Examination of Witnesses (Questions 22-212)
DEPARTMENT OF TRANSPORT AND HIGHWAYS AGENCY
16 DECEMBER 2010
Q22 Chair: Good morning, everybody.
Thank you very much for returning, Graham Dalton, Martin Capstick
and Ginny Clarke, and our apologies that we had to abandon the
last hearing on this issue.
I just want to ask a question. One of the continuing
themes in this Committee is the failure to get the senior responsible
officer to come and explain his or her actions. In this instance,
it is Ian Scholey. Can you just explain to me why he can't come?
Graham Dalton: Chair, Ian Scholey
was employed at the Highways Agency until the time we closed this
deal. He is not actually in the employment of the agency now.
Q23 Chair: He was still the
responsible officer. We called people
Graham Dalton: And when you called
the last meeting, he was actually overseas on business.
Q24 Chair: And why has he
been unable to come today?
Graham Dalton: I am not sure if
we followed up today.
Q25 Chair: And is it true
that he now works for one of the advisers?
Graham Dalton: He works for Parsons
Brinckerhoff, which was an independent company working for us
as an adviser at the time. He is now working on rail activities
and rail schemes, not on highways.
Q26 Chair: So he has left
this awful project and gone to work for one of the advisers advising
the Department for Transport?
Graham Dalton: He left the Highways
Agency when the project was completed, for career reasons. He
is a professional
Q27 Chair: For what reasons?
Graham Dalton: Career reasons.
And he works for Parsons Brinckerhoff on rail schemes
Chair: I don't know if I would have given
him a job after this one, but never mind. [Laughter.] Go
on.
Graham Dalton: He had the opportunity
to work on large projects and at the Highways Agency had the opportunity
to do this transaction. He came from railways into highways and
he has gone back to work on rail schemes.
Q28 Joseph Johnson: Was he
a manager there?
Graham Dalton: No.
Q29Stephen Barclay: Do most people leave
jobs for career reasons?
Graham Dalton: He's a major projects
professional and wanted to go back into rail on major project
schemes.
Q30 Stephen Barclay: Can I
just clarify something that relates to the Chair's question? Regarding
the firm that he has gone to, during his time as senior responsible
officer how much was paid in professional fees or other fees to
that firm?
Graham Dalton: The implication
is a conflict of interest. We have the numbers in the additional
information that we provided you with.
Stephen Barclay: I wasn't implying anything.
Ginny Clarke: Parsons Brinckerhoff
was an adviser up to a certain period, which was to 2008.
Q31 Mr Bacon: I'm sorry. Can
you be clear? When you say, "which was to 2008", do
you mean "until 2008"?
Ginny Clarke: Sorry. Yes. My apologies.
Until 2008. Parsons Brinckerhoff was employed as an adviser. It
was then taken over by one of the contractors that worked for
the private finance initiative consortium, the joint venture,
and we requestedit was at our instigation that it
was removed from our contract. It was a partner in a JV that was
employed by us. It was removed from that, because we said that
there was a potential conflict of interest. So, from that point
onwards it was not involved with the M25 PFI.
Q32 Chair: From the point
that he entered their employment?
Ginny Clarke: No, no, no. He joined
the company a year and a half later, I think.
Q33 Stephen Barclay: Sorry. Can I
just clarify something? Can you tell us what date he was appointed
SRO on the project and what date he finished as SRO and joined
the company, between those two dates? It was a number really that
I was looking for, whether it is zero or morewhat was paid
by the DFT to that firm?
Ginny Clarke: I was just going
to say that that is listed in the additional information that
was provided after the last hearing.
Stephen Barclay: That is what I am trying
to get to.
Q34 Mr Bacon: What is the
answer to the question? When was he appointed SRO?
Graham Dalton: I believe that
it was at the time that the procurement started.
Q35 Mr Bacon: What date? Give
us a date.
Graham Dalton: It would have been
2005, when the procurement started.
Q36 Mr Bacon: He was appointed
SRO in 2005. Which month? Do you know which month?
Graham Dalton: No, I don't.
Q37 Mr Bacon: It's extraordinary,
because we understand SROs to be the person who is in ultimate
charge of the project. That's why the word "responsible"
is in the title"senior responsible officer".
Yet we have the problem again and again. Departments cannot tell
usthe MOD has the same problemexactly who was the
senior responsible officer, and when. Is there anyone in the Room,
behind you, who knows when that individual was appointed senior
responsible officer in 2005which month?
Ginny Clarke: We can find it out,
clearly.
Chair: Do you know
Q38 Mr Bacon: When did he
stop being senior responsible officer?
Ginny Clarke: I think it was March
2009sorry, June 2009when he left the employment.
Q39 Mr Bacon: So from some
point in 2005 until June 2009, he was the senior responsible officer
of the project.
Ginny Clarke:
Yes.
Q40 Mr Bacon: And during the
period 2005-06 Parsons Brinckerhoff was paid £1,900,000;
in 2006-07 it was paid £2,700,000; in 2007-08 it was paid
just £27,000; and after that it was not paid anything. Is
that right?
Ginny Clarke: In 2008-09 it was
taken over by Balfour Beatty, and was part of the joint venture
that was effectively contracting for the service. That's when
we said, "Actually, you can't be part of the JV that is supporting
us because of the potential conflict of interest."
Q41 Mr Bacon: But hitherto
they were advising you, the DFT.
Ginny Clarke: They were advising
us on design aspects. It was October 2009I have just been
passed a note. That's when Balfour Beatty took over Parsons Brinckerhoff,
and at that point we said that Parsons Brinckherhoff couldn't
work for us any more in the joint venture that was supporting
us rather than supporting the contractor. That's when we asked
for them to be removed from the joint venture.
David Finlay: I just want to clarify
this evidence. Ian Scholey, who was the senior responsible officer,
is working for a firm that was one of the advisers at a particular
point in time, but is now owned by one of the contractors to the
project, so he is within a group of companies that is actually
Balfour Beatty
Chair: Which is still working on the
project.
David Finlay: It is a major shareholder.
Q42 Chair: It owns 40% of
the project. So the senior responsible officer goes off and works
for a consultant, which is then taken over by a company which
is getting 40% of the deal.
Graham Dalton: The SRO was a senior
civil servant and went through Cabinet Office clearance prior
to leaving, and as part of the deal the arrangement was that he
would be working on rail for a consulting engineering firm. After
he left, that consulting engineering firm was bought by Balfour
Beatty.
Q43 Joseph Johnson: Has anyone
checked whether he is working on rail projects?
Graham Dalton: We know that he
is working on rail projects.
Q44 Joseph Johnson: Exclusively?
Graham Dalton: Yes.
Q45 Chair: Why. Because he
is advising you on those, is he?
Graham Dalton: It's not highways.
He went to work on rail.
Q46 Chair:
Is he advising you on those?
Graham Dalton: No.
Q47 Chair: He is not advising
the Department.
Graham Dalton: I can't answer
for the Department, but I think it unlikely.
Q48 Chair: Is he advising
the Department on rail projects?
Martin Capstick: I can check,
but I am not aware of that.
Q49 Chair: Can we have an
urgent note on that? I think we should write to the Cabinet Secretary,
because it is not right.
We have had a week of this, I'm afraid, so you're
coming at the end of a week of really depressingly awful reports
on projects. I asked you last time what you would do differently.
You've had a fortnight to think about it, and perhaps you would
now give us an answer.
Graham Dalton: I think what you
were talking about was what we would do differently on the programme,
and there are three areas that we would look at doing differently.
One is that at the early stage of the procurement, when the project
started in 2004, we did a lengthy consultation with both the construction
markets and financial markets, before going on to confirm the
nature of the procurement and how it would be packaged and go
out. There is a question about whether we could just have taken
a view and put together a procurement without doing the market
consultation.
The second thing we could have looked at was
that, rather than asking the bidders to come back with bids and
then have a finance competition, which would have meant going
to the market for the finance only once, we could have asked bidders
to arrange finance during the bid process. That would have meant
a shorter period post-competition for financing.
A third area we could have looked at and we
picked out in our lessons learned was to look again at whether
to restrict the size of the tenders that come back. There were
something like 30,000 pages in each tender document, and if there
are three tenders, that is a lot of material to be gone through.
That is one of the areas that took us longer than expected.
Each of those first two actions were, in the
view at the time, to take risk out of the procurement and make
it run more smoothly.
Q50 Chair: Let me put to you
a number of things. I am sure that my colleagues will add to them.
Why did this take so long in the first place? You decided in 2000
to do a consultant's report. Who was the consultant, just out
of interest?
Graham Dalton: Kellogg, Brown
and Root.
Q51 Chair: Who?
