covering 5% of national waste. I'm just
trying to understand to what extent you were looking at these
objectively as value for money deals, or whether there were other
things driving the need to complete.
Andy Rose: I think
there are two answers to that, which I will split if I may. One
is from TIFU's point of view in particular, TIFU did not have
a policy role; TIFU was there to provide liquidity to the market.
The policy around VFM for each individual deal is a decision
for the authority and supported by the policy team within Treasury,
so I think it's wrong to say that VFM was not a driver for all
PFI dealsbut I will defer in terms of that particular onebecause
TIFU was very much set up to respond in a commercial manner, rather
than establish policy for Treasury.
Andrew Hudson:
Charles will be able to help on the policy side.
Charles Lloyd:
If I could just add to that; I was Head of Policy at the time.
Obviously in the case of the Greater Manchester Waste Disposal
Authority deal there was an external imperative to building that
facility, and indeed other facilities in the sector, as there
is in many PFI deals. That does not mean that we do not look
for value for money in the transaction. We know that waste facilities
have to be built; there is some choice about the method of procurement
and financing for that transaction, and we would apply the same
value for money test to a deal which has to be built for EU reasons
as we would apply to a deal that has to be built for any other
public sector reason.
Q6 Stephen Barclay:
Sure. What I am driving at is I am just trying to understand
what pressures were driving this, because when, at a previous
hearing, we looked at the multirole tanker aircraft, instead
of using the 3.5% discount that was the Treasury guideline in
2004, an out-of-date 6% was used because the MoD just did not
have the money for these planes, but there was a military requirement.
So there was a defence imperative to get on with this deal.
What I am trying to understand with this one is whether there
was a legal and regulatory driver that was, in essence, shaping
the thinking. Linked to that: what were the sunk costs on this
deal at the point where you were deciding whether it was value
for money?
Charles Lloyd:
Well, to take the first point, there certainly were external drivers,
as I think we've discussed, so that is established. I don't know
the precise quantum of the sunk costs. On the authority sidethat
is Greater Manchester Waste Disposal Authoritythere will
have been quite substantial sunk costs incurred in its advisers
and its own resources going into the deal. We can find out what
those are and let you know what
Q7 Stephen Barclay:
As a ballpark figure? This is a contract worth £3.8 billion.
If it didn't go ahead how much would have been spent in very
broad terms?
Charles Lloyd:
I would estimate on the public sector side something in the region
of £5 million to £10 million would probably
have been spent.
Q8 Stephen Barclay:
Okay. In terms of jobs, because this was in the North West, so
there was probably a political driverthere were a lot of
marginal seats up there in 2009/10this was a project covering
36 recycling facilities across 23 sites. How many jobs would
have been linked into this going ahead?
Andy Rose: I believe
the authority's press release at the time articulated 5,000 jobs.
Q9 Stephen Barclay:
So about 5,000 jobs
Andy Rose:
That is my understanding
Q10 Stephen Barclay:
in the run up to a general election. Okay. Could I then
just come to the figures, because at paragraph 1.7, page 16 of
the report, it says, "A review of a sample of Outline Business
Cases by Partnerships UK estimated that all cases remained value
for money at higher bank rate margins of 3%". However, if
we look at this deal the margins start at 3.25% and go up post-year
21 to 4.5%. What I am driving at is when you assessed those as
value for money, were you including refinancing within that assessment?
Charles Lloyd:
No. We never include the possibility of refinancing gains within
value for money assessments, simply because it is speculative;
we do not know whether those deals will be refinanced or not.
Q11 Stephen Barclay:
So what assessment were you making about refinancing on this deal?
Charles Lloyd:
We were not assuming the possibility of any refinancing gains.
Can I just make one point on that? We would never assume and
we would never ask an authority to assume the possibility of refinancing
gains. Our role, if you like, is to set out how authorities should
go about doing their value for money assessments, rather than
doing the individual value for money assessment on every deal
that went through during this period of time.
Q12 Chair:
But you approved every deal?
Charles Lloyd:
We approve every deal when it goes into procurement. So we take
deals through something called the Project Review Group, which
approves that they should go into procurement, yes.
Q13 Chair:
Sorrypost credit crunch, when the credit crunch started,
if something had already been approved for procurement you didn't
draw it back to look again for value for money?
Charles Lloyd:
As the NAO report makes clear, we did not draw every deal back.
We did not ask every project to come forward with a new assessment
of whether it was
Q14 Chair:
You did not?
Charles Lloyd:
We did not.
Q15 Chair:
Did you ask any project to come forward for reassessment?
Charles Lloyd:
We did.
Q16 Chair:
Which ones?
Charles Lloyd:
We ask any project where what is called the PFI credits they require
go up by either 20% or £20 millionall of those
come back for reassessment. We also did the exercise that the
report describes, which was asking PUK to do an overall evaluation
of whether the movement in margins was likely to have created
a systemic problem for us.
Q17 Chair:
20% is a jolly high figure to start worrying as to whether you're
getting the VFM, isn't it?
Charles Lloyd:
It's quite a high figure. There are a number of things that we
would be trying to balance here, including not requiring projects
to come back on a timeaftertime basis for relatively
small changes, so I guess it is a matter of judgment as to whether
20% is the right figure.
Q18 Chair:
20% is small change?
Charles Lloyd:
No, 20% is quite a material change; I think that is why we do
want those to come back.
Q19 Chair:
Who set that figure?
Charles Lloyd:
The Treasury set that figure.
Q20 Stephen Barclay:
What was the tipping point for you, percentage wise, at which
you would have assessed it not being value for money?
Charles Lloyd:
One tipping point for us would have been the 300basispoint
figure identified in the PUK report. On the basis of the sample
they looked at, we were aware that, if margins went above 300
basis points across the market, there was likely to have been
a systemic problem for us; that is, many deals might not on that
basis have been value for money.
Q21 Stephen Barclay:
So all those that went above that tipping point you assessed,
did you?
Charles Lloyd:
We were certainly closely involved in deals that went above that,
of which there were very few. Greater Manchester Waste Disposal
Authority is one we have looked atthat is a unique deal
for size, scale and technologybut the great majority of
deals were in the region of 250, 260 basis points throughout the
credit crisis.
Q22 Ian Swales:
That deal itself was financed through this new Infrastructure
Finance Unit that had to be set up. As I understand it, that
effectively took public money and converted it into the private
money going into that deal. Why did only one project get put
through that unit at the time?
Andrew Hudson:
Remember, this was a very febrile time in the markets. What actually
turned out was that the effect of TIFU making that intervention
in the one deal had the effect of helping the market after that
to work more conventionally again. The fact that market players
knew that the Government were ready to make further loans if it
judged it appropriate had the effect of stimulating market movement,
which was one of our objectives. TIFU intervention was always
intended as temporary and reversible.
Q23 Ian Swales:
Do you think the market moved because they got frightened that
they saw the Government starting to finance projects themselves?
Andrew Hudson:
I don't know about frightened. Again, I will ask Andy who was
most active in TIFU at this point.
Andy Rose:
From the feedback we have received, the problem was a lack of
supply of finance, and again, TIFU was not set up to lend in competition
with banks. The policy at the time was that it was there to lend
where there was no availability of finance from the private market,
and in reality the only time that manifested itself clearly was
on Greater Manchester. Because there was a lack of supply of
bank finance at the time, the tension in the negotiations, I think
the public sector felt, was very strongly on the side of the banks,
so I think the answer is it had a material difference in that
it created some competitive tension. Authorities were able to
say to banks, "If you don't accept that point we have the
option of going to another party," and we are aware of a
number of cases where we were informed that that had a very powerful
effect.
Q24 Ian Swales:
Do you think the taxpayer as a result has had a better deal on
that project than it otherwise would have done and if so why not
do more in that way?
Andy Rose: I think,
again, the driver was liquidity; it was not there to drive down
pricing. So the
Q25 Ian Swales:
Well, what is the answer to my question: has the taxpayer as a
result of this crisis had a better deal on that project than they
otherwise would have done?
Andy Rose: Well,
I think this is my point; I think the project would not have gone
ahead at all had TIFU not lent. TIFU lent £120 million,
and that was a gap because the other banks were not able to fill
it. It is hard to answer the question because I think the answer
is: at that stage the risk is the deal would have been cancelled
only due to a lack of available funding.
Q26 Ian Swales:
Has that £120 million been converted into a commercial
loan now?
Andy Rose: TIFU
only lent on a commercial basis. The policy of the intervention
was temporary and reversible, so TIFU was staffed only with senior
project finance specialists from the private sector market that
negotiated a commercial deal and entered into the loan agreement
on identical terms to other commercial lenders.
Q27 Ian Swales:
So the taxpayer is sitting on an asset that is generating a commercial
interest rate now?
Andy Rose: Absolutely.
Q28 Ian Swales:
So is that not a good idea?
Andy Rose: I think
the key was to try and keep the private sector in the market,
so I think, with the evidence of 49 deals having occurred since,
it was very, very important not to distort the private sector
market where the private sector market could deliver, and the
target of the intervention was only where there was not money
available from the private sector.
Q29 Ian Swales:
Does that unit still exist?
Andy Rose: It still
exists but at the last spending review it has been identified
that no further funding will be made available other than to honour
the legal obligation on the draw-down on that Manchester loan.
Q30 Ian Swales:
Is that not something we should be looking at? The Olympics and
the Crossrail projects have a combination of public and private
finance; should we not be doing more of that?
Andy Rose: Well,
I think there are a number of initiatives currently being considered.
Again, in the Budget and the spending review there was an announcement
that the Green Investment Bank was looking at mechanisms. Again,
the concept of the Green Investment Bank is still being developed,
but I think the Government is looking at a number of possible
interventions. The TIFU intervention was targeted on the PFI
market, and given that 49 deals have closed since then without
TIFU being asked to lend, I think the decision was made that allocating
scarce public finances to TIFU going forward was not the right
decision.
Q31 Mr Bacon:
Couldn't the taxpayer be having that margin on all those deals?
This one deal unblocked this pipeline and the other 49 deals
that were at risk have suddenly been found resources. Isn't Mr
Swales right that the private sector suddenly got rather scared
that the Government was quite capable of doing it itself and at
better value for money for the taxpayer? I think it was Mr Hudson
who said that the deals were valued on the basis of just above
investment grade, or perhaps it was you, but at the end of the
day we all know you have to go through the inconvenience of building
the prison, hospital, motorway or whatever it is before you get
the payments starting to flow. But once you have done that it
is almost like buying a gilt, isn't it?
Chair: Quite.
Mr Bacon:
In fact, when Investors Chronicle described the PFI market
as the hidden golden egg, it was precisely for that reason, because
you were paying only just above investment grade, but you were
getting something that was pretty much gilt-edged. Isn't that
right?
Ian Swales: Has
there ever been a default on a PFI payment?
Charles Lloyd:
In my 18 months in the Treasury there were two deals in the operational
phaseso the construction had completed and the asset was
being managedthat terminated for poor performance. So
there are risks to these deals in the operational phase and they
do manifest themselves.
Q32 Joseph Johnson: Just
continuing on a point that Mr Barclay was making earlier, this
was a preelection period where there were a fair number
of politicised lending decisions by the Government, in the view
of many commentators. I would like to know, please, what role
did the Treasury play in greenlighting the 35 projects that
followed the one that was unblocked by the TIFU unit?
Andrew Hudson:
Well, the Treasury played our normal role as we do at all times
in ensuring value for money with appropriate projects, with projects
either being approved by the relevant spending teams or, for a
number of projects, particularly local authority ones, going through
the Project Review Group, which Mr Lloyd chaired.