Graham Dalton: KBRKellogg,
Brown and Rootwas the original consultant.
Q52 Chair: Why did it take
them so long? Three years?
Graham Dalton: It was one of the
multimodal studies that the then Government undertook in 2000-2002.
There were 22 multimodal studies as part of the then Government
taking a fresh look at transport and moving away from just road-building.
That study was done from 2000 to 2002.
Q53 Chair: Why two years?
Graham Dalton: Because it was
a comprehensive study.
Q54 Chair: They were looking
at a whole range of schemes, not just one.
Graham Dalton: They were looking
at a whole range of solutions, not just road. They were looking
far beyond road.
Q55 Chair: So they weren't
just looking at the M25.
Graham Dalton: No, they were looking
at roads, local planning, the need to travel, whether other public
transport solutions could come init was much more than
that.
Q56 Chair: So it was not just
the M25.
Graham Dalton: Let Mr Capstick
from the Department cover a little more of what was done in that
report.
Martin Capstick: If I may help,
paragraph 1.4 of the report gives a bit of a summary. It says
that the report was looking at strategies including better traffic
managementnot just road-buildingand a new approach
to managing incidents and roadworks. It was particularly looking
at alternatives to car travel, the opportunities for public transport,
ways to reduce traffic levels, and working with employers on whether
they could get their staff working flexibly.
Q57 Chair: But it is a study
of the M25.
Martin Capstick: It is about orbital
travel around London, of which the M25 is clearly the focal point.
It was expected that the result would lead to
Q58 Chair: Okay, this is a
study of the M25 and, one assumes, the roads that lead into it,
but I still think that two years is an outrageously long time
to do a report.
Graham Dalton: It was one of 22
reports done at the time. It was a fairly major study.
Q59 Chair: It doesn't matter.
These guys did a report. It took them two years. We will come
back to your use of consultants, but presumably the longer they
spent, the more they got.
Graham Dalton: They were set a
brief on what they had to study.
Q60 Chair: And you paid them
on time spent.
Martin Capstick: Actually, it
was the Government office for the south-east that paid them, not
the Highways Agency.
Q61 Chair: We the taxpayers
paid them for time spent.
Q62 Ian Swales: Was a price
agreed up front for the work? Would it typically be agreed up
front? Did we agree to pay them £2.8 million for that piece
of work? I think that is what the number is. Would we have said,
"Right, we want you to do this work, and it will be £2.8
million," or would that figure have accrued over time? I
am looking at the detailed table of adviser costs that was sent
to us.
Graham Dalton: Kellogg, Brown
and Root: the study was done between 2000 and 2002, it was not
paid by the Highways Agency, we were not part of it
Q63 Chair: It was paid by
the Government.
Graham Dalton: But it is not in
that table of charges.
Q64 Ian Swales: Oh, this is
different work, then.
Q65 Jackie Doyle-Price: What
did they do for the money that is in this table?
Ginny Clarke: This was the subsequent
modelling that was done for the detailed design of the widening
schemes. It was a separate contract. It was a contract with us,
and, if you look at the time frame, it was done later. What they
did was support the design that we did, which went into the contract
and tender documents. They did the detailed traffic modelling
associated with the widening schemes.
Q66 Joseph Johnson: I do not
think the Chair has had an answer to the thrust of her question,
which was whether you had any control over the speed with which
they undertook the work, in the form of the contract that they
were given.
Martin Capstick: This is what
I think would have happenedI don't have the detail. Typically,
for a contract like this, the Government would set out a brief
and identify the key tasks that needed to be done. We would invite
bids for it, and people would bid against that and indicate their
costs. Clearly, over a project of this length, there would be
milestones and payments related to milestones. The task involved
a degree of analysis, consultation, and working with other transport
operators and local authorities, so the timing of the project
would have been agreed as it went along, particularly to allow
time for work to be done and then discussions to be held.
Q67 Joseph Johnson: And did
it conform to the time milestones that you are talking about?
Martin Capstick: I
believe so, but I am afraid that I don't have the records of every
project, to reassure you.
Q68 Joseph Johnson: You
surely know that this is a hearing on the M25 report. Do we not
know whether they kept to their timetable?
Graham Dalton: This was a study
that was done before the project that we're talking about actually
commenced. It was one of 22 multi-modal studies that were going
on right around the country at about that time, and that was a
typical duration, because they had taken their time
Q69 Joseph Johnson: So it's
a reasonable length of time for a report like this, in your view?
Graham Dalton: For that sort of
thingyes.
Q70 Chair: Two years?
Martin Capstick: If it helps,
many of the multi-modal studies were reporting around the same
time, which led to a range of Highways Agency schemes being added
to the road programme round about 2004.
Q71 Chair: I think we would
be interested if you could provide the National Audit Office with
a note about the amount of money being spent on consultants on
your reports and about the basis on which those consultants were
employed. We will come back to consultants because there are a
lot of issues around consultancy. But it sounds like a heck of
a lot of money was spent.
Q72 Stephen Barclay: Could
we include in that note legal fees for all projects, temporary
services and any other consultant costs that fall outside management
costs? I am just minded of the hearing we had with Ofcom, where
it suddenly appeared that there was potentially a general contingency.
There was £30 million, which Richard was looking at in terms
of costs just last year, so it would be quite interesting to get
the breakdown.
Amyas Morse: So we understand
each other, and for clarity, I am happy that we do that, but we
are asking about projects that we'll need the Department to supply
information on, not the Highways Agency, primarily. These were
projects let by the Department. I am not saying that's wrong;
I'm just making sure we understand each other.
Q73 Chair: It doesn't matter
if they'd managed to get another agency to pay for the consultants.
We need to know, because it is still taxpayers' money.
Amyas Morse: Okay. Absolutely.
We understand that.
Q74 Chair: In terms of lessons
learned, one of the things I find most shocking is that you based
the value for money of going down the PFI route on what is, at
best, flawed data; at worst, this is almost an issue of maladministration,
in terms of using out-of-date calculations and not challenging
the maintenance cost. Perhaps you can turn to pages 16 and 17
and figure 3. How do you justify that?
Graham Dalton: Are you talking
about paragraph 1.19?
Chair: Yes.
Graham Dalton: First, you have
to use the data that are available. If contracts hadn't been used
or let, there was no data coming from them.
Chair: I'm really sorry, but I can't
hear what you're saying because of the acoustics in the room.
Graham Dalton: First, you have
to deal with the data available from real contracts. We had data
available from previous widening schemes. Paragraph 1.19 talks
about data from 1992-94. The schemes that were done after that
were design, build, finance, operate schemesPFI contracts.
They were not directly comparable, because we didn't have the
disaggregation of costs from those early PFI contracts.
Q75 Chair: You were using
data that were 13 years out of date?
Graham Dalton: From contracts
from 1992-94, three of which were M25 widening schemes, so they
were highly comparable. There are published indices that can be
used right through construction, which actually track how construction
cost prices have tracked over time. Those are the estimates we
used to build the widening estimates. Indeed, once the bids were
in, our estimate of the cost of the widening was pretty close
to where the bid cost came in for widening.
As to the estimates and figures we then used
for operations and maintenance, when we first started, we had
the reference. Unlike with a new-build PFI, if you're going to
build a facility and then operate it, and it hasn't been there,
you haven't got a direct comparison. We had already been maintaining
and renewing parts of the M25 for a number of years, so we had
a term maintenance contract in placewe called it our area
5 contractand we knew what it actually cost. That was our
reference point for bids. Then we had to make an estimate of how
much better than that, or how much more efficient, a PFI contractor
would be on maintenance.
Q76 Chair: It is quite astounding
to read in this report that your costs were between 27%, 40% or
80% higher than all the bids. They were completely out of kilter.
Either you were spending far too much on your previous contracts,
or your estimates were wrong. For your estimates to be so wrong,
relative to the bids, something must have been deeply wrong. Can't
you accept that?
Graham Dalton: Our estimates and
the bids as they came in were about the same: about £1 billion,
for the widening of those first two sections. We did a public
sector comparatorit wasn't an estimate beforehandfirst
to judge whether to follow the PFI route, and that is when we
made the estimate of what efficiencies would come through that
procurement route. We followed that through and then did what
was effectively a shadow bid, using tender assessment, and it
estimated higher than the bids that actually came in.
Q77 Joseph Johnson: On the
maintenance costs?
Graham Dalton: On the operation
and maintenance costs.
Q78 Chair: That was 65% of
the PFI contract. I understand the basis on which you did it,
but it was so out. What went wrong? It was not just a bit out;
it was enormously out.
Graham Dalton: We have not bid
one like this. This was down to how competitive the bidders would
be.