Q33 Joseph Johnson:
So, chosen out of a universe of how many potential projects?
Andrew Hudson:
I think pretty well all of these projects would have Treasury
scrutiny at one stage.
Charles Lloyd:
All PFI projects would be scrutinised by the Treasury, typically
Q34 Joseph Johnson:
Sorrythe ones that got greenlighted, the 35, were
chosen out of a universe of how many potential PFI projects?
Charles Lloyd:
I am not sure I know how to answer that question. There were
35 that closed in the period that we are looking at. In that
period other transactions were going through the Project Review
Group. There wereI think in my timethree deals
that were brought to the Project Review Group to commence procurement
that we said no to initially, because we thought they were not
ready, either on value for money, affordability or some other
grounds.
Q35 Joseph Johnson:
Right. Of the 35, do you know how many were in what you might
call marginal seats, seats where the incumbent had a majority
of less than 3,000?
Andrew Hudson:
No, because that is not a consideration that we would have needed
to know about or wanted to know about.
Q36 Mrs McGuire:
Can I ask you a question? Was there any political influence at
all brought to bear in deciding which PFI projects? I think we
are going down a line of questioning here that I think we need
some clarity from you on. Was there any undue political influence
that you felt uncomfortable with in greenlighting these
projects?
Andrew Hudson:
Not that crossed my desk.
Charles Lloyd:
None whatsoever from my point of view.
Andy Rose: None
from my point of view.
Mrs McGuire:
Thank you.
Q37 Nick Smith: Isn't
that nice and categorical? Given the further £500 millionplus
that was paid for the high cost and use of bank finance during
this periodlots of extra money being spent at the timewhy
did you not get a better mix and use more public money for these
investments?
Andrew Hudson:
At that time the then Government was actually investing more public
money through the capital programme, so that was happening as
well. The decision on these projects was whether they were still
value for money, within the context of the ministerial statement
that they should go ahead where they were value for money. The
choice in front of us wasn't whether we could continue these deals
at a lower or higher borrowing rate; the choice was do we go ahead,
acceptingas we have explained earlier in the hearingthat
rates were higher because the banks' cost of finance was higher.
Our job was to ensure that these were still value for money and
we've talked about some of the steps that we took to ensure that.
Q38 Nick Smith:
We understand it was a very difficult time and there were big
charges for extra finance, but the world had changed and there
was an opportunity here to save between £500 million
and £1 billion by providing it through the public sector.
Why didn't someone say, "Hmm, let's perhaps jump off this
horse and do this differently"?
Andrew Hudson:
As I say there has always been a mix of provision of types of
funding for infrastructure projects. The Government did increase
its own capital spending at the time and we also looked to bring
in other sources of finance. So the European Investment Bank,
for instance, contributed £1.1 billion across a total
of seven projects over the period in question, so this wasn't,
to use your metaphor, the only horse we were on. But the judgment
was it still had a role to play, albeit accepting that that is
at higher cost to the taxpayer, but we took steps to ensure that
the projects that went ahead still represented value for money
for the taxpayer.
Q39 Austin Mitchell:
You answered Anne's question by saying there was no political
pressure, but you were presumably under pressure from the top
given the fact that everything is stalling and we desperately
needed a stimulus to the economy to get this show back on the
road. Presumably there was such a pressure?
Andrew Hudson:
Well, it's not a question of pressure, but there was a ministerial
statement by Yvette Cooper as the then Chief Secretary, who said
in March 2009 in a written ministerial statement, "The Government
believes it is vital to get these infrastructure projects under
way as swiftly as possible to support jobs and the economy this
year as well as delivering proper public services."
Q40 Austin Mitchell:
So it wasn't a pressure, it was a desperate, sweet plea from a
lovely person. Why did it take you nearly a year to get the show
on the road? Lehman collapsedthe table is on page 15in
September 2008. You don't issue the guidance note until August
2009; what took so long?
Andrew Hudson:
We were working on these projects through the autumn and winter
and judging what the best response to the new situation was.
In terms of getting this show on the road, the key intervention
of TIFU making the loan to Greater Manchester took place in March
or April 2009 so we'd taken action at that point and that had
begun the process of unblocking the market, which led to the 35
deals being completed in 2009-10.
Austin Mitchell:
Okay.
Andrew Hudson:
So, far from doing nothing until the application
Q41 Austin Mitchell:
Okay, and then you put the frighteners on with the Manchester
deal, which is a graphic way of putting it. I wonder how far
the dominant consideration was to keep the private sector in at
all costs; in other words to keep PFI going and feeding the private
sector in the way PFI does. Did you consider alternativesthere
are a number of alternativesthat I and an obscure organisation
that I chair were suggesting at the timelike bringing pension
funds in to invest in PFI contracts or printing the money. We
are now going through quantitative easing, and the Bank of England
is buying back its own debt; why can't Government write cheques
to itself to carry through these projects?
Andrew Hudson:
As I say, there's always been a mix of provision here. The Government
did
Q42 Austin Mitchell:
Yes, but did you consider these specific alternatives?
Andrew Hudson:
We considered a number of alternatives. We did encourage schemes
to look for as wide a range of financing sources as possible.
We've never thought that the PFI was the only show in town.
I mentioned that we took steps to get the EIB more closely involved.
Colleagues may be able to say more in a minute about whether
we involved pension schemes. PFI clearly has a part to play.
There is clearly an appetite for it, viz. the fact that 35 deals
went through, and we thought it was important to keep that source
of finance as part of the mix, provided that the schemes were
value for money.
Q43 Austin Mitchell: The
private sector has to be fed, hasn't it? We have to keep it happy?
Chair: Well
Q44 Austin Mitchell:
Did you consider printing the money?
Andrew Hudson:
It's not a question of printing money; the alternative would have
been to go ahead with Government-funded capital and the Government
took a judgment as to how much it was prepared to do there and
where that was most appropriately spent and that went through
the
Q45 Austin Mitchell:
So even though that could have been done at a lower rate of interest,
you are still rejecting it, under Government instruction?
Andrew Hudson:
Government borrowing, remember, was running at an extremely high
level
Q46 Austin Mitchell:
I remember. They are constantly telling us. I am asking whether
you considered using that as an alternative at the time, in view
of the desperate need for stimulus?
Andy Rose: The
policy at the time wasn't to accelerate deals; it was to make
sure deals went ahead when the only thing that was stopping them
going ahead was the availability of finance. I think as the NAO
Report acknowledges, because the procurement rules are quite tightly
drawn, to change the procurement methodology would have caused
quite considerable delays because you would have had to reprocure
most of those projects. Given that the policy at the time was
to ensure those deals that were ready to go went, if the only
thing stopping them was finance, to cause delays by reprocuring
I think would have been inconsistent with that policy.
Q47 Chair:
Can I just ask you three questions arising out of that, because
in one or two circumstances you did change tack. You decided
in those circumstances that the Newham school would be better
brought on balance sheet and do it as a straightforward publicly
funded deal. What were the circumstances in which you decidedduring
this credit crunch periodthat you would terminate PFI procedures
or that you would look for another route for financing these particular
projects?
Charles Lloyd:
I would say there were two situations where PFI deals did not
proceed: one is where they were not affordable to the authority
concerned, so they just didn't have the budget to allow them to
proceed because cost had gone up; the other was where they were
not value for money. Many deals struggled during this period
on both of those grounds. Obviously, 35 did come to close but
many others didn't. Just to pick up the Newham one specifically;
this was a schools transaction. It had been structured as a PFI
deal. At the very last minute the lender dropped out of the picture.
A case was made to us there that what we should do is allow that
to close on a conventional design and build basis, but with the
plan to switch that into a PFI very shortly after the financial
close and, indeed, that is what happened in that particular case.
Q48 Chair:
Let me just pick you up on the value for money, because as I understand
it, the imperative is to keep the capital programme going because
of the macro-economic circumstances. Value for money is questionable
on all these deals in the traditional way in which you assess
PFI, because your loan charges are 6% to 7% higher according to
this Report and the margin on PFI is 5% to 10%. I'm not sure
you could make a value for money case for any of the 35 deals,
could you?
Charles Lloyd:
Our view is that you could make a value for money case on all
of the 35 deals.
Q49 Chair:
How did you base that?
Charles Lloyd:
We based it on two main things. One was the piece of PUK work
that we commissioned which indicated that margins would have to
rise to about 300 basis points for there to be a systemic value
for money problem, and the other was that authorities follow the
very substantial value for money guidance that exists from the
Treasury and that they are required to go through before their
own accounting officers or Section 151 officers sign off on these
transactions.
Andrew Hudson:
I would also just point out that we are grateful for the NAO's
endorsement of this, that the report at paragraph 28 says, "It
is our opinion that in the circumstances the extra finance costs
of projects financed during 2009 were value for money."
And
Q50 Chair:
Just to interrupt. It says that and I understand that and this
is not, in a sense, us being critical of you. It says that, in
the circumstances, the overall policy objective was to maintain
this capital expenditure for macro-economic reasons. That seems
to me a different test to the one you would have applied to PFI
projects in 2003-04? That's the point I'm making. Am I right
or wrong?
Charles Lloyd:
I don't think you're right on that point. The TIFU intervention
was designed to redress a particular problem in the market, the
problem of liquidity and lending capacity. The approach we took
to all of these transactions, consistently, through the market
was that we should solve that problemand we think we didbut
that deals should only come to financial close if they were, on
a conventional assessment basis, value for money.
Q51 Chair:
Let me ask you another question, because looking at the way in
which many of these 35 projects were financed, there appears to
be no competition over accessing the finance. Indeed, for many
of the projects they have to woo a number of banks, and I can't
remember the term you usedthere are bank clubs. You developed
this concept of bank clubs to try and entice a sufficient number
of banks in to then fund the deals. Now that seems to me again
to offend the principle behind PFI, which is that competition
in the banking system will give you a better deal. The projects
were grappling around looking for funders.
Charles Lloyd:
It was a very difficult market.
Q52 Chair:
So there was no competition?
Charles Lloyd:
Well, I wouldn't say there was no competition. That depended
on the scale of the deal. To take two examples, the M25 transactionthe
biggest that closed in the marketrequired pretty much every
bank in the market including the EIB to come in to allow that
to close. Smaller schools transactions typically had one, two,
sometimes three or four banks in them, and there, although it
was very difficult to follow our conventional funding competition
guidance in those circumstances, strenuous efforts were made,
on a sort of bookbuilding basis, to try and get the best
value for money for the financing of those transactions.
Q53 Chair:
Strenuous efforts were made. So you would say there was sufficient
competition in there to meet the conventional principles of a
PFI?
Charles Lloyd:
No, I wouldn't. It was a very, very difficult market. So it
was difficult to try to persuade banks to come into a conventional
funding competition.
Q54 Chair:
Yes.
Charles Lloyd:
So we had to try, and authorities who were at the front line of
this had to try whatever approach they could, but with a competitive
tension wherever possible.
Q55 Stephen Barclay:
Both Mr Lloyd and Mr Hudson mentioned in the last few minutes
the European Investment Bank, which is a not-for-profit investment
bank that lends on more favourable terms. Did you make full use
of the European Investment Bank?
Charles Lloyd:
We made substantially more use than we had done in the period
prior to the credit crunch. Treasury collectively put, I would
say, quite a lot of pressure on the European Investment Bank to
step up and get involved with more transactions, so they brought
a lot more funding forward. They became involved in sectors that
they had not previously been involved in. I think we did a great
deal. Was there anything else we could have done on the margin
to get them involved? It is difficult to say. Their main issue
is that they're resource constrained. They have a certain number
of transactors. Those transactors were in demand all around Europe,
as you can imagine, to be involved in deals of this sort. We
were trying to get at least our fair share of that resource.