Chair: Someone showed a complete lack
of understanding of both the market and the real costs of doing
this maintenance, which is two thirds of the cost of the PFI.
Q79 Joseph Johnson: Presumably,
it was the people who were advising the Highways Agency.
Q80 Stephen Barclay: Paragraph
14 of the NAO's report states, "We are concerned about the
credibility of the comparison because the Agency had not taken
up the earlier opportunity to investigate the difference between
the bids and its benchmark cost model. Consequently, the updated
comparator, in our opinion, was not a sufficiently robust guide
to likely costs under a conventional procurement." That is
the NAO's finding.
Graham Dalton: That is the NAO's
opinion.
Chair: But the reports are agreed by
you.
Amyas Morse: Perhaps it would
be fair if I pointed out that the subject of the Highways Agency's
understanding of the costs of maintenance isn't a new one. We
have had a hearing on this even in the time I have been in this
job. The NAO report on the subject states, "The Agency is
only now beginning to exploit the good visibility of costs within
these contracts, so that it can challenge contractors' costings
and establish benchmarks for continuous improvement."
Quite honestly, although that report found that
you were starting to do that, we didn't find that you had mastery
over the costs environment on maintenance. I think that that is
a fair summary on where we got to in the hearing. This is not
something that we thought up when we were writing this report,
as we had a long discussion and a hearing on highways maintenance
and produced a report on it, and I recollect that I was sitting
in the same seat.
Q81 Joseph
Johnson: Was it Parsons Brinckerhoff that encouraged the Highways
Agency to have this inflated view of what it would cost?
Graham Dalton: The shadow bid
model, which is the one you are referring tothe numbers
are in figure 6was actually put together by PricewaterhouseCoopers
as part of the cost model.
Q82 Mr Bacon: Isn't it amazing
that you spend all this money on consultants£80 million
all togetherand still get it so badly wrong? What does
that say about your ability to buy advice?
Graham Dalton: Can I just point
out that we did have the maintenance report before? In the two
and a half years that I have been in the agency, we have done
quite a lot of work to improve the commercial management and estimating
capability. Before, maintenance was actually on the major projects
as well. The difference with this one is that we go out routinely.
In 2008, we let three maintenance contracts, which are typically
for five to seven-year terms. We have much better data about what
those costs will be when we go and do the job.
Q83 Chair: Do they all come
in below your estimated costs?
Graham Dalton: The winning bids
on two of the three, if I recall, were below by a small margin,
and our estimate was typically around the second bid levelso
a spread of bids around our estimate. The difference between this
and the maintenance contracts that we've bid more routinely is
that this is asking contractors to take a view over 30 years of
what it's going to cost them to either maintain or renew the asset
and the structures. Routinely, we just take a four or five-year
look ahead, or get rates for the type of work, however much of
that work comes up.
Q84 Ian Swales: So was that
a bad decision, to decide to do that, then? To go over 30 years?
Graham Dalton: This is the nub
of what this contract is really about. The widening is an important
part of improving the service to road users, but we are effectively
pre-buying maintenance and transferring the renewals of asset
risk on to the contracting consortium. The competition that we
got, where we got two very tight bids, two very close bids, was
an ambitious view on what they could do to operate and, really,
their view on when they were going to have to renew assets, or
the amount of work they'd have to do over that time. That's where
the real competition comes in.
Q85 Mrs McGuire: How did you
judge whether or not they were taking a pessimistic view of what
needed to be carried out over a 30-year contract, which would
inflate the cost of the maintenance, or an optimistic view? How
did you benchmark their analysis?
Graham Dalton: Ginny Clarke
was the chief highways engineer. I'll ask her to give the detail.
Ginny Clarke: We gave them an
indication of what maintenance we would expect in the normal five-year
cycle, and part of the tender they returned to us was their indication
of how they would renew the asset over that 30-year period. So
against the overall cost of operation maintenance they then told
us an indicative basis on which they would renew the asset and
maintain it. So we were able to make a judgmentwhether
they were actually underestimating, for instance, the sustainability
of the road pavement, and when they would renew that. So that
was part of the assessment of the tender and of the robustness
of those bids.
Q86 Mrs McGuire: And they
would build in a 30-year projection on construction inflation
costs and so on into that?
Ginny Clarke: No. Effectively
the cost model gave them high-level figures. What we asked them
to do was understand the techniques they were going to use, rather
than the cost of thosebecause the cost is the total cost;
what we wanted to understand was what sort of work would they
be doing. Would it be similar to the sort of things we might project
over that period of time?
Q87 Mrs McGuire: Why did you
go for the 30 years, which
obviously you had little experience of, as against
your normal projection of five or even 10 years? Thirty years,
in terms of coming up with a figure for a highway, just strikes
me as a little lengthy. I can understand it in terms of a building
or something, but I don't quite understand why you would want
to do it 30 years.
Ginny Clarke: Actually we had
done our previous design, build finance and operate schemes on
30 years.
Q88 Mrs McGuire: So you weren't
new at this game.
Ginny Clarke: No. They are now
10 or 12 years old, now, the first ones, so we have some understanding
about how, over the period of time, the DBFO actually enacts those
plans. Rather than the theory of it, what do they actually do
in practice? That's the basis on which we did, again, a 30 year.
It's also in relation to the financial model
Q89 Chair: But you got it
horribly wrong. So what have you learned? You got it wrong.
You know you were out by between, whatever it isI've lost
the figures now27% to 43%. Or 48%? I cannot read my own
writing. You got it horribly, horribly wrong.
I'll tell you what it just makes me think.
If any contractor came in, they came in lower. We haven't a clue
whether at their lower price actually we're getting value for
money.
Graham Dalton: Well you could
look at it the other way and say that's actually the power of
the competition and three strong bids coming in
Q90 Chair: No, because we
can have no confidence in your advice or your advisers' advice
as to what is a real value-for-money figure for maintaining this
bit of the M25 for 30 years. We just haven't got a clueand
no confidence, given your track record in failing to understand
the real cost of it.
Graham Dalton: Well, the estimates
came in very competitively. I think it's a good thing that they
came in competitively. The thing we had to do is to really make
sure that the assumptions that have been made in those bids and
those tenders were actually bids that the contractor was going
to be able to live with.
Q91 Chair: That's not your
job; that's their job. That's the whole point.
Graham Dalton: Well, it is until
it goes wrong. We need to ensure that we will not have a contractor
that cannot live with
Chair: I don't think you understand our
point.
David Finlay: I think that the
evidence, as set out, is that the PFI costs for operation and
maintenance over 30 years came in much lower than the agency's
estimates, which were based on short-term conventional contracts.
That raises two issues. First, why wasn't there a better estimate
of what the PFI cost would be in advance of the bids coming in?
Secondly, there are question marks over why you couldn't get better
deals on conventional procurement for operation and maintenance
over a long period.
Q92 Chair: Do you want to
respond to that?
Graham Dalton: Sorry, I missed
the last point.
David Finlay: The second point
is that it raises question marks about whether you couldn't get
better deals on operation and maintenance under conventional procurement
over a long period.
Amyas Morse: You mean if
you were offering the conventional maintenance over 30 years.
Presumably, people would give you a pretty sharp pencil for estimating
that for that length of time.
Graham Dalton: That's a fair
question. If we have enough knowledge of the asset, the question
is the viability of the contract. Some 15% of the motorway strategic
road network is now under PFI, so we have a number of those contracts
running. This is by far the most competitive that we have had.
Q93 Joseph Johnson: Can I
dig into the comparison between the estimates of the present value
of the cost of the contract versus the present value of the expected
benefits of the contract? When you started the bidding process,
what were the two figures?
Graham Dalton: Are we talking
about the widening?
Q94 Joseph Johnson: Everything,
the whole thingconstruction and maintenance, cost versus
benefit, at the start and then at the outcome.
Graham Dalton: Figure 5 gives
us the table at the outset, which is the anticipated benefit-cost
ratio initially.
Ginny Clarke: Figure 6 is the
tender stage, and it looks at the costs and present value costs.
Those were at the tender stage. Against it, we have the unadjusted
standard tender.
Q95 Joseph Johnson: The reason
why I am struggling is that in paragraph 12 of the report, we
appear to be saying that the present value of the cost increased
from £2.7 billion in May 2008 to £3.4 billion in May
2009, when the contract was awarded, versus what appears to be
the expected benefit of £2.3 billion, which is mentioned
in paragraph 7. Can you help me to understand that? On the face
of it, it would appear that from the outset that the expected
benefits were lower than the expected costsif those two
figures are comparable. If they are not comparable, can you tell
me why they are not?
Graham Dalton: The net present
cost of the contract is for the widening and for the maintenance
and renewal of the asset over 30 years. When we work out the benefit-cost
ratio, paragraph 3 might be useful. It states that the capital
cost for the widening is £900 million and that it delivers
£2.3 billion present value of benefits. That is the extra
benefits bought by the widening.
Q96 Joseph Johnson: Why can't
I have a figure that is directly comparable to the £2.7 billion
and the £3.4 billion? Where is that directly comparable figure?
Graham Dalton: I don't think there
was a benefit-cost ratio calculated at either stage.
Q97 Joseph Johnson: Why?
Graham Dalton: There was for the
widening, because that is the benefits that you buy. For the maintenance
and renewal, that is keeping a network in a steady state, so I
don't believe that you do a benefits calculation for how much
you are spending. You can compare the price and get the lowest
net present cost.
Q98 Joseph Johnson: Would
you never undertake a benefit analysis of a maintenance contract?
Graham Dalton: Because you are
not buying new benefits.
Q99 Joseph Johnson: So you
would never attempt to establish that. How would you measure value
for money?
Graham Dalton: We look for the
lowest net present cost. If it's for normal maintenance, then
yes, the lowest cost-compliant bid. For this one, it's the lowest
net present cost for undertaking maintenance and renewals.
Q100 Chair: That is a deeply
disturbing statement to have made. We know that your ability to
assess the costs of maintenance is, at best, flawed, because you
have got them so wrong. We have no clue whether the figure you
have ended up with actually reflects best value. All it reflects
is lowest price, not best value. You do no workand neither
do your consultants, from my understanding of your answer to Mr
Johnsonto assess whether those figures represent best value
rather than lowest price.
Graham Dalton: We know what we
are getting; there is a specification for maintenance and condition
of the asset.
Q101 Chair: You don't know
whether you are getting best value.
Graham Dalton: We know what we
are getting, so there is no doubt about what we are getting. We
know the cost of maintaining and renewing, as has been, through
conventional procurement, and we are doing that across the network.
The bids came in much lowerI agree they came in a lot lower
than our estimate. It is always difficult to second-guess what
bidders in a tender situation will do to price. That fact that
we have two very close bids is quite informative.
Amyas Morse: I want to ask you
to help to clarify this, as it is an important point. If you calculated
the costs in exactly the same way that the bidders did, and they
simply decided to drive down their margins or do something else
that you had not assumed, just to get the business, within certain
limits that would be acceptable and a positive effect of competition.
What you need to know is whether that is all that they are doing.
For such a large difference, it is surprising if that would be
all that was at play. Normally, in a situation such as this and
you do a shadow bidwhich I agree was the right professional
thing to do, to calculate thatyou would expect that to
be pretty skinny. You would use it to push the bidder, wouldn't
you, to say, "Don't bother producing something. I'm expecting
you to take all this into account."
The difficulty is that, because there is such
a big gap between the two, it is hard to believe that comes simply
from competition. Looking at the way that they have costed it,
you are left asking whether you have got best value, because it
has been in such a different way and there has been such a big
disparity. It must be hard for you to determine that. Is that
fair comment? I am not trying to say this in a combative way,
but from a commercial point of view.
Ginny Clarke: Can I go back to
the point that we are talking about? That is assessing the case
for a maintenance operation over 30 years, rather than five to
seven years? We were comparing it with effectively extending our
presumption about what you would maintain between the five and
the 30-year period. That is over a time scale that in our traditional
maintenance claims we don't do. We do it over a five-to-seven-year
period.
You are right to say that the tenderers were
looking at different ways in which they would invest money over
30 years and the rate at which they would renew, as distinct from
our making that decision about renewing over a five-year period.
That is where the differences lie. If you looked at the tenderers,
that is where some of the differences were. Would they go and
do maintenance on their bridges on a seven-year cycle or a 14-year
cycle?
Effectively, they took the risks about those
different decisions. The price of their offer is directly related
in the maintenance field to their assessing the risk against things
such as the life of the road, pavement, the structures, and how
the much the cycle of investment will change from the ones that
we do. Our estimates are based on our best presumption about how
we would do it. Theirstaking both the financial risk and
the quality riskare about how they would measure it. The
benefit side of that isn't assessed in the way in which widening
benefits are. It's about renewalat what stage you would
renew an asset, looking at its life. You chase the curve to some
extent, and how much you let an asset deteriorate before you start
to put money in.
Q102 Chair: They were so consistent
in their bids, and you were so wrong. Did PWC advise you on this?
Ginny Clarke: On the financial
model, yes.
Q103 Chair: What's your view
on the advice you had internally and the advice you got from your
consultants? They were so consistent; you were so wrong. It wasn't
just one tender that came in that took a different view; they
all did. What do you learn from that?
Graham Dalton: The blindingly
obvious question for us is about how we take the techniques that
Connect Plus now uses to live within that budget. We take those
into our conventionally managed maintenance for the other 85%
of the network. Apart from the practicalities of what they are
doing on the ground, they show us a lot about how the business
works and how they are running it, so that we can make sure they're
performing. We'll copy with pride. I am quite happy to take ideas,
if they've got some good ideas about
Q104 Chair: Are you still
using PWC to advise you on this?
Graham Dalton: PWC's contractis
it nearly finished?
Ginny Clarke: Its contract is
on a framework for general legal advice to DBFO, so we use it
for advice on other things. We are just about to retender that
contract.
Q105 Chair: Do you have confidence
in it?
Ginny Clarke: Yes; in terms of
the financial modelling, very much so.
Chair: It was the financial modelling
that was so bloody wrong!
Amyas Morse: The question is,
does PWC prepare the model on your instructions? In other words,
do you give it the data and it cranks out the model?
Ginny Clarke: Yes.
Amyas Morse: So it's actually
your responsibility for what is in the model.
Ginny Clarke: It was our view
about that cycle of maintenance, renewal and replacement. That
was our view. What PWC did was to help us to understand how, in
a 30-year investment profile, you would put the money against
it.
Q106 Chair: And is that "our"
Ian Scholey?
Ginny Clarke: Ian was the SRO,
but it was my side of the organisation that advised on the techniques
for maintenance and the specifications for that. That is around
the technical specifications that my part of the organisation
dealt with.
Q107 Stephen Barclay: It is
a small point, but you have said that PWC also provides legal
advice. Is that the case?
Ginny Clarke: No, it's Denton
Wilde Sapte.
Q108 Chair: Because you tried
to put this in the market at the time of the credit crunch, you
ended up with an extra £660 million cost and an extra £68
million of risk being borne by the Agency. Have we got a value-for-money
contract?
Graham Dalton: I believe so. While
going through the funding competition in that final year from
preferred bidder to the contract being awarded, we could clearly
see the increase in the cost of finance. That is why, right through
that phase, we prepared and refreshed the cost estimate that we
had by conventional means, which is where the graph in figure
8
Q109 Chair: So £3.4 billion
is a value-for-money contract, although it's £660 million
more than you thought? What is the basis for that? I don't get
it.
Graham Dalton: We prepared a range
of estimates. On the widening costs, our estimates had been close
to the bidders, so we took those as fixed. We looked at a range
for the operation and maintenance costs, again based on what the
Agency was buying and procuring.
Chair: I don't think you're answering
the question.
Q110 Joseph Johnson: You were
previously saying that you had done no estimate of the potential
present value of the maintenance. You just said that you looked
at the lowest bid, so I don't see how you can compute it as being
part of a calculation for value for money.
Graham Dalton: I said that we
didn't do a benefits calculation. Appraisal doesn't have a benefits
calculation.
Q111 Joseph Johnson: But that
was because you didn't value the maintenance.
Graham Dalton: Right the way through,
we estimated what the net present cost of maintenance would be,
which is what we have just been discussing. We took a range, if
the Agency were to do it itself, based on optimistic, most likely
and pessimistic, built up from our experience in the market. That
gave us a range from £3.4 billion to £4.2 billion, which
the NAO has analysed. Our view at the time of the contract award
was that while the cost of financing had increased, it had taken
that level to the very best that we could achieve by going through
a conventional approach. The 30-year contract gave us the opportunity
to lock off at that price, rather than retaining the risk, so
we deduced that it was a value-for-money decision.
Q112 Joseph Johnson: Just
in case I'm being rather dim, does that mean to say the Department
estimated that it would cost it, to do the maintenance and operations,
more than £1.4 billionthe difference between £3.7
billion and the £2.3 billion estimated present value of the
benefits of the construction?