Q56 Stephen Barclay:
Sure, but more is better, but is not best, isn't it? So if we
look at say Italy and Spain, which have a similar share of ownership
of the European Investment Bank as the UK, would we have had a
comparable lending approach to those countries?
Charles Lloyd:
I don't know the answer to that.
Andrew Hudson:
We can research that
Q57 Stephen Barclay: If
you can let us have a notebecause it would be odd, would
it not if, for the sake of argument, £6 billion was
going into Spain and Italy, but £4 billion was going
into the UK, as ballpark figures?
Andrew Hudson:
Yes.
Q58 Stephen Barclay:
Could I justoh, go on Ian, and then I'll come back.
Ian Swales:
Go on, you finish.
Stephen Barclay:
To me it looks like we were asking the banks to face both ways.
On the one hand we were asking them to build up their capital
and on the other hand we were saying to them, "We want you
to lend for 25 years." It strikes me that the last thing
the banks would want to do is loan for 25 years at a time when
they are reluctant to lend to each other, and therefore they are
going to be charging a huge premium in order to do so, which goes
back to my point about Appendix 4 and the fact that the margins
were so big. Just coming on to it, again as to whether we made
full use of the European Investment Bank and its favourable terms,
which strikes me as a good starting point, the capital ratio of
the EIB at the time of the credit crunch would have been around
26%, would it not, that sort of figure? Mid-20s?
Charles Lloyd:
Again, I don't know, I'm afraid.
Q59 Stephen Barclay:
Okay, let me rephrase it. The capital ratio of the European Investment
Bank would be much more favourable than that of commercial banks.
Charles Lloyd:
I mean, it is certainly a well-capitalised entity, yes.
Q60 Stephen Barclay: So
it's easier to get them to lend than it is to get the commercial
banks to lend?
Andrew Hudson:
From that point of view yes, but as Charles Lloyd explained a
few minutes ago there are constraints on the European Investment
Bank as well. I well understand your point about were we getting
our "fair share" of its lending, and we will research
and let you have a note of that. We did try and there are different
constraints on them from those that we've talked about on the
commercial banks.
Q61 Chair:
"We will research"were you or weren't you? I
mean, it is quite an interesting question. Rather than us wait
two years for the answer, you must know now: could we have got
more out of them?
Andrew Hudson:
As Charles says, that's hard to judge. We had a number of discussions;
we worked hard; we certainly stepped up the share compared with
what had historically happened in the UK. They lent well over
£1 billion to seven projects, crossing several different
sectors. Could we have got more? Hard to judge. Did we get
our fair share? We tried hard. In terms of sort of "our
share" compared with our contribution and size of the economy
or whatever, that is what we will let you have a note on.
Q62 Stephen Barclay:
I was asking about in terms of share ownership, but seven out
of 35
Andrew Hudson:
Yes.
Q63 Stephen Barclay:and
how we benchmark. My final question in terms of the EIB is just
around what happened to their pricing compared with what happened
to the commercial banks' pricing? My perception would be that
the increase in the EIB pricing was modest compared with that
of the commercial banks. Is that a fair view to have?
Andy Rose:
Absolutely. The way that the capital markets were working at
the time, it was a real flight to quality, and EIB because of
its ownership is viewed as a very strong quasisovereign
AAA, so in the flight to quality in the capital markets there
is no question that the EIB's access to finance and its ability
to pass it on was beneficial.
Q64 Stephen Barclay:
Given that the first one of these, the first TIFU one, which was
the Manchester waste authority one, had the EIB involved, it just
strikes me as odd, if we were getting value for money, that we
didn't maximise that in the subsequent deals.
Andy Rose: Again
I think the comment being made is that, in the conversations I
was involved in, the Treasury was pushing very hard on EIB to
step up its lending; the feedback, as Charles indicated, was around
the resources they were able to apply. So the deals they tended
to do were the larger more complex deals, such as Greater Manchester.
They did do some schools deals as well, but they tended to focus
their resources on the larger, more complex deals.
Q65 Ian Swales:
Can I just return to this question of risk? Has anybody ever
defaulted on a PFI deal for financial reasons?
Charles Lloyd:
Would you mind expanding on what you mean by for financial reasons,
sorry?
Q66 Ian Swales: Has
anybody ever failed to do the payments on a PFI deal because they
didn't have the money to pay?
Charles Lloyd:
I don't believe so, no.
Q67 Ian Swales:
So you said there had been two operational reasons for PFI problems,
but there's never been a financial reason?
Charles Lloyd:
No, the Government or a local authority has never defaulted on
their obligations under that.
Q68 Ian Swales:
So PFI is giltedged, 100% secure, based on its record so
far, financially speaking.
Charles Lloyd:
Well, I would say the credit risk
Q69 Ian Swales:
Credit risk.
Charles Lloyd:
of the counterparty is low or negligible.
Q70 Ian Swales:
Okay. I think all three of you have used the word "complex"
at some time during this morning. Do you think the taxpayer's
getting the best value for money by tying up the 100% secure capital
financing with the risk of the operational contracts that go alongside
most PFI deals, or do you think it would be better if they were
separated?
Andrew Hudson:
Sorry, just to make sure I understand the
Q71 Ian Swales:
Well, a PFI deal for a school, as I understand it, isn't just
about building the school, it's about operating the school. Would
it be better to separate the financial costs of building a school
to the ongoing operational contract that goes with it in terms
of value for money to the taxpayer?
Charles Lloyd:
Can I have first go at that? I suppose my answer is I don't think
so. One of the underlying almost philosophical points about PFI
is you need to have the same party incentivised to both deliver
and maintain the asset, so one counterparty to the Government
entity that is responsible for minimising the cost of that asset
and securing its performance over the whole life of it, or you
run risks of building something cheaply and then finding it expensive
to maintain in the long term.
Andrew Hudson:
Which had been the experience of the public sector over the years.
Now, I think we're getting better at managing our own capital
programmes and one of the emphases in the spending review capital
settlement that was announced last week is to make sure that assets
are properly maintained. Not having that link that Charles Lloyd
has just talked about was one of the problems that PFI addresses
by making the special purpose vehicle and behind them, the banks
Q72 Ian Swales:
My question is about the risk premium that you have to pay for
large amounts of finance, given that, as Mr Bacon said earlier,
this is only very, very slightly worse than a giltedged
investment. Are we paying too high a risk premium for these projects?
Certainly through this period it appears that we were.
Charles Lloyd:
We would certainly do whatever we can to try and reduce the risk
premium, both at the construction phase and the operational phase.
One way to do that is to try and get these deals refinanced after
the construction period at a cheaper rate in the operational period,
where I agree with you, the risk has been diminished. That historically
has happened a lot. This Committee knows very well the Government
have benefitted from that to an extent over the years. I think
we are very enthusiastic; we would like to see more refinancing.
It is a difficult market for that at the moment.
Q73 Ian Swales:
When PFI first started it was legendary how much money you could
make by doing a PFI scheme and then refinancing it. What proportion
of that refinancing benefit now comes back to the taxpayer?
Andrew Hudson:
Well, this is something which has increased over time, so for
projects, for the most recent projects reaching financial close
since October 2008, the authority share will be 50% of gains up
to £1 million, 60% between £1 million and £3 million
and 70% of the gain above that. So that has been stepped up over
time and, of the projects that the NAO report has talked about
where they have quoted this potential extra cost of between £500 million
and £1 billion, they also say that some £400 million
might be recouped through refinancing
Q74 Ian Swales:
What would you describe as the source of that refinancing gain?
Why does it occur?
Andrew Hudson:
As Charles was saying, it is at the point where the risk to the
lenders reduces, but do you want to explain in a bit more detail?
Charles Lloyd:
I think there are two things. One source is the diminution of
risk at the point where construction of the asset is completed.
The second source is changes in the market. So clearly if rates
or margins or loan tenures go down between the point where the
deal was signed and the point where refinancing is looked at,
there can be a gain. Progressively there's
Q75 Ian Swales:
I've done work in the commercial construction industry and they
think a margin of 4% or 5% on a construction projects is fantastic.
Would you say that these refinancing gains are of that order
or are they much greater?
Charles Lloyd:
I think that varies according to what is happening in the market,
principally. Historically we have seen substantial gains in refinancing.
More recently on the whole it has not been possible to refinance
these transactions because many of them were signed at a time
when loan margins were 70 or 80 basis points, so less than 1%.
Loan margins in the market now are 2.5%, so it's not possible
as a general matter to refinance and make a profit at the moment.
Obviously, we hope it will be possible in the future and we've
increased the refinancing gain sharing to give Government more
of that share if it does happen.
Q76 Chair:
If we've done that, don't we then make it more difficult for banks
to participate in the market, because it's less advantageous?
If the Government takes a greater share of the gain out of refinancing,
there's less incentive for banks that traditionally participate
in that market?
Andy Rose: The
banks prefer the shorter-term lending, as articulated earlier.
They actually prefer that. The person who's incentivised by
the refinancing is the owner of the equity and again, when we
came up with the 70:30 balance, we wanted to come up with a balance
that recognised that Government had paid more and therefore was
entitled to recapture more, but retain the incentive for the private
sector to do the refinancing. The banks, frankly, are very pleased
to be refinanced as they can recycle their own capital and not
be tied into very longterm lending, so striking the 70:30
that Andrew alluded to was an attempt to come up with the optimal
balance of recapturing more on behalf of the taxpayer, but retaining
the incentive for the private sector to refinance.
Q77 Mr Bacon:
Talking about longterm funding, one obvious source of longterm
funding is pension funds, who are looking for longterm funds
to match their longterm liabilities. Now, what effort was
made to start marketing PFI finance deals to those sources of
finance or are they only of interest once the risk is reduced,
as Mr Rose discussed?
Andy Rose: Well,
there has been an active dialogue with pension funds for as long
as I've been in the market, which is a very long time. The reality
is that pension funds at the moment from a debt perspective do
not have the analytical capability to analyse the construction
risk, and therefore what they would rather have for their investors
and their pension holders is long-term stable cash flows that
are more likely in a refinancing
Q78 Mr Bacon:
So a major potential source of refinancing?
Andy Rose: I think
it's a terribly important area for us to develop and there is
an enormous dialogue with them; I do think it's a very, very important
area to develop.
Q79 Ian Swales:
We have just established that, as a lender, the track record is
that the risk is nil. Financial risk is nil.
Andy Rose: I think
CharlesI'm not sure that
Q80 Mr Bacon:
Mr Swales and Mr Lloyd, were the two projects that you were talking
about the National Physical Laboratory and the Shrivenham Joint
Services contract?
Charles Lloyd:
No.
Q81 Mr Bacon:
Which were the ones you were talking about?
Charles Lloyd:
There was a Cornwall Schools Project and something called the
Defence Animal Centre, both terminated in 2009.
Q82 Mr Bacon:
When they were terminated, why were they terminated?
Charles Lloyd:
They were terminated because the performance of the private sector
was unsatisfactory.
Q83 Mr Bacon:
Right. Okay. So they weren't terminated because in some way
the authority failed to make its payments, which would be a good
reason.
Charles Lloyd:
Absolutely not. No.
Q84 Mr Bacon:
I remember we looked at it on this Committee, both the National
Physical Laboratory years ago and the joint services college in
Shrivenham, where Laing construction decided to build it on a
swamp, except they didn't know it was a swamp and indeed they
went out of business and had to be bought. That is a different
kind of risk; it is an operational risk. Mr Swales is talking
about the finance risk and indeed the finance risk is very low,
and what we are still interested inI've always been interested
in thisis whether we can prise away the finance risk.