Graham Dalton: Yes. As agents
we estimated that it would cost us more, and we estimated the
net present cost at a mid-point of £3.8 billion for operations,
maintenance, renewals and widening. The £3.4 billion was
compared to
Q113 Mr Bacon: While you are
talking about net present value of the cost of maintenance, can
you turn to page 30, figure 10? The chart describes the Highways
Agency's attempt to answer a question from the Secretary of State
as to whether it was still worth while to proceed with the widening,
or whether it would be better to do hard shoulder running. What
it basically says is that, on the top half, there were a series
of potential savings from not going ahead with the widening, but
then there were further assumptions in the bottom half of further
possible costs, which could offset those savings. At the top
you've got a saving of £330 million, but then you've got
all these additional costs that have been put in, so that the
net saving is only £87 million. The biggest, by far, of
those additional costs is the maintenance cost over 30 years.
That £193 million is spread over 30 years isn't it?
Graham Dalton: Yes.
Q114 Mr Bacon: So why is that
not a net present value figure? It should be, shouldn't it?
Graham Dalton: I thought it was,
actually.
Ginny Clarke: The figures that
you have quoted are costs.
Q115 Mr Bacon: It's the cost
over 30 years, so if you're trying to work out the value of the
savings, versus the value of the additional costs, the number
that should go in there should be a net present value figure,
shouldn't it?
Graham Dalton: I haven't got the
reference here. I would expect it to be a net present value figure.
Q116 Mr Bacon: But it's not.
We've been told by the National Audit Office that it is not a
net present value figure.
Ed Humpherson: It is at paragraph
3.4, the first bullet, which reads: "The Agency offset maintenance
costs over 30 years against upfront savings, without carrying
out a discounted cash flow. This overstated the offsetting costs."
Q117 Mr Bacon: Thank you.
You've just been talking, in your answers, earlier,
to Mr Johnson, about the way you've calculated these things, and
the importance of assessing the net present value of the maintenance
costs over a period of time; but you didn't do it here.
Graham Dalton: Figure 10 is about
looking at an alternative solution to widening.
Q118 Mr Bacon: Yes, but you're
trying to look at the cost and the value now spread out over 30
years into the futurearen't you? So you should have put
in a net present value cost, and the effect of not doing that,
as Mr Humpherson has just said, quoting paragraph 3.4, is to overstate
the offsetting costs.
Amyas Morse: We would roughly
say, Mr Bacon, very crudely, if you had discounted that number
it would certainly be reduced by half, depending on what you choose
to assume. Taking any reasonable rate of discounting, you know
Ginny Clarke: Probably more.
Amyas Morse: Probably morethank
you.
Q119 Mr Bacon: In other words,
that figure at the bottom, where it gives the net additional cost
of using active traffic managementthat's the hard shoulder
runningand shows that it was £53 million more expensive
to do widening than to do hard shoulder running, is just pie in
the sky, isn't it? It's wrong. This chart basically says you've
got £87 million of net savings, but you've also got further
costs down at the bottom of £140 million. The difference
between the two£140 million minus £87 millionis
£53 million. In other words, what it is saying is that it
is £53 million more expensive to do the hard shoulder running
than it is to do the widening. That is correct, isn't it? That's
what it is saying.
Graham Dalton: That is what it
is saying.
Q120 Mr Bacon: Good. Okay,
we are on the same ground.
Now, intuitively it is bonkers to think that
it would be more expensive to do hard shoulder running than to
do widening, when there is an absolutely huge slug of capital
cost in doing the widening that is higher than the capital cost
of doing hard shoulder running, and in either case you will have
to do maintenance. So, intuitively it is bonkers. This is just
manipulating the numbers to give you the answer that you wanted
anyway, isn't it?
Graham Dalton: This was an assessment,
at that stage, of stopping the competition and procuring hard
shoulder running, which would have given us fewer benefits and
a different outcome.
Q121 Chair: Have you got confidence
in this assessment?
Graham Dalton: I agree that the
figure of £193 million should be a net present.
Q122 Mr Bacon: The whole point
is that, if it were, it would beit is difficult to say
exactlysignificantly lower. Gosh, it might even be £53
million lower and you would have, at best, nought at the bottom,
or you would have it going the other way. In other words, this
chart was designed to give you the answer you wanted, wasn't it?
Graham Dalton: This chartit's
quite righthas an error.
Q123 Mr Bacon: Did you just
say, "quite right"?
Graham Dalton: It was not designed
just to give the answer that we wanted. There is an error in the
chart about the figures at the time, which the NAO has pointed
out, and that is right.
Mr Bacon: But the error is so significant
that it completely alters things. You've got £330 million
in capital costs and you say, "We'll bung in all the maintenance
costs spread over 30 years, we'll stick in £193 million therethat
is a nice big chunk off £330 million", and lo, you suddenly
find it is more expensive to do the smaller project than to do
the bigger project. It doesn't make any sense.
Q124 Joseph Johnson: It is
the other way round. You would have produced the negative number,
which would have meant that the forecast saving would have been
greater. Either way, it's a bogus table, because they're not using
net present added figures, but it doesn't mean that it was boosting
its own case, I don't think, because the number was in the wrong
directionit has a negative sign on it.
Ginny Clarke: That is what I was
going to point out. Some of these are negative signs, so they
work in the opposite direction.
The figure at the end is not a summation of
widening against hard shoulder. It is about the costs at the time
in 2008
Q125 Mr Bacon: It is the net
additional costs of doing hard shoulder running.
Ginny Clarke: No. It is not just
the net additional costs. It is the whole cost
Mr Bacon: That is what it says.
Ginny Clarke: It's the whole cost
to the Government of stopping the procurement at that stage, because
it took into account the advice that said, "If you change
to hard shoulder running, you'll have to stop the procurement
and start again." So it included those costs as well. That
was the only point that I was going to make. It is, in that sense,
trying to look at the whole picture of costs, not just the narrow
aspect of the comparison of hard shoulder running versus widening,
where quite clearly we had said, "You can deliver hard shoulder
running or widening on the same stretch of road for up to 40%
cheaper".
Q126 Chair: So have you got
confidence in this table?
Ginny Clarke: Yes, I have.
Q127 Chair: I will tell you
the other figure that absolutely astounded me was the presumption
that if you stopped this suddenly everybody else would charge
you morethe £90 million and the £50 million.
You believed that at that time, in the middle of the credit crunch,
when absolutely everybody was absolutely desperate for construction
work, they would shove up their charges. It just seems unrealistic
to me.
Ginny Clarke: But that was the
view taken about how the market would respond.
Q128 Chair: Your view.
Ginny Clarke: The Department's
view, with our financial advisers.
Q129 Chair: Who?
Ginny Clarke: The Department's
corporate finance team took that view, because it had a view across
lots of projects.
Q130 Chair: Which advisers
on this one?
Graham Dalton: That was the corporate
finance specialist employed as a member of staff within the Department
for Transport.
Q131 Chair: Which adviser?
Ginny Clarke: No, no, nothey're
members of the Department for Transport.
Q132 Chair: Well, I can't
think that anybody else in the middle of a credit crunch would
have thought that construction costs would go up if you dumped
one of the projects. The whole construction industry was absolutely
desperate for work.
Ginny Clarke: Just in time terms,
this was March 2008. So it wasn't at the height of the credit
crunch. Just as a point of information, this table was submitted
through the project to the Department and Ministers in March 2008.
I was just making the point that that is when those figures were
produced. The figures were then adjusted as we got further in
and subsequently led to another set of figures, which the NAO
looked at, at the time when we were going to award and when we
were clearly in the height of the financial crisis.
Q133 Mrs McGuire: What evidence
did they have to make that calculation? Was it just a hunch, was
it just plucked out of the air that one of the largest procurers
of this kind of work would suddenly find themselves at the end
of a financial cosh if they changed tack?
Ginny Clarke: I didn't do the
actual bit of work, but I understand, because I was there at the
time and I was involved with this, that they looked at other PFI
contracts across Governmentyou're right that this wasn't
just within the Department, but across Governmentand at
the view of the risks of pursuing all those other PFIs. That was
what that was trying to do in terms of the impact for us.
Q134 Chair: I accept that
that was March 2008. By September 2008, if I've got my chronology
correct, the table would have changed. Why did you not then review
whether you should do a PFI?
Ginny Clarke: We did review when
we got to the next stage, which was a little later than that.
That was when we had gone through the assessment and we were getting
to the stage of contract awards.
Q135 Chair: Why did you do
it?
Ginny Clarke: Effectively, that's
when we reassessed all these numbers. In fact, higher costs were
put in at that stage
Q136 Chair: Was it still value
for money then? If we looked at figure 10, with all the provisos
that we have around it, redone in, I don't know
Ginny Clarke: 2009, it was. The
contract
Q137 Chair: When?
Ginny Clarke: The decision about
whether to award the contract, which was May
Chair: A year later.
Ginny Clarke: That was when it
was reassessed.
Q138 Chair: Was it still value
for money?
Ginny Clarke: It was still value
for money.
Graham Dalton: These figures are
comparing two different things. Figure 10 is talking about what
if we went forthis was as yet unprovenhard shoulder
running instead of widening.
Chair: It wasn't unproven, but we'll
come back to that.
Q139 Mr Bacon: You've got
a huge number in there that distorts the amount of saving that
you make. You've got a figure that's far higher than it should
be and that intrudes on your £330 million saving and makes
it much smaller than it would otherwise be. In fact, the number
that's doing the intruding on the £330 million should be
much smallerthat was my point. I take Ginny Clarke's point
about what the number at the bottom for the net additional cost
covers, but, regardless, it would have been much, much, much smaller
and might not even have been a net additional cost at all; it
might have been a net, net, net additional savingthat was
my point.
Graham Dalton: I accept your point.
If you just take the top half of the table, the £87 million
may have come down to a lower figure.
Q140 Mr Bacon: No, no. It
would have been a much higher figure. You wouldn't have been lopping
£193 million off your £330 million. At the bottom, you'd
have had a net, net, net additional saving.
Graham Dalton: The minus £53
million may have got closer to zero.
Q141 Mr Bacon: It would have
got above zero, almost certainly.
Graham Dalton: I don't know which
side of zero it would have got. The other important thing we were
doing was assessing the different benefits.
Q142 Joseph Johnson: Can we
just clarify that point? Ms Clarke has said that the figure would
fall by more than half on a net present value basis. If someone's
got to calculate it, we can do it easily. Let's say for the sake
of argument, that the £193 million becomes £80 million
or £90 millionlet's take half.
Mr Bacon: I will just give you an example.
The cash cost of all PFI contracts in the United Kingdom is £210
billion, and the net present value of that is in the region of
£117 billionthe Treasury give us evidence on this
recently. When the cash cost was £191 billion, the net present
value was around £91 billion, so there is a big chunk you
have to lop off. You're probably right that it is at least half,
if not more than half.
Joseph Johnson: If, as you say, it was
half, that minus £53 million becomes plus £40 million.
Mr Bacon: That's quite reasonable, isn't
it? If you knock £100 million or so off the £193 million,
you're going well the other way; you're suddenly into a net saving,
aren't you?
Graham Dalton: That is to buy
a different solution.
Mr Bacon: But you might have considered
buying a different solution if the numbers had been accurate.
Chair: You're advice to the then Secretary
of State, one would hope, would have been different.
Amyas Morse: I know you weren't
there at the time, but it is worth just commenting on this for
the Committee. As I look at all these numbers, the hard number
in this list is £330 million. Then there are increasingly
a lot of non-hard numbersestimation, broad-judgment numbers.
If you look at the note on the right of the minus £90 million,
it says, "The Agency assumed"assumed"that
cancellation of the M25 widening contract would lead to market
uncertainty and an assumed increase in financing". These
are best estimates. You can't really describe these as more than
finger-in-the-air numbers. Is that fair? I am not saying that
they are not relevant at alldo speak up if anyone has anything
to say by the waybut what they are essentially saying is,
"We think there is an effect here and we need to find some
way of expressing what that effect might be. Here is a broad way
of estimating it." You could explain the calculation, but
you couldn't regard it as provable, could you? Is that a fair
comment?
Ginny Clarke: Some of the numbers
are very hard. On the £330 million, we have evidence and
we have talked about that. You are absolutely right: some of the
others are about people's judgment and people making the point,
as the Chair said, about the view of what the market would do
in response to a cancellation of one of the biggest PFIs. I accept
that that is a judgment. You are right: it is a mixture of the
two.
Q143 Stephen Barclay: The
£140 million of additional cost to other projects is questionable
as well.
Ginny Clarke: Yes. That is where,
potentially, there is more a judgment than
Q144 Chair: So, did you follow
the PFI route because you were told to by the Treasury?
Ginny Clarke: No. Are you talking
about the original decision?
Q145 Chair: This one. Our
view, as you can quite clearly see, is that this was a lousy contract.
It became even more lousy when the credit crunch hit. So why on
earth did you enter into it? Why on earth did you give advice
to the then Secretary of State that this was a sensible thing
to do? I am almost giving you a let-out clause here: did you go
down this route because the Treasury instructed you to?
Mr Bacon: You are nodding.
Ginny Clarke: No. I said no.
Mr Bacon: I just wanted to be clear.
Q146 Jackie Doyle-Price: What
assessment did you make? When the Treasury came to talk to us
about PFI deals, one of the things that it told us was that the
Department had made money available in the event that a PFI deal
was not forthcoming. Obviously, given the market situation at
the time, that was a very real concern. So what judgments did
you make to decide that PFI was the appropriate funding vehicle
on this occasion?
Graham Dalton: The Department
made money available to co-fund if the funding competition was
not fully subscribed. That was effectively to say to the market,
"We are serious about going ahead with this," and to
effectively break a stand-off to see whether anyone was going
to go into it. That was what that money was for. That money was
not offered up to say, "Let's do it in a conventional way
instead." The assessment about the value for money was made
right back in 2005 when the procurement route was selected, and
the test was, as figure 8 shows, immediately before contract signature.
Q147 Jackie Doyle-Price: In
terms of the additional cost that the delay caused to the PFI
contract, which was £660 million, what are the long-term
consequences of that for the Department's ability to deliver other
projects?
Graham Dalton: Figure 8 tells
usthe additional cost is the blue on the graphthat,
on the cost of paying for the widening and operating and maintaining,
we believe, at the very best, we could have got the same through
conventional procurement.
Q148 Chair: But your basis
for calculation was so way out that I do not have any confidence
in your calculation. That is the problem. Because you were so
way out on the figures, and the way in which you assessed costs
was so wrong, particularly for maintenance, what confidence can
we have?
Graham Dalton: Our incorrect estimate
was on the basis of what a PFI contractor was going to give. We
repeatedly come close on estimates for our maintenance contracts
as we let them on the five and seven-year terms.
Q149 Mrs McGuire: May I ask,
given the exchange we have just had, whether you accept or not
the NAO's comments in paragraph 3.10 on page 31 that the figures
in figure 10 were not a "sufficiently thorough assessment
of the savings"? We need to have a sense of whether or not
you accept that assessment of this analysis? There is a great
deal of concern around the table that these figures, by any objective
standard, don't stack up. It may be a judgment, Ms Clarke, but,
robustly, they do not pass muster.
Ginny Clarke: My view is that,
at the time we were doing this in 2008, it felt very real and
it felt, based on the evidence that we had, that that was effectively
Mrs McGuire: Can you move us on from
2008 to today? Given the exchanges that we have just had, do you
or do you not accept the NAO's comment in paragraph 3.10 on page
31 that this was not a sufficiently robust set of figures on which
to make an analysis?
Ginny Clarke: I believed that
it was robust at the time, and what we haven't looked at here
is the benefits side, at what this was buying. The presentation,
in informing others and recommending it, was not just about the
cost but about what it was buying. That's the other side of the
equation.
Q150 Mrs McGuire: Can I put it another
way, then? Although this Committee gets the reputation for being
a bit of an attack-dog Committee, it also wants to encourage Departments
to learn lessons.
Ginny Clarke: I accept that.
Q151 Mrs McGuire: Right. So,
has the Department, or have you as officials, taken a lesson from
this, that advancing a cause on this set of figures does not stack
up in terms of the scrutiny that the Public Accounts Committee,
or indeed any objective analysis, would make of those figures?
Ginny Clarke: The answer to that
is, "Yes, we've learnt lessons."
Q152 Mrs McGuire: In other
words, would you do it differently?
Ginny Clarke: I think that we
have. When we've done a lessons learnt on the whole procurement,
there clearly are things that we would do differently. We've learnt
every time we've done a PFIso I do accept thatand
I think that we could do it better. In all these areas, we're
seeking to be more and more robust because of these challenges
to recognise how we provide the evidence.
Q153 Mrs McGuire: So, will
you now go back to your corporate finance people and say, "We
got a grilling today on these figures that you gave us, and on
the advice that you gave us that the market would somehow make
life difficult for us, and you need to look at how you make your
market assessments"?
Graham Dalton: What we clearly
take is that the figure in there, in figure 10, for the maintenance
costs over 30 years is not stated on the correct basis. That's
what the NAO brought out.
Q154 Joseph Johnson: Who gave
you that figure? Who's the consultant who provided that figure
and this table?
Graham Dalton: This was generated
by our own staff, as far as I recall.
Ginny Clarke: These figures are
taken from a table that was generated by the Highways Agency,
through our project.
Q155 Joseph Johnson: Right.
And did you use the table in this form in your decision to go
for the widening as opposed to the hard-shoulder route? Was the
table presented like that in your analysis of the final decision?