One of the first PFI deals we looked at when I was on this Committee
was the competition for financing the Treasury building PFI, which
was the result of an NAO Report. I see Mr Finlay nodding. The
report concluded, unsurprisingly, that if you have a competition
for the finance you get a better rate than if you don't. 300
basis points is quite a lot in financing terms, when you consider
that we are really talking about near gilt.
Charles Lloyd:
Can I make one point on risk? Although the risk of the authority
or the Government defaulting on the loan is very low, the Government
will only pay what they are due to pay under the contract, and
it is the performance under the contract that matters. In those
two examples I gave, the banksnot withstanding they got
their paymentshad to write off significant amounts of their
loans because the performance of the business they had lent to
was unsatisfactory. So there is risk on this finance: it is not
a credit risk; it is a performance risk.
Andy Rose: Can
I come back? The longterm fixedrate investors are
very sensitive to the view of the rating agencies
Q85 Mr Bacon:
We know how good they are, don't we?
Andy Rose: I had
the feeling you might say that. They are very sensitive, particularly
when they are the pension trustees and people like that. The
reality is that when the rating agencies look at these longterm
transactions they certainly do not look at this as no-risk transactions.
They do look at these as quite considerable risk because these
are very complex. As you said, there is performance risk and
quite a high degree of gearing in
Q86 Mr Bacon:
Certainly, and I think I'm right in saying there were AAA-rated
monoline insurers that were basically getting into trouble, so
Andy Rose: Absolutely.
That was the model from 1997 to 2007, as far as I'm aware. All
the PFI transactions done in the capital markets were with the
benefit of what was then, as you suggest, a AAA rating from the
monoline insurers.
Q87 Mr Bacon:
Going back to the EIB point, which I wanted to ask earlier, why
then did you not take more advantage of this flight to quality?
Mr Lloyd said there weren't enough transactors. I take it you
mean corporate finance professionals, project professionals, who
could run these deals? Why didn't you, becauseyou're back
in PwC now I thinkyou were yourself a secondee, your predecessor
as Head of PFI Policy at the Treasury was from Deloitte; he was
a secondee? His predecessor, Mr Abadie,
was also a secondee from PricewaterhouseCoopers. Why didn't you
guys say to the EIB, "I know, we know lots of these project
professionals. Why don't you take 10, 15, 20 or 25 of them, second
them into the EIB for a bit, run more deals"because
you've said the number of transactors was the limit "until
we get things settled down?" Then you can go back to the
private sector and take advantage of the genuine quasisovereign
ratings that the EIB was able to get for raising its own funds.
Couldn't you have done more of that?
Charles Lloyd:
We did some of that. Speaking for PwC, we seconded people into
the European Investment Bank at that time. I think it's really
a question for the EIB about the extent to which they are prepared
to
Q88 Mr Bacon:
We are a shareholder. I was actually talking about HMG. Wasn't
HMG prodding the EuropeanI'm sorry about all these threeletter
acronymsbut wasn't HMG prodding EIB and saying, "Look,
we're a shareholder in your bank; why don't you get more people
from places like PwC?" Were you doing that, Mr Hudson?
Andrew Hudson:
I wasn't. Could we have done more of that? I don't know.
Q89 Mr Bacon:
Mr Lloyd was doing it. That's because he wanted to keep the deal
flow going.
Andrew Hudson:
Sorry, I'm thinkingwell, indeed.
Q90 Mr Bacon:
You wanted to keep the deal flow going as well, so why didn't
you do it?
Andrew Hudson:
I think we
Q91 Mr Bacon:
Because you would have more deals going more cheaply, because
the EIB
Chair: Bureaucratic inertia,
I think is the answer.
Andrew Hudson:
I understand the point. I don't know whether that was considered
at the time. What I would say is that the Treasury had a huge
number of other preoccupations at the time. So it is an imaginative
idea
Q92 Mr Bacon:
Like keeping the money coming out of the bank holes in the wall
Andrew Hudson:
And keeping the banking system, as a whole, afloat, so I hope
it wasn't simple inertia but there were some other priorities
in that space.
Q93 Mrs McGuire:
I'd like to turn back my question to something that Austin highlighted,
which is the length of time that it took youthat it appeared
to take youto respond. Given that there was a storm raging
around some of our financing of infrastructure projects, did you
feel that you were just like one of these big tankers that just
didn't know how to turn? What I am trying to, I suppose, elicit
from you is what lessons did you learn from that periodone
hopes we won't face another period like itbecause just
to say, "Well, we did it over a sixmonth period,"
frankly, is not good enough. The Chancellor of the Exchequer
at the time was warning in September 2008, I think, that we were
about to face the greatest economic crisis that any of us would
ever have countenanced. What would you have done differently
to respond far more quickly than, frankly, you did?
Andrew Hudson:
I think it is always easy with hindsightthere are always
things that you say you could have done more quickly and in a
minute I will ask Andy, who was in the thick of the discussions
on the financing at the time, to say more. My perspective is
that what was happening in the markets was unprecedented, very
fast moving and hard to read. We were trying to balance first
of all identifying what the appropriate policy should be on these
deals, and advise Ministers on that, and also think about what
financing options we had. In the end, the TIFU approach was the
one we went for. That process did take a certain number of months.
In the course of that, we commissioned work to get some better
idea of the value for money implications of the higher margins
that were emerging; we commissioned PUK in the winter to produce
a report, which came out in early January, that gave us a handle
on how far margins could rise before threatening the value for
money assessment. It wasn't that nothing was happening at this
point. We were doing some detailed work that enabled us to put
together the policy response for Government and the TIFU intervention
which then kicked in in March-April. I don't know whether Andy
wants to
Andy Rose: I think
it's fair to reflect just how uncertain things were post Lehman.
There really was a high degree of uncertainty about what was
going to happen thereafter and I thinkfrom my understandingwhat
did Treasury do? I think Lehman happened in September. Over
the next three or four months there was a lot of analysis about
the value for money. There was also a lot of analysis about different
responses. TIFU wasn't the only response considered by Treasury.
Q94 Mrs McGuire:
What other options were on the table?
Andy Rose: Looking
at shortening the term of the financing to create an embedded
refinancing is the term, technically a mini perm financing; ways
to look more at the pension funds and the capital markets. For
a number of reasons, TIFU was chosen as the preferred intervention,
which was put in place over January and February. That then took
to March. TIFU made its first loan in April. One of the, I think,
very important things was advising procuring authorities to have
more flexibility in their OJEU notices so they weren't tied into
one particular financing. There was encouragement to look at
more capital contributions from more authorities, which reduces
the price by changing the mix. There was the issue about increasing
the refinancing gain that the public sector took, and also giving
the authorities the right to call for a refinancing, which they
didn't have before. So I think to call it a "tanker"
wouldn't be the word I would use, because I think there were a
number of things. I think lessons learnt: again, I think it's
just really important to reflect on how uncertain things were
for anyone who was very close to the finance community. We were
entering a world that none of us had ever seen before.
Q95 Mrs McGuire:
So you were being so cautious because you were frightened you
might make things worse?
Andy Rose: I don't
think setting up TIFU was cautious. I think a lot of people would
say it was quite a bold move.
Andrew Hudson:
Yes. It was a very big change from previous practice. Just reflecting
as Andy Rose has been speaking, I'd rather be sitting here saying
that knowing what we know now we could have perhaps have moved
a little quicker, than sitting here explaining why we rushed into
something which turned out to fail, which the TIFU intervention
didn't, or to be wholly misjudged.
Ian Swales: If it was
such a good idea, why did you only do one project through TIFU?
Q96 Mr Bacon:
Going back to why didn't you get more of the margin on more of
them: admittedly it was the taxpayer who was going to pay for
it, but the net effect down the line would have been overall to
reduce the cost. If you could get most of that margin by providing
the funding through the Treasury directly, obviously that sent
a signal to the private market that, if they didn't step up to
the plate, you would. That did probably scare them, I'm sure
it did. It probably gave them confidence I suppose, which was
a good thing in circumstances where nobody had any confidence
Chair: It is a very attractive
market.
Mr Bacon: but it
gave them confidence to buy a near gilt, but once you got the
structure going if you could do one, you could do two. If you
could do two, you could do four. If you could do four, you could
do 35. In doing so you would have then extracted all of that
extra margin and you'd have ended up with TIFU making an enormous
profit that they could have then repaid to the Treasury.
Andy Rose: Because
that was not the policy at the time. The policy at the time was
very clear: it was temporary and reversible; it was to only finance
when there was not available finance from the private sector.
I think going further would have done two things. I think it
would have changed the risk transfer mechanism in a lot of projects,
rather than just by necessity in one, because it is the taxpayer
lending into Manchester. I think the other thing is there was
a risk that it would unsettle the rest of the market. Again,
49 further projects have closed, and I estimate 25 different banks
have participated in those 49. I think if the other banks saw
this as an unlevel playing field then there is a real risk that
they would not have stayed in the market the way they have, which
from my point of view was consistent with the policy at the time.
Q97 Chair:
But it might have met another objective of better value for money
with lower loan rates.
Andy Rose: Well,
it would have achieved better value for money by Government taking
back the risk as a lender by driving down price, but that I think
would have had a material change on the risk profile had that
been across the whole market.
Q98 Mrs McGuire:
Just on the same line, were you astonished at how quickly you
unblocked the market
Andy Rose:
Yes.
Q99 Mrs McGuire:with
this one loan, and does that give you any feeling that perhaps
you should have been tougher on the banks from the beginning?
It is like miracle at Manchester, frankly.
Andy Rose: No,
I think again the reality of the market with hindsight is there
were two very, very large projects and, again, we talked earlier
about competition; there is competition on the smaller deals.
There wasn't competition really on the much larger deals and
I think that was quite difficult and club deals have been referred
to earlier. I think, with hindsight, with Greater Manchester
and the M25, which between them had approximately £2 billion
of finance to be raised, a lot of banks were very uncertain post-Lehman
about the markets, and I think once those two deals closed successfully
and banks and procuring authorities knew that TIFU was there,
that gave confidence to the market, and personally it did surprise
me how quickly the banks recovered.
Q100 Austin Mitchell:
I can see your predicament. You are correct in saying that you
were bound by policy at the time, even if the policy was insane.
You were bound by it. Or daft, should I say? Daft. Mr Hudson
said the situation was difficult to readnot quite true
because two people, Vince Cable and I, read it perfectly. He
did better out of it than I did, because he was better at publicity.
Mrs McGuire: Talking about
miracles.
Austin Mitchell: You were
being screwed by the banks, to put it in simple terms. Now, the
problem is, having succumbed to that screwing, what we do now
in the future, because it is my argument, and I think it is Richard
Bacon's, that you weren't inventive enough at the time. Now the
report says at 3.2 on page 26, that as a result there may have
been a longterm increase in the cost of using private finance.
A longterm increase. Now, the infrastructure report just
out, which is a very good one actuallyI hate saying this,
but it's goodsays in the introduction, this is page 4,
paragraph 3, that there's meant to be a reduction in construction
costs, but there also needs to be a reduction in the costs of
capital, and a 1% reduction in the average cost of capital would
result in an annual saving of £5 billion. Now it is
you jokers that are paying out these huge sums on capital projects
through PFI. Aren't you going to have to be much more inventive
about finding alternatives to bank financing, perhaps involving
the pension funds, perhaps even printing money, which is what
I suggested, but you are certainly going to have to cast around
for a way of reducing those costs.