Ginny Clarke: It wasn't presented
quite like that, but the figures are the same. To be clear: the
figures are the same because the NAO saw the report that went
up. The descriptors on the right-hand side of figure 10 are taken
from our words, so I can recognise the words on the right-hand
side. So, yes, it is, in fact, taken from our report.
Q156 Joseph Johnson: And you
derived the £193 million number. It's your number; it wasn't
given to you by consultants. It's your table.
Ginny Clarke: Yes, we derived
it. Yes, they're our numbers.
Q157 Mr Bacon: May I just
ask about the descriptors while you're on that subject? It says
what the things were for the £90 million below the line:
"the Intercity Express Project, Thameslink rolling stock"those
both sound like Department for Transport issues"and
the Local Authority private finance initiative programme."
Was that the entire local authority PFI programme?
Graham Dalton: That would be a
local authority transport programme, which our Department administers.
Q158 Mr Bacon: So, it wasn't
everything, it was for transport. What was the value of it?
Graham Dalton: I don't know offhand,
but it would be the street-lighting PFIs and similar street maintenance
PFIs, such as the one that's just been let in Birmingham.
Ed Humpherson: I want to make
a broader observation about these calculations for the Committee.
The lower half of this table considers externalities, that is
to say ways in which pursuing a hard-shoulder-running option would
affect a series of other projects. That's a very sensible thing
to do and, generally speaking, we would support the consideration
of externalities. However, we were not aware that any consideration
was given to the externalities of signing the deal that was actually
signed.
Without doing the analysis, we can't say what
those externalities might have shown up, but it is plausible to
say that signing a PFI deal with higher interest rates than those
that were prevailing in the market at the time could have had
a signalling effect, and you might have wanted to include those
in some kind of analysis. It's important to realise the kind of
analysis that this is, and what it might lead you to in looking
at the PFI deal as well.
Q159 Ian Swales: On that point,
in terms of this page, we can reference appendix 1. It has three
pages of timeline, and we're already on page 3 in March 2008.
So my question is: what real flexibilities did you have at this
point? What could you have done? What could you not have done?
Or were we actually on a steamroller that was simply rolling forward,
and this was done in order to justify the route that was already
decided?
Graham Dalton: You're exactly
right. The decisions were made about where we are and not about
where one might have liked to be, which is always the way in contracts.
Q160 Ian Swales: But what
about where we were going?
Graham Dalton: The decision on
value for money, which is the table in figure 8, was on a like-for-like
basis: in buying this thing, if we bought the same thing a different
way, could we get it cheaper? Right up to the signing of the contract
and financial close, that is when we said that we couldn't buy
it cheaper; at the most optimistic we'd buy it at the same price.
This table, as you quite rightly pointed out, was saying, "If
we were to buy something a bit different, which is hard-shoulder
running, what would we have to do?" That was saying that
we would have to terminate that procurement. What it doesn't make
assessment of here are the reduced benefits that hard-shoulder
running would have given and still gives, as we are doing it now.
It doesn't give any assessment of the impact of delay to the contract
either, and the question whether we would have then impacted on
an Olympics window and would not have started the widening until
Autumn 2012.
Q161 Ian Swales: Okay. Well,
there's another angle. My real question is: if we were flies on
the wall in those rooms, would we have been hearing discussions
about go or no-go, different forms of financing and different
forms of project, or would we actually have been listening to
a discussion of, "How we are going to justify the route we
have already decided?"
Graham Dalton: As accounting officer,
I was very clear, right the way through from when I took over
in June 2008I know my predecessor was, because I discussed
it with himthat this was a procurement; a lot of work had
gone into specifying and getting it right, and this was a very
important procurement that a very important motorway has got to
operate right. I was very clear that we needed to maintain a view
on what it would cost to do it another way. These were genuine,
"Do we go or stop?" decisions.
Q162 Chair: Can I just ask
you a question about the actual contract, because it takes you
back? The contractthe way in which you framed the invitations
to tenderstopped any alternative being considered. Who
advised you of that nutty way of having a contract, particularly
when one of the people whom you asked to tender wanted to give
you a hard-shoulder running alternative? Why on earth did you
set yourself that framework? What you should care about is the
outcome, namely that you wanted people to move faster and delays
to be fewer. That's what you wanted. Telling them how to do it
was absurd, particularly when one of your tenderers wanted to
do a hard-shoulder running option.
Graham Dalton: I accept and I
agree that that original notice in the Official Journal of the
European Union should almost certainly have been worded more loosely.
Q163 Chair: Who did that?
Graham Dalton: That would have
gone out with the agencies and the Departments.
Chair: Who was responsible for that?
One of the consultants, presumably.
Ginny Clarke: The Highways Agency
was responsible.
Q164 Chair: Who advised them?
Ginny Clarke: We had one or two
advisers but the decision was the Highways Agency's.
Chair: Who? Who advised?
Ginny Clarke: At that stageyou
will see on your listwe had Halcrow advising on procurement
and we had PricewaterhouseCoopers advising on financial elements,
but the decision about what went in the OJEU notice was solely
from the Highways Agency.
Q165 Chair: The decision was
based on advice you got from internal officials and external.
I would have utterly no confidence in advice I got that limited
my options so that I then went for a solution that we find it
very difficult in the Committee to assess as a value-for-money
solution.
Graham Dalton: We need to remember
that we had already considered whether hard-shoulder running could
be piloted on the M25.
Q166 Chair: Why was it excluded?
That's what is so nutty. Why was it excluded?
Graham Dalton: The decision that
was made at the time was that having looked at it carefully and
decided this was not the place to pilot hard-shoulder running,
had the OJEU notice been worded more widelywhich I think
would be a good thing to do and we put a lot of effort into doing
that, and it is a lesson we have taken awaywe would have
still been at the question of okay, it allows us to do it, but
would we still be prepared to go into what would have been a re-bid
and a re-tender
Q167 Chair: And you are still
using the advice of those consultants?
Ginny Clarke: No. Can I just be
clear, Chair? We might have had advice, but the decision about
what went in that OJEU notice was for the Highways Agency and
the Highways Agency made that decision in consultation with its
parent Department.
Q168 Chair: I understand that.
We should probably turn to advisers. You spent £80 million
on advisers for this project, which was 7.5% of this absurd cost,
against an average spend of 2.6%, usually, on advisers. It seems
to me they gave you lousy advice and I accept you, in the end,
took responsibility for the decision. What on earth were you doing
spending this much money on advisers?
Graham Dalton: Can I just come
on to the comparators first? As I think I said when we met a couple
of weeks ago when we started getting into this, the 7.5% is a
calculation against the two stages of widening, sections one and
four. The contract that is being put together enables us to do
works to, widen or improve the other two sections as well and
enables the operations and renewals over the 30 years. The norm,
which is capital investments of, say, £100 million to £200
million on a PFI, of 2.5% is the norm across all the range of
PFIs. This is a PFI where, even if you just include the other
two wideningsanother £1 billionthe 7.5% starts
to look like 3.75% just by that calculation, so there is a factor
of percentages taken against a low capital figure.
This is an operational motorway. We don't just
write something for a new facility, which gives fairly free reign
to the PFI company on what they provide and output terms. We do
specify, quite heavily, the performance that they have to give.
We want them to take full responsibility for this network over
30 years. We have provided them with complete records, documents
and drawings going back for the life of the scheme. To enable
them to price it, we had already gone through the early stages
of design. We have produced a reference design, and it was really
important that we did that, because, while this is still widening,
it is not the widening that has previously been done on motorways,
because this was done within the land corridor. If you drive around
the north-west section now, where the motorway goes under the
Chiltern railway line, you will see that it is squeezed through
under that viaduct. Had we gone for a conventional approach, we
would have had to rebuild that viaduct. That would have added
hundreds of millions into the scheme. We had to do the design
work to test that we weren't going to be immediately hit with,
"I'd love to do it, but it's not physically possible,"
or, "I need to take extra land," and then get into compulsory
purchase and the rest of it. A lot of work has gone into its viability
and into providing records.
Q169 Chair: Why consultants?
Graham Dalton: Because the Highways
Agency, since it was set up, and also, in fact, its predecessor,
when it was a departmental body, have contracted out since the
early '80s.
Ginny Clarke: Since the early
'80s, we have not done our own designs, so a chunk of this was
about the design. I would separate them out, so the design is
that bit that we always contract out. That is the model.
Q170 Chair: Is that value
for money?
Ginny Clarke: Yes. We would otherwise
have to employ all those people ourselves.
Q171 Chair: Yes, but if you
are paying a consultancy, you are paying a bomb. We presumably
noticed this in the paper in that we had on consultants. Was the
Highways Agency included in the consultancy?