Andrew Hudson:
Well, the National Infrastructure Plan raises a number of new
ways of providing finance for infrastructure, spanning private
and publicly funded infrastructure. Indeed, yes, we are looking
at those new ways, being more inventive, and things like the Green
Investment Bank will have a part to play with public funding behind
it. There are other things set out here which the private sector
will want to think about, and part of the purpose of the Plan
is to set an environment in which the private sector will feel
more confident about financing infrastructure. Andy may want
to say more about some of the specific ideas.
Q101 Austin Mitchell:
And you will be working to reduce those costs on PFIs?
Andrew Hudson:
Well, the mechanisms we have to reduce our costs on PFI are the
refinancing provisions which we talked about, which were strengthened
a couple of years ago. So that's what we'll be looking to do,
as and when market conditions permit.
Q102 Austin Mitchell:
Not for new projects?
Andrew Hudson:
Well, for new contracts we need to continue with public funding
reduced all round; we need to be tougher than ever at driving
value for money, but I would not want that to imply that we have
not been rigorous in that before.
Q103 Chair: There's
a queue of people wanting to ask questions. The loan rates aren't
going down so does this mean there is no future for PFI?
Andy Rose: Well,
again
Q104 Chair:
We are in a much more stable financial market, but the loan rates
are staying high.
Andy Rose: I think
there are a number of issues; if I may just touch on a couple
of them? On the "screwed by the banks" point, the reality
is the banks were passing on a lot of their own increased funding
costs, rather than making enormous profits at that time, because
it is a reality that their own funding costs in the longterm
capital markets were increasing dramatically. In terms of looking
at new funding sources: we are absolutely keen on bringing pension
funds into the market and interestingly there was a recent transaction
earlier this year, which was the Southmead Hospital in Bristol,
where the bidder ran a competition between bank finance and bond
finance and the bank finance came out cheaper. As Treasury we
did not think it was appropriate to tell the Southmead Trust to
pay more for the bond finance than the bank finance. So there
is competition in the market and the bond finance was more expensive.
Q105 Austin Mitchell:
Not much.
Andy Rose: Not,
not much, but remember this is money raised by the private sector
and the public sector has a huge interest in that it pays unitary
charge and therefore had they selected the more expensive finance
that would have been passed on to the Southmead Trust. I think
the IUK document, and I work for IUK, as Andrew suggested, looks
at a number of different markets and not just PFI but very much
economic infrastructure as well, where a lot of the finance is
raised in a very different way; it is more private to private.
These aren't concessions left by the public sector. Yes, I think
looking at reducing the cost of capitalthere will be a
regulatory review undertaken over the next few monthsis
critically important. Yes, absolutely we need to continue to
explore different forms of finance.
Q106 Chair:
Can I just ask the question: is there a future for PFI in this?
You are looking at all these alternatives; given where we are
on loan rates, is there a future for PFI?
Andy Rose: Again,
I think it goes back to the selection of the authority of a prudent
methodology and whether that's value for money. The view, as
Charles articulated earlier, is that, based on individual deals
at these margins, it can be value for money, yes.
Q107 Chair:
Amyas, Jo and then Stephen.
Amyas Morse:
Thank you Chair. I just want to make
sure of some of the points in the report. Although we said that
the additional funding costs in the special circumstances and
with the policy direction were overall value for money, we made
some, I thought, intentionally trenchant points. First of all
it wasn't just additional financing costs, it was also transfer
of risks by the banks to the Government. So they took the chance
to improve their position there. Secondly, going forward we are
very clear that we think much tougher criteria need to be applied
in assessing value for money on PFI projects in future and, if
there are changes in the financing cost component, the margin
of tolerance that the Treasury will accept before requiring a
restated business case should in future be much narrower. We
made all of that very clear, so I think we should let the market
decide if there is a future for PFI and if it doesn't meet those
tough criteria then let the answer be what it may. If I may,
one thing, Chair, is I thought Mr Swales's comment about the very
substantial amount of the value in any PFI deal that represents
the maintenance and operating agreementI felt we passed
by that without really hearing a very full answer, if I may say
so.
Q108 Chair:
Mr Hudson.
Andrew Hudson:
I think on Mr Morse's pointsthe more exacting testsI
stressed all along that we have been rigorous in assessing value
for money but, as I said just now, public money is a whole lot
tighter and we certainly need to keep our eye very much on that
ball. As to the threshold, whether we should have a specific
number and what that should be, that's under consideration and
we're going to put out some more guidance shortly, but we'll draw
together the lessons of the whole of this episode, and we'll take
a final decision on whether to have a specific threshold above
which projects need to come back for reapproval or some
demanding test, but not a point estimate, in the course of that
piece of work.
I'm sorry if we didn't cover between us the point
that Mr Swales was driving at, and Charles Lloyd may want to say
a bit more, but the way I see it is that through the construction
phase there is a considerable risk and that is reflected in the
premiums that are paid. After that, the risk comes down; it isn't
eliminated altogether and, as Charles explained, there are reasons
why the financing, the design, the building and the operating
are held together in these contracts, because that gives the incentive
for the private sector provider to take the right decisions at
the design stage and the right decisions in preparing its operations
to provide best value for money over the lifetime of the project.
That's why the financing is integrated but with these strengthened
provisions for the public sector to benefit once the risk reduces
as the construction is completed.
Q109 Ian Swales:
My point was really that the fantastically complex structure of
these deals means that the whole risk is tied together. You have
people assessing everything from the construction of something
to how something might operate in 20 years' time. As the report
says, that can deter people from getting involved, including pension
funds, because they may not have the resources to assess all that
risk. So my question was: is there a way of unbundling it so
that we get the proper risk premium separately on the two key
stages of any deal?
Andrew Hudson:
Do you want to say a bit more about how these risk premiums are
worked through?
Charles Lloyd:
Yes, I suppose conventional capital procurement in Government
is an unbundling of the risk, so we get a construction contract
and then offer an operations and maintenance contract. That is
certainly one way to do it and indeed the great majority of capital
is procured in that way, as opposed to on a PFI basis. The problem
with that though is that the public sector, the client, sits in
the middle and at the point where the construction risk switches
to the operations and maintenance risk, what is passed back to
the public sector is the risk that the building was built inadequately
in the first place or was not suitable for the most efficient
form of maintenance. Yes, absolutely, we can do that, but we
shouldn't do that and pretend there is no risk in that to the
Government.
Q110 Ian Swales:
Well all I'm saying is it's two packages, not one, isn't it on
most of these projects? The building of a hospital is entirely
separate to the operating of the hospital
Charles Lloyd:
But if you
Ian Swales: Sorry, just
to finish my pointwith usually completely different commercial
players carrying out the work. So, Shepherd Construction might
build a hospital, but they are not going to operate the hospital.
Ed Humpherson:
Can I make an intervention here and ask,
Mr Lloyd, particularly about the bundling of facilities management
services into PFI contracts, because I think that goes to the
heart of the point Mr Swales is making. It is not simply a bundling
of capital with the maintenance, but it's the bundling of the
capital with the maintenance, which one understands makes some
sense, with things like security and cleaning and catering, all
of those things, which add to the complexity.
Q111 Ian Swales:
Just to emphasise that point, as we heard earlier we've never
had a default on a body not being able to pay for the construction.
We have had two cases, I think you said, where it's the operation
that falls down. So the two risks are different.
Charles Lloyd:
So, to pick up on Mr Humpherson's point, I think there is a clear
case for combining in a contract the construction of an asset
and then the maintenance of that asset
in order to get the cheapest wholelife cost.
There are different issues that arise when you look to also bundle
into the contract what we would call soft services: cleaning,
catering, security, IT helpdesks and all of that. We've issued
a lot of guidance on this in the past, which I think has made
clear that the Government, the Treasury, do not insist that those
services get bundled into those contracts. Each authority is
expected to make an assessment of whether there are benefits in
bundling those services together or not.
Q112 Chair:
Is there a value for money issue there as to whether or not you
do? Have you looked at that? So is it better trying to untangle
this debate? Were you not to incorporate those into the PFI would
you get better value for money or not? Have you looked at that?
Charles Lloyd:
I think the answer to that would probably vary significantly between
sectors. So if I take a couple of sectors, in the prison sector
I think there is quite a case for integrating all services so
that you have one provider who is providing every service to do
with that asset. Indeed that has been the model. I think in
other caseshospitals, schools are ones that come to mindwhere
in any event the Government's policy has been that the front-line
delivery of services remains a public sector jobteachers,
nurses, doctors and so onthere is more room for discussion
and debate.
Q113 Mr Bacon:
It is not that uncommon to unbundle. I visited the new Belfast
cancer centre some years ago, where they had done the building
and the machines that go inside it in different ways. One was
conventional and one was PFI. I can't remember which way round
it was, although originally they had assumed they'd do it all
in one group, they found it was better not to. When Mr Swales
said there are two components here I think he was perhaps even
understating, because there are three: there is the original construction,
there is the operating, and then there is whether you keep it
at all or whether you sell it off into the secondary market.
The House of Lords Economic Affairs Committee said more work should
be done on this.
Now, Mr Hudson, a minute ago you were saying there
is of course a way to share with the taxpayer the gains once the
risk is reduced, but it says in paragraph 3.9, "Treasury
guidance currently permits such equity sales without the sharing
of resulting gains with the public sector." Are you going
to change your guidance on that? Why shouldn't the taxpayer get
a share of gains from equity sales? At the moment there is an
incentive. This happened with the Norfolk and Norwich Hospital;
they refinanced the project. At the time they refinanced it they
put an extra £100 million, £106 million of
debt on top of it. Interest rates were falling at the time; the
internal rate of return went from 18% to over 60%. Essentially
they extracted all their profit or most of their profit from the
35year deal up front. Well, you don't have much interest
then, once you've already got all your profit out of it, in whether
you run the contract in the way that PFI theology says that you
should over the life of the contract. In fact, the House of Lords
called for further investigation of any impact on service delivery
that may result from the sales of shares. So if you believewhich
you do, because you just said sothat taxpayers should share
in the gain, for example from the reduction of risk and the consequent
refinancing, why don't you do the same for equity sales?
Andrew Hudson:
Well, that is something that we are working on as to how we would
respond.
Q114 Mr Bacon:
It says, "The Treasury has yet to publish research on the
contribution made by equity investment at various stages in the
life of a public-private partnership." When will you be
producing research?
Andrew Hudson:
I don't have a date for that yet, Mr Bacon, but it's something
that we're working on.
Mr Bacon:
Right.
Q115 Joseph Johnson:
Turning back to TIFU please. The credit crunch hit in full in
late 2007. TIFU wasn't set up until March 2009, 15 to 18 months
later. If I understood your earlier answer, I think you were
saying it's no longer going to be funded going forward as of the
spending review. What steps are you taking to ensure that, in
the event there is a new freeze-up in capital markets and in bank
lending markets, there won't be a similar hiatus that causes UK
PFI projects to suffer from lack of access to finance?
Andrew Hudson:
Well, I think having gone through the process of setting up TIFU
and working out how it might operate, what the appropriate governance
is, although it is not being funded at the moment, it would be
much quicker to turn that facility back on again.
Q116 Joseph Johnson:
Are you retaining the staff that were associated
Andrew Hudson:
Yes.
Andy Rose: One
of the things that IUK has enabled us to see, and particularly
the mandate it has around looking at the critical area of inward
investment for the £200 billion that was articulated yesterday,
is that an enormous amount of work with finance expertise is required.
So examples are working with UKTI on inward investment, working
with BIS on the Green Investment Bank, working with DECC on the
electricity market reformareas where we think finance expertise
is critical to be successful. So we have retained a degree of
operational flexibility in that capability is retained and employed
in IUK, but no funding is currently provided by Treasury.
Q117 Joseph Johnson:
I suppose what I'm driving at is it would seem, from the decision
to cease funding of TIFU, that you've reached a sort of epiphany
in terms of your understanding of what the role of the Government
is; whether it really is the role of the public sector to lend
to itself in order to enable private players to cream off the
very rich returns that are available from participating in PFIstyle
projects, or whether you actually do believe that that is a good
way of proceeding.
Andrew Hudson:
I was just going to say that the policy was always that TIFU's
activity should be temporary and reversible. As it turned out
there was only the one loan and, given the present state of the
market and the work that is going on on other financing sources
that we've talked about, we felt that it was time to be clear
that there wasn't funding for other projects.
Andy Rose: Yes,
I think a lot of it is to do with the statements around the spending
review, where public finances are just more constrained. I think
TIFU can only be credible if it has a budget that it can lend,
and to allocate funding to an entity that had not lent for a year
and a half, I think, people felt was inappropriate.
Q118 Jackie Doyle-Price: Going
back to what you said earlier, Mr Rose, about when the contract
regarding the M25 widening was concluded successfully, if we look
at the figures in the report we see that there was a massive increase
in costs by 23%, and that much of this was down to increased financing
costs. On what basis can you say that was concluded successfully?
Andy Rose: Well,
first of all I'm aware that there is an independent report due
on that so I won't comment too much. What I meant is that, from
a TIFU perspective, the money was made available from the private
sector, and therefore it was completed without TIFU being asked.
In that case, the Department for Transport had made money available
should it be needed and that was never used, but I am very conscious
that there is a separate report pending on that transaction.
Q119 Jackie Doyle-Price:
What I'm trying to get to is the degree of challengethat
you really considered the value for money aspects of this in terms
of securing this as a way of finance, because this is a considerable
increase in cost from what was originally
Andy Rose: Again,
from a TIFU point of view, we were very clear to separate the
policy role that was held by Charles and the transaction role.
So TIFU was staffed by senior project finance specialists from
the market with the hope that it would give confidence to taxpayers
that money was lent very professionally. We did not take a policy
view about value for money because we didn't want the market to
see policymakers only, and there was a very clear separation between
TIFU's activities and the policy activities of Charles. When
I talked about it being successful, I meant the private sector
delivered that transaction without recourse to TIFU.
Q120 Jackie Doyle-Price:
So you are talking about success in terms of negotiating a contract,
rather than seeing it against the broader scheme of
Andy Rose: To be
fair, I'm coming from a very narrow perspective and my comment
was that at that stage my role was solely to lend when asked to
and there was a very comprehensive process that we went through
before a lending request would come into TIFU.
Q121 Jackie Doyle-Price:
Perhaps Mr Lloyd might have an observation to make on this particular
case.
Charles Lloyd:
Yes. The Treasury was heavily involved in the M25 transaction,
both through my team and through the spending team, as you would
expect given the scale of the transaction. I would say that our
principal role was to make sure that DfT and the Highways Agency,
which was the authority for it, had done everything it could to
create the maximum amount of competition for the funding of that
deal, and had applied our value for money and our other PFI guidance
appropriately. We were heavily involved in working with them
to ensure that they did assess value for money, that their accounting
officer was aware of the value for money consequences and the
price increases, and considered all of that. It's for the DfT
and the Highways Agency accounting officer to come to a view,
in the first instance, on value for money, but we wanted to make
sure that they were aware of those issues and thought about them
properly, and no doubt the NAO will comment on that in due course.
Chair: Austin then Ian,
and then I just want to draw it slightly into the future before
we come to a close.
Q122 Austin Mitchell: I've
just got a couple of requests for information. Mr Hudson, in
your answer to Richard Bacon on why you haven't made arrangements
to get some return for the taxpayer from these refinancing dealswhich
have been going on a long time, are clearly profitable, and exposed
by Private Eye, my usual source of information, for a long
periodyou say you are still thinking about how you can
get some return for the taxpayer. That's absolutely extraordinary.
This is a major racket. Much money has been made out of it,
and you haven't decided yet how you can get a return for the taxpayer.
Now can you supply us with information
Mr Bacon: I wasn't talking
about refinancing, I was talking about equity sales.
Q123 Austin Mitchell:
You were saying refinancing is a cost.
Mr Bacon: They already
get a share of the refinancing gains. They don't get a share
of the equity sales gains.
Q124 Austin Mitchell:
Right. Can you give us an indication of how many deals of this
kind there have been, in sales of the equity and refinancing?
Not now, but if you can give us a note.
Andrew Hudson:
Refinancing, in terms of the financing costs of the projects,
we have taken steps over the years to increase the share that
goes to the public sector. We don't keep a central track of how
much the public sector has recouped from that, not least because
the projects are spread over probably hundreds of local authorities.
Q125 Austin Mitchell: Do
you not issue any guidance?
Andrew Hudson:
It is not just guidance; we have a standard practice agreed with
the market as to what the refinancing gain share is. The point
I was answering Mr Bacon's question on was a more specific area
of equity stakes and so on, and that's more complicated, and that's
where work is still going on. I don't know whether Charles Lloyd
can answer this point.
Charles Lloyd:
Just to comment briefly on it, obviously refinancing is a major
source of profit to equity, and we've addressed that in the way
that Mr Hudson describes, but equity can make profit in other
ways as well, by trading its shares. Until this point in time,
the view the Government has taken is that there is a benefit in
having a liquid secondary market in equity in private finance
transactions. It enables, for example, the contractors, who often
invest in this up front, to recycle their capital, to put capital
into other new projects in due course, and it's clearly in the
Government's interest that there is a liquid market. The more
liquidity, the cheaper the price of equity is. So I think
Q126 Austin Mitchell: Surely
it's in the Government's interest also to get a return on this?
Charles Lloyd:
I think if the Government were to say, "We will have a slice
of the profit that equity makes, absent refinancing," you
have to trade off on that the disincentive effect for those sales
to take place. That's a judgment , and so far Government have
always come down on the view that liquidity in the market is good
and outweighs the initial income we might get from clawing back
some of that profit.
Q127 Austin Mitchell:
There's no indication of the scale?
Charles Lloyd:
I'm sorry?
Q128 Austin Mitchell:
You've no indication of the scale; the number of cases in which
there hasn't been
Charles Lloyd:
There has been a lot of secondary equity trading transaction activity
over the past several years, so it is fairly common for equity
in these transactions to be sold.
Q129 Austin Mitchell:
Okay. Well, the second question, for information: we're looking
at projects which were stopped by the credit crunch in this report,
but the report says, in paragraph 1.9 on page 17, that "delayed
projects were also vulnerable to the credit crisis". It
instances the M25, where costs increased by over £600 million
because of delays in the contract, which then had to be refinanced.
Do we have an indication, or can you give us an indication, of
how much extra costs accumulated because of refinancing problems
like that?
Charles Lloyd:
I suppose the best estimate at the moment is probably the NAO's
work, which looks at the cost of finance pre-credit crunch and
the cost of finance now, and estimates that in those projects
which have closed, costs are now £500 million to £1 billion
higher than they would have been at the lows of the financing
markets.
Q130 Austin Mitchell:
But you don't have a list or information you could give us?
Charles Lloyd:
We have a list of all projects that have closed, and I suppose
we could look at, hypothetically, what I think the NAO must have
done, and hypothetically what they would have cost had they closed
in, let's say, 2007 and what they actually cost now.
Amyas Morse:
Pardon me, Austin. What we explained
before the hearing is that it depends. We looked at around a
range between £500 million and £1 billion
because that depended where you take the starting point in the
marketplace to be. I think going back a bit, the very keen market
just before the financial crisis, that would give you £1 billion,
and if you went back a bit further, it would be £500 million.
So that is why there is a range. Can I just say on equity sales,
our understanding, as we sit here and try and estimate, is that
we think there have been a very substantial number of equity sales,
at least 150 different equity sales that we can pick up, and some
of those equity sales were sales of portfolios of equities rather
than individual equities. There is a very active trading market
in equity stakes in countless instances.
Q131 Chair:
Is it your view, is it the NAO view, that there is a potential
there for some money back to the taxpayer out of that?
Amyas Morse:
Perhaps I can put that a different way.
Because people aren't doing these trades for fun, therefore I'm
assuming that they're doing it to realise gain. Therefore, if
you were able to establish that there is a pattern of systematically
realising gains through trading equity as well as refinancing
debt, you would imagine there might be a case, and I gather already
from what Andrew Hudson has said that it has been considered,
of saying, "We want to capture some of that gain from private"
Q132 Chair:
Do you agree with that, Mr Hudson?
Andrew Hudson:
It's clearly something that we keep an eye on. Charles Lloyd
has explained the reasons why Government policy so far has been
not to seek to intervene in that particular bit of the market.
If we can say any more, then we will let you have a note.
Q133 Chair:
Just to pursue that, at present there is no review taking place
that would suggest that, in the equity market in PFIs, we would
look to the Government recouping some benefit from the profits
made?
Andrew Hudson:
We work on it in the sense that we keep an eye on how this market
is working.
Q134 Chair:
But that's very vague, isn't it?
Andrew Hudson:
It's not a review as such. There is no review as such going on
at the moment.
Q135 Mr Bacon:
Mr Hudson, do you keep an eye on who the owners are? Do you know
who all the owners are of these assets that are providing public
services?
Andrew Hudson:
We do.
Charles Lloyd:
Yes, we do.
Q136 Mr Bacon:
So you wouldn't have North Korea buying one of our hospitals without
our knowing about it?
Charles Lloyd:
We don't try and manage through the contract who the owners are.
Q137 Mr Bacon:
I'm talking about after the initial construction phase and possibly
any refinancing. I'm talking about whether, in the secondary
market, once the asset has been sold and perhaps sold againand
the C&AG said that he was aware of 150 or so such transactionsand
perhaps sold again two or three times further, do you, at each
stage, up to and including the most recent owner, know who the
owner is?
Charles Lloyd:
We know who the owners are. Other than in a very small subset
of sensitive defence contracts, the contracts don't contain arrangements
precluding certain categories of people from owning that equity.
Q138 Ian Swales:
Can I just ask, because I think we need to move on to the end,
just one specific question, because I think that there's quite
a bit of confusion about policy. In March this year, a new hospital
was announced for the area between Stockton and Hartlepool, costing
£460 million. The Trust was told it would be funded
directly by the Department of Health. Does that make any sense
to you?
Andrew Hudson:
There will always be a judgment; there's always been a mixed economy,
if you like, in terms of some facilities in different sectors
being provided through public money, some through PFI. That's
a judgment as to what's appropriate in each case.
Q139 Ian Swales:
Why would a £460 million hospital suddenly be funded
by the Treasury, as opposed to PFI, which I understood was the
normal way of doing these things?
Andrew Hudson:
I'm afraid I'm not familiar with that particular example, but
it would be a judgment based on the availability of public finance
and a value for money judgment.
Q140 Chair:
Why don't we get a note on that one?
Andy Rose: I think
it's fair to agree with the NAO. The NAO suggests there should
never be an assumption that PFI is value for money, and I think
that has always been Treasury's view; that there is no assumption.
I don't think the default situation is it should be PFI
Q141 Mr Bacon: It
was in the case of the tanker. Sir Bill Jeffrey described it as
"the conditions we were operating under at the time",
which is the best euphemism I have heard for the former Prime
Minister.