David Finlay: No. This is external.
Q172 Chair: The Department
for Transport is the highest spender on consultants. It spends
70% of its staff budget on consultants. What do you spend? If
you look at your staff costs and then look at your consultancy
costs, what percentage is on consultants?
Graham Dalton: If I use the staff
numbershow many have we taken out?
Ginny Clarke: We've taken about
140 of what we call consultants sitting in our offices, which
is distinct from people who sit outside and are effectively a
contracted service.
Q173 Chair: 140?
Ginny Clarke: In the region of
140.
Graham Dalton: Just over 200.
Ginny Clarke: That is from 1 May
to the beginning of November.
Q174 Chair: 140 consultants.
How many staff?
Graham Dalton: 3,800.
Q175 Chair: What is the relative
cost? Your staff bill will be x; what is your consultancy bill?
Graham Dalton: I haven't got a
separate print for consultants. You can see in the daily rates
that we have here that we use engineering consultants, which typically
cost some £500 a day.
Q176 Mr Bacon: We are not
interested in thatwell, we arebut I understand the
Chair to be asking a fairly simple question. How much in total
do you spend on staff, how much in total do you spend on consultants
and, thus, what is the ratio of one to the other?
Graham Dalton: Can I just explain
a little bit more about the model of the Highways Agency? We have
3,800 staff. Some 1,700 of them are uniformed in control rooms
or traffic offices, and the balance is professional staff, but
most of the work that is done on the networkeven where
it is badged up as Highways Agencyis contracted out.
Q177 Mr Bacon: I am just asking
you a question to which I'd quite like an answer. I'm not saying
that it's good or bad. I used to represent the consulting industry.
I used to work for the Management Consultancies Association. I
quite understand that if you want to build a motorway, it's probably
better to get a consulting civil engineer, under a contract, for
the period while you want your motorway, rather than to keep one
on the books just in case you want a motorway. That is fairly
elementary. What I am asking you is what the costs are?
Chair: Do you know, David?
David Finlay: We've noted in our
report, in paragraph 2.26, that there was very limited information
on internal costs. That's why we haven't put that in.
Chair: I think what we're after is your
annual cost of staffing and your annual cost on consultancy. Those
are the basics.
Q178 Mr Bacon: Why don't you
send us a detailed note that sets it all out and hopefully justifies
it?
Graham Dalton: My overall staff
coststhe costs of employing Highways Agency staffare
just over £50 million per annum. I don't have a figure to
hand of what we are spending on the consultants in our offices
in the current financial year. We have had more last year, because
we were delivering the fiscal stimulus.
Q179 Mr Bacon: What is the
total that you are spending on consultants, whether they are in
your offices or watch what Ginny Clarke called contracted staff
out and about?
Graham Dalton: That is a very
substantial part of our budget and our overall budget is £2.5
billion per annum.
Q180 Mr Bacon:
Okay, but "very substantial" doesn't really help me;
£200 million is a lot of money, but so is £2 billion.
Ginny Clarke: The bulk of our
costs are spent on the construction, so in terms of the consultant
staff, if you include these design people, then they are in the
regions of hundreds of millions.
Mr Bacon: I'm sure that they are. It
may be that you spend far more on consulting staff, of one kind
or another, than you do on your in-house staff. That might be
perfectly reasonable and reflect the nature of your business,
as opposed to, shall we say, a police force, where you might expect
most of the constabulary to be constables who are employed. It
is something that may be intrinsic to your business. I am just
asking you, and I think so is the Chair, what it is, and you don't
seem to be able to tell us.
Ginny Clarke: I cannot give you
that number off the top of my head. I know that our staff costs
are £50 million.
Mr Bacon: If you could give us a detailed
note, that would be helpful.
Q181 Ian Swales: On consultants,
I am sure that there is a mine of information here. We could ask
lots and lots of detailed questions, and I'm sure I can think
of people around the table who enjoy doing that. Just as a kind
of sampling, on the supplementary information that you've sent,
you say that the Denton Wilde Sapte people, who I understand are
lawyers, apparently spent four years advising on pensions and
TUPE advice. Who are we talking about? Why would they be giving
us all that advice?
Graham Dalton: For example, as
part of this contract, there were something like 100 staff previously
employed by a concession that ran and operated the Dartford crossingthe
bridge and tunnelswho were TUPE'ed into the Highways Agency,
and are now part of our traffic officer service. We have integrated
that with our overall traffic management. Other staff were TUPE'ed
from the previous maintenance contractors into Connect Plus.
Ian Swales: That is 100 people.
Graham Dalton: Many more were
TUPE'ed the other way.
Q182 Ian Swales: We started
paying for advice about that in 2005, and we were still paying
for advice about it in 2008. There is a very complicated project
going on in my constituency at the moment, where the TUPE advice
would probably be six weeks, or three months at the most. That
is for a very complicated deal involving 10 times as many people
as that. Why would we have paid for that advice for so long? What
was so difficult about it?
Ginny Clarke: In the early years
it is about helping us put the proposals together in the tender.
In the subsequent years, it was looking at the proposals coming
back. The activity flows through the actual transfer of the staff
when the actual TUPE action happens, if there is any uncertainty
around that. That is why you have them at three distinct stages.
Q183 Chair: Can I get something
clear? Are these figures just the money spent on lawyers for the
M25?
Ginny Clarke: This is in relation
purely to the M25 PFI contract, yes.
Chair: £15 million, totting it up,
on Denton Wilde?
Q184Stephen Barclay: It was £13.8
million over six years. The first year was just £405,000,
but even if you average it out, it is £2.3 million a year.
As a solicitor who worked in a law firm at one stage, I was just
trying to work out how many full-time lawyers you actually had
on this piece of work, because £2.3 million a year pays for
quite a lot of associates. Do you have an idea?
Graham Dalton: The hourly rates
are in there at the moment. I don't have a calculator with me.
Ginny Clarke: We certainly have
records.
Graham Dalton: There would be
some other costs in there as well.
Q185 Stephen Barclay: It would
be interesting to dwell on it. I would just like to leave legal
advice to come back to appendix 1, which we discussed earlier.
The bit that I was struggling to understand was that in June 2007,
legal advisersI assume that that was Denton Wilde Saptestated
that allowing the active traffic management variance could be
challenged in the courts. That is seven years after the agency
considered the M25 for the ATM trial. Obviously, Denton Wilde
Sapteif it gave the advicewas commissioned in 2004.
Regardless of that advice, the pilot continued. In July 2008,
the 12-month report on the ATM trial was published. In January
2009 ATM was rolled out nationally. I am just trying to understand
why it took so long for that bit of advice to be given.
Graham Dalton: Going back to the
original OJEU notice, or the publication notice for this contract,
the best advice in June 2007this is on whether we should
stop that procurement or whether we could change that procurementwas
specifically that if we changed with the preferred bidder, Connect
Plus, to use active traffic management, notwithstanding the benefits
or whether it was viable or anything else, we could be challenged
not just by unsuccessful bidders but by those who either dropped
by the wayside in the early phase or who did not even register
an interest to bid for the contract originally.
Stephen Barclay: With respect, you are
missing my point. My point is that you have had lawyers on it
from the start. You then go down the track
Q186 Mr Bacon: That is the
point. In May 2007, one of the M25 bidders asked whether it could
submit an active traffic management variant bid. That is not an
unreasonable thing to ask given that seven years previously, in
August 2000, active traffic management was announced. The agency
considered the M25 for the ATM trial, but rejected it in favour
of the M42. A year later, in July 2001, the Department announced
the M42 ATM trial. So ATM was already a possibility in the mix.
Seven years later, somebody asks if they can include active traffic
management in their bid, you seek advice on it and are told that
if you allow it, you could be legally challenged. Why had you
so structured things that you were in a position in which you
might get legally challenged on something that you had said seven
years earlier that you wanted to take a look at? That is what
I don't understand.
Ginny Clarke: But the legal advice
wasn't because it was hard shoulder per se; it was about a variant,
which effectively is what they were asking us about, and whether
that variantas it happened it was hard shoulder runningwould
prejudice the position in terms of continuing the procurement.
That was what the legal advice was about.
Q187 Mr Bacon: In that case,
why not have a procurement process that is flexible enough that
it would not have prejudiced it? That is the point.
Ginny Clarke: The advice was that
it goes back to that original decision about the OJEU We recognise
that and accept that is where the decision tracks back to and
the legal advice made that point.
Chair: What I am interested in is who
gave you the advice to make such a silly invitation to tender?
If your lawyers told you that at the time, you should have sacked
them.
Ginny Clarke: Let me be clear,
the lawyers did not give us advice at producing the OJEU