Andy Rose: My understanding
is that that decision was made a very long time ago. I don't
think in current Treasury methodology there is anything that says
there should be a presumption that it should be PFI.
Chair: I don't think it
was that long ago.
Q142 Stephen Barclay:
But you weren't re-assessing these, so you were basing it on an
earlier presumption. You were saying, because of the urgency
of the market, we are not calling these back in for reassessment.
Andy Rose: That's
the PRG, which is around local authority transactions, where it
is. On FSTA, it is my understanding that that decision to go
down that route was a long time ago and I believe that was not
reassessed.
Q143 Stephen Barclay:
Well, the project team advised against it in 2004 on the Air Tanker.
Q144 Ian Swales:
There are different policies adopted for different things. We
also heard that various things are under review at the moment.
Do you regard this review as being total, or are there some sacred
cows in terms of policies and things where we won't be looking
under the stones?
Andy Rose: I think
the reality is there's been quite a lot of change over the last
six months, from the General Election to the Spending Review to
the National Infrastructure Plan. There's also a cost review
ongoing. I think it's quite a good time to review quite a number
of things. I think there will be an update to the market about
some of the mechanics, about how PFI works; there will be an update
on the value for money guidance. I think it is quite a broad
review; I wouldn't necessarily say that it encompasses everything,
but I think the reviews at this time will be quite broad.
Q145 Chair:
This takes us into the future, really, because we had the infrastructure
report yesterday. There is going to be a steady decline in capital
infrastructure over the Spending Review period by, I think, nearly
30% when we get to 2014-2015. However, am I right in thinking
that the imperative will be to keep as much of that as possible
off balance sheet? Can you answer that first?
Andrew Hudson:
Whether something is on or off balance sheet is a technical categorisation
issue. The aim is to use that capital spending and it's explained
which Departments it's going to, in the best possible way to fund
the key projects.
Q146 Chair:
No, it isn't technical, because you will not be able to afford
to get it on balance sheet if we're to get the cuts in public
spending that the Government seek to achieve.
Andrew Hudson:
Well, the amount
Q147 Chair:
It may be technical in the sense that you want it to stimulate
other activity in the private sector. I get that. On the other
hand, given the constraints on public finance, you won't be able
to do that through techniques that are traditional, on-balance
sheet capital investments. Can you?
Andy Rose: I think
it's important to recognise that many of the markets covered by
the National Infrastructure Plan are more in the areas of economic
infrastructure, where the money is raised by the private sector,
such as the large utility companies in the energy market. The
PFI is not part of
Q148 Chair:
But the £40 billion, if you stick to the £40 billion
that will be our per annum capital investment from Government
by 2014-2015, where's that going to come from? On balance sheet?
Off balance sheet?
Andrew Hudson:
The public sector capital is on balance sheet.
Q149 Chair:
That will all be on balance sheet?
Andrew Hudson:
Yes.
Q150 Chair:
So there won't be a PFI element to that at all?
Andrew Hudson:
Some PFI is on balance sheet. I think 24% of transactions have
been on balance sheet; the rest, three-quarters or so, has been
off balance sheet. The key thing in judging whether a PFI project
goes ahead, now as before, is whether it's good value for money,
because it has to be paid for, and in the case of PFI it's paid
for from a Department or local authority's resource budget, rather
than from its capital budget, so that all needs to be paid for
out of scarce resources. That will only go ahead, on or off balance
sheet, if the Department judges that it's value for money.
Q151 Chair:
I'm trying to work out the role of PFI in the future, as we come
out of the credit crunch. We've said that loan rates remain high,
so that will become a disincentive to go down the PFI route.
Right or wrong?
Andy Rose: Could
I just clarify? I beg your pardon. The £40 billion
per annum, some £200 billion in the National Infrastructure
Plan, the vast majority of that is delivered by the private sector,
and it is not public sector capital at all. PFIs, I think, will
be used selectively in certain sectors, where it's proved value
for money, but the vast, vast majority of that £40 billion
per annum is not public sector capital; it's raised by the private
sector for investment in, for example, water, energy, digital
and areas like that. That number is a much broader arena than
just the areas previously handled in PFI.
Q152 Chair:
In which areas can you see PFI playing a continuing role, given
where we are on loan rates, which I don't think are likely to
change during the CSR period?
Andrew Hudson:
I think it could still have a role in the various sectors where
it has had a role over the years. Certainly authorities making
these judgment s will have to be very rigorous and apply the exacting
tests that the NAO are calling for, in judging whether it's still
value for money. They have every incentive to do that, because
for most Departments, if not all, the revenue budgets, out of
which future PFI projects will have to be funded, are also constrained,
the same as, as you say, public sector capital is constrained.
The point of the National Infrastructure Plan is to look at this
in the round, as Andy says, covering public and private sector,
and look at some other things we can do to try and get the infrastructure
we need, by whatever means, spanning public and private, at the
best possible cost? Mr Swales talked about are there any sacred
cows? The one sacred cow, as far as I'm concerned, is to get
the best possible value for money for every pound the taxpayer
spends, which obviously is a shared interest round the group.
Q153 Chair:
'Twas ever thus.
Andrew Hudson:
'Twas ever thus, but at a time when public spending is severely
constrained, it's all the more important that we redouble our
efforts on that. Some of the things that the plan talks about,
like looking into why we appear to have a substantially higher
cost of construction in this country than some of our competitors,
looking at how we can get the cost of capital for infrastructure
projects down, looking at things like the Green Investment Bank
as another way of bringing a certain amount of public spending
to bear on getting better infrastructure for green projects, are
all moving in this direction of getting the best mix. What that
mix will be, will vary over time and will vary from project to
project.
Q154 Chair:
With the new localism, will you be allowing local authorities,
whatever the new health bodies are, et alGP Commissioning,
whatever they are, commissioning bodieswill you be allowing
them to take the decisions in this infrastructure world, or will
you be retaining central control of all this?
Andrew Hudson:
The final decisions have always been for authorities, because
in the end, for local authorities, it is the Section 151 officer
who has statutory responsibility for advising the council on whether
something is value for money. We do certainly plan to keep going
with central guidance, with the availability of central support,
and with review mechanisms, because we feel that those have helped
to drive better value for money across the board.
Q155 Chair:
You won't stop projects at those sort of levels, at local authority
level or whatever health service level we're talking at?
Andrew Hudson:
Charles can perhaps explain how the Project Review Group has operated.
Q156 Chair:
I know how it's operated in the past, but it's a very centralist
mechanism for controlling the process of infrastructure investment.
We now have a Government that says it wants to localise and decentralise
this all; I'm just wondering whether this will be true of infrastructure
or whether we will carry on with the current centralist controls?
Charles Lloyd:
I'm out of the Treasury now, so I don't know. I suppose, in an
area that creates as much attention as PFI does, my own view is
that I would be surprised if there wasn't some continuing degree
of Treasury scrutiny of those transactions. Exactly what that
will consist of will be for others to decide, rather than me.
Chair: Okay. Anne, then
Stephen.
Q157 Mrs McGuire:
Can I just ask for some clarity on the £40 billion,
because the implication in the Commercial Secretary's foreword
to the national plan implies that that is Government money, whereas
I think Mr Rose said that that was a mixture of private and public
money.
Andrew Hudson:
I think the
Andy Rose: Sorry,
can I clarify? There are two £40 billions, unfortunately.
There is the £40 billion per annum, which is a mixture
of public and private over the five years, and then there is the
total of £40 billion that is public spending. Unfortunately,
there are two £40 billions. When Lord Sassoon said
"We are committed to invest over £40 billion in
supporting project investment," that is more the public spending,
where again the focus was on economic infrastructure that led
to growth. The £40 billion per annum is more the total
expenditure, which is the £200 billion that is referred
to elsewhere.
Q158 Mrs McGuire:
Which is a mixture of public and private? Or is that totally
private?
Andy Rose: No,
that's a mixture.
Q159 Mrs McGuire:
That's a mixture. Could I just develop a wee bit the questions
that the Chair has asked you about the future? If public authorities
find themselves between a rock and a hard place here, i.e. there's
constraint on public spending, that the market is too high, do
you have any idea of what our infrastructure development is going
to be like in terms of education, hospitals, whether or not these
public authorities will be in a position to make decisions about
investing in that type of infrastructure project? Or will we
be, in fact, seeing a situation, which once happened, where there
were very few schools built and even fewer hospitals?
Andrew Hudson:
As far as public spending is concerned, the Government have set
out the capital plans for both health and education, and that
will govern what the public sector can spend over the coming four
years. As to whether those Departments choose to go ahead with
further PFI schemes, I think there's been a lot of attention paid
to Building Schools for the Future. There's a review under way,
but the intentions there are clear. On the hospital side, there's
a certain amount of public sector capital available, and the Department
will no doubt be considering how it wants to use its future resource
budgets, and whether building further hospitals is something it
wants to give priority to compared with other calls on the resource
budget.
Q160 Mrs McGuire:
I'm not quite sure if that's a yes or no.
Andrew Hudson:
It's
Q161 Mrs McGuire:
That's definitely a Sir Humphrey answer. Can I ask one more question
on construction costs? I think sometimes it's quite easy to draw
international comparisons, as have been done in the foreword.
I wonder whether or not there will be an attempt to judge construction
costs, not just in terms of how much money they cost, but whether
or not we have a regulatory regime in this country that makes
our construction industry one of the safest industries in Europe.
All of the higher construction costs are not just about the way
the financial market operates in the UK, but relate tothere
is still all sorts of room for improvementsome of the lowest
rates of fatalities and injuries on our construction sites anywhere
in Europe. Will the Treasury be considering that aspect of the
construction costs?
Andy Rose: There
is an extensive review being led by Terry Hill from Arup, and
IUK are supporting that; as you suggest, the cost of construction
is not just a simple number. It encompasses an enormous amount
of areas. I think there was something posted on the Treasury
website yesterday or before, but the final report should come
out late DecemberI think that is the current estimate.
As you suggest, it will address the issue that the cost of construction
is not just a simple number, but encompasses an enormous amount
of issues. I'm sure that things like health and safety will be
factored in, so that will not be left out of consideration.
Q162 Stephen Barclay:
Could I just take Mr Rose back to something he said earlier, about
a recent PFI deal where bank finance was chosen over bonds. Is
there any difference in the regulatory treatment of risk between
banks and insurers?
Andy Rose: I'm
not an expert; I'm sure there may well be.
Q163 Stephen Barclay:
What I was trying to drive at is, is there any regulatory arbitrage?
We talked earlier about the desirability of getting pension funds
into these longterm investments. If you look at the earlier
projects like the Channel Tunnel, that was driven by the insurance
market and bonds, and there was a potential backlash after Equitable
Life. I'm just trying to understand: is there a difference in
treatment in the way the same risks are being assessed between
the way banks are financing it and the insurance market is?
Andy Rose: Again,
I am not a regulatory expert but I'm sure all the regulators for
different markets apply capital differently. From the purpose
of the Trust that is paying for it, that's a completely different
thing. My point was, are we beholden to the banks? No. We do
look at, and encourage authorities to look at, a range of funding
options, and then run a competition. Are there reasons that those
prices vary, that are driven by regulation and capital allocation?
Very possibly, but
Q164 Mr Bacon:
This is a very interesting pointI don't know, maybe for
Mr Hudson to answer. Surely the point is, if there are differences,
it might be that pension funds are not as eager as they perhaps
could be, because there are regulatory inhibitions that perhaps
need not be there. To take a slightly different case, the reason
the French and German banks filled their boots with the Greek
Government bonds wasn't because they trusted the Greek Government,
it was because Greek Government bonds were regulated as if they
were the same risk as buying UK gilts, or German Government bonds,
and therefore the bank had to set aside the same amount of capital
as it would if it were buying UK gilts, but gets a better return,
because everyone knows that Greek Government bonds are dodgy,
so the yield is high. So I think that's the point Mr Barclay
is making. If, in the same way, or in the reverse way, pension
funds were being inhibited from investing in these vehicles, because
of regulatory constraints, you're the guys who've set the regulations,
at the end of the day.
Andy Rose: I think
it's a much broader discussion about the appropriateness of the
regulatory regime for insurance companies and pension fund investors,
which, again, I don't feel well enough versed to
Q165 Stephen Barclay:
But Treasury is the driver; clearly, the FSA, and even the Bank
of England, will set the regulatory landscape in conjunction with
European authorities. But HMT has a big say in this, and my point
is: the policy you're setting, again, is pointing in two different
directions. Linking on to that, what concerns do you have that
Basel III will put up the cost of finance for banks?
Andy Rose: It is
back into the same area of regulation, and again I think Basel
III has developed quite a lot over the last few months, so I think
the banks would say they are concerned about any change that causes
the costs to them of long-term funding and of investing in long-term
assets
Q166 Stephen Barclay:
If they have to hold more capital for these long-term loans, they're
going to have to put their prices up.
Andy Rose: It goes
back, I'm afraid, to my prior answer. I understand that point,
that if holding these loans increases the cost to them, that will
mean that will be a risk that they will pass on, but it brings
in so many different constituent parties to whether that is the
appropriate thing to do or not, that I absolutely accept the point
that if there is a regime that increases the cost to them, they
would attempt to pass it on. I don't feel well enough versed
to give a view on Basel III and the implications.
Q167 Stephen Barclay:
To me, you see, if we look at paragraph 27, the NAO is warning
on the value for money for subsequent projects. In its paragraph
23, which is on page 10, it's saying, "The usual cost advantage
lay in a range of 5% to 10%" some of which, when they audited
it, showed smaller savings. Yet the annual contract charges are
going up by 16% to 17%. We have touched on this tension in some
of the earlier questions, but if there's regulatory hurdles in
terms of the access to this market for the insurers, which is
why they're losing this competition you just referred to, and
also the banks' costs through Basel III are going up, then the
viability of PFI surely comes under more pressure?
Andy Rose: I will
go back to Mr Morse's comment earlier about the recommendations
the NAO makes about transferred risk across the criteria; I think
we welcome that. I think as part of the review we're doing, we
will certainly take those recommendations on board, and we are
looking at this, but as I say, there are other areas in the marketglobal
banking regulationthat may have an impact, and that would
ultimately drive into the value position of the overall PFI valuation,
because the finance is one component of that evaluation.
Q168 Stephen Barclay:
We heard with these major projects, because of the urgency and
the macro-economic climate, individual assessments were not called
in, because there was seen to be an overarching policy priority.
In terms of PFI projects that haven't closed as of today, will
you be reassessing those?
Andrew Hudson:
That's a continuing exercise of the Treasury, whether through
the Project Review Group or through the Treasury spending teams
doing their work on the value for money of a project, and of the
Department doing its work on value for money, because in the end,
responsibility rests with the Accounting Officer, to satisfy himself
or herself that a project is still value for money.
Q169 Stephen Barclay:
Sure, but, Mr Hudson, we've heard in reply to Mr Johnson's questions,
about the role of the Treasury as the green-light body on this,
and the role moving forward in terms of having some sort of central
controlit just seems strange. What I am trying to understand
is what has changed. We have a clear reason why individual assessments
were not done in this report, because we were told there wasn't
time. There was a policy objective that overrode that need.
What I'm saying is: is that policy urgency in terms of time still
a constraint, and if so, when is it going to be lifted? Or if
not, why is it that individual assessments are not being called?
Andrew Hudson:
Those deals that have closed
Q170 Stephen Barclay:
The ones that haven't closed, I'm talking about.
Andrew Hudson:
They will be going through a scrutiny process at the moment, which
will take account of current market conditions.
Q171 Stephen Barclay:
Presumably some of those won't go ahead.
Andrew Hudson:
If they're good value for money, they will go ahead; if not, they
won't. As Charles Lloyd says, through the period that we've been
talking about, some were sent back for further work.
Q172 Stephen Barclay:
It's just that on the reports I've seen today, and we take the
Air Tanker one, there was a pressing defence need for it to go
ahead, so a different valuation discount was applied. The waste
one was a regulatory and legal requirement, not to mention a political
requirement, driving that, and therefore value for money figures,
dare I say it, surprisingly were made to fit in order for that
to go ahead. It's very difficult to see which PFI deals have
been turned down.
Q173 Ian Swales:
What proportion are turned down for good? They disappear because
they're not good value for money? What proportion?
Andrew Hudson:
I think the best evidence that I'm aware of is that, of the 35
that went ahead, six, I think, were sent back to be looked at
again and were then able to renegotiate or redo the deals such
that it did turn out to be one that the Project Review Group felt
able to support.
Q174 Stephen Barclay:
They went ahead with TIFU to renegotiate on them
Ian Swales: What changed
on those six? What changed?
Stephen Barclay: It didn't
go to the comparison and then say "We're going to fund it
in a different way". What happened was it just went back,
but it still went ahead as a PFI deal.
Charles Lloyd:
Some go ahead as PFI deals; some don't go ahead at all. Andrew
Hudson is exactly right that of the deals that came to us we sent
six back, for a range of reasons. I think it's important to remember
that most of these deals come to us at a fairly late stage in
their evolution. They've been thought about a lot by the authority,
they've put a team together, a business case and so on. Many
of the deals never get to that point, and we don't see the deals,
obviously, which don't get to us. They don't get to us because
they are not value for money, because they are not affordable,
so we don't have data on that set of transactions.
Andy Rose: There
are two other recent developments. One is, in the Spending Review
it was announced that funding would not be available for certain
PFI schemes, and also there is a change in the PFI credit regime,
whereas now Departments have to look at their spending in the
round, they are not having the allocation of funding for PFI credit.
I think there have been profound changes in making sure there
is a level playing field when these Departments look at their
particular PFI budget.
Chair: I'd like to just
draw us to a close. Richard, then Ed wanted a quick one and then
that's it.
Q175 Mr Bacon:
Three quick questions; if perhaps you could give quick answers,
because I know the Chair does want to finish this. There's an
intriguing sentence in paragraph 3.8 of the NAO's report, which
talks about how once in operation, many of the risks that you
have during the construction phase fall away, "Making possible
an approach that coordinates the right to refinance by a number
of public authorities." Is that saying, or have you thought
about, the possibility of, once they are all in operation, bundling
up a whole load of different projects together, which would also
make it more attractive to a longterm institutional investor
like an insurance company, offering something larger to a larger
investor? Perhaps even through one entity that ends up having
the legal right to receive the annual unitary charge payments,
and then passes them on? Has that been considered yet?
Andy Rose: The
answer is yes.
Q176 Mr Bacon:
And once you've done that, of course, then you could securitise
it, which is my note.
Andy Rose: Obviously
yes, but I think it's important to understand that these PFI deals
individually are relationships between private sector borrowers
and their banks, where it (the public sector) has a very important
stake because it's paying the bill. Very often the shareholding
in each of these individual deals is different and complex, and
therefore I think the ability for Government to mandate a portfolio
refinancing is actually very difficult.
Q177 Mr Bacon:
I wasn't talking about mandating.
Andy Rose: What
I think we can do, and to take the advice and recommendation of
the NAO, is be more proactive, and that's part of the work we're
Q178 Mr Bacon:
And you could steer large bundles together to meet large bundles
of potential institutional investors. That would then recycle
and enable the banks to free up a whole load of capital.
Andy Rose: And
sell the portfolio of loans on. Absolutely. That is a dialogue
we intend to have. Driving the private sector on how to refinance
and when, in its relationships with its banks, creates enormous
complexities, but the aspiration I absolutely accept and we will
be more proactive.
Q179 Mr Bacon:
Second quick question, which I'm sure Mr Hudson knows the answer
to. The last time I asked this question, the answer was about
£5 billion, I think. What is the total value of the
annual unitary charge payments that are being made in the current
year, for all projects?
Andrew Hudson:
It is estimated at £8.555 billion in 2010-11.
Q180 Mr Bacon:
If you roll that forward by however many years you would need
to for each of the contracts, however long it runs for, what's
the total value in cash terms and in net present value terms?
Andrew Hudson:
This is the exchange you had with my predecessor.
Q181 Mr Bacon:
It is, yes. Actually it was Mr Kingman. We had a long correspondence
about it.
Andrew Hudson:
Mr Kingman and Mr Pocklington.
Q182 Mr Bacon:
He started talking about foreign exchange, for no obvious reason.
Andrew Hudson:
If you simply add up the cash, then, as Mr Lloyd says, you get
to £210 billion.
Q183 Mr Bacon:
Because it's my constituents and my colleagues' constituents who
have to pay the cash, at the end of it.
Andrew Hudson:
Indeed.
Q184 Chair:
Is this for all PFI contracts?
Q185 Mr Bacon:
It's £210 billion. It was £190 billion, so
it's gone up £20 billion.
Andrew Hudson:
Yes, but I think we explained in the note that we sent to you
after that exchange that we thought that the meaningful figure
was the present value.
Q186 Mr Bacon:
This was where Mr Kingman got into foreign exchange. But the
present value figure is?
Andrew Hudson:
The present value figure is £117 billion.
Q187 Mr Bacon:
So that has gone up from £91 billion?
Andrew Hudson:
Yes.
Q188 Mr Bacon:
So the net present value figure has gone up by more than the cash
figure, quite considerably so. £17 billion and £9 billion
is £26 billion more than last time I asked the question.
Finally, the Green Investment Bank, which you've mentioned a
couple of times. I must say, perhaps this is disloyal to my party,
but when I heard that you were going to launch a Green Investment
Bank, my first thought was, "Oh my goodness, how long will
it be before an NAO report is delivered to us about how horribly
it's gone wrong?" Which of the eight common causes of project
failure did they fail to take any notice of? Who is going to
have oversight of it in the Treasury, and will it stay the same
person, and why won't it go wrong?
Andrew Hudson:
It won't go wrong because we will learn the lessons from the common
causes of failure that you refer to, and other inquiries by the
Committee and the NAO.
Q189 Chair:
But you won't be asking for it?
Andrew Hudson:
Within the Treasury, colleagues in Infrastructure UK, with the
market expertise that someone like Andy Rose brings to bear, will
have a role to play. Also other colleagues working on relevant
sectors will be involved, but we will make sure we learn lessons
from
Q190 Mr Bacon:
There will be hires in from the private sector to run it, will
there?
Andrew Hudson:
We certainly want to use the relevant expertise.
Q191 Chair:
Ed, very quickly.
Ed Humpherson:
A point of clarification to Mr Barclay's questions. There are
different regulatory requirements for the assets that can be held
by insurance companies and pension funds. They are set by a European
Union directive called Solvency II, and those institutions tell
us that that does affect the attractiveness of PFI assets for
them to hold.
Q192 Chair:
It does?
Ed Humpherson:
It does indeed affect; it does act as an impediment.
Chair: Right. Well, thank
you very much indeed, and can I just commend you for the way that
you've given evidence this morning. I think it's been really
very helpful: very thorough, straight and to the point, and honest.
Thank you very much indeed; it's been a really good evidence
session.
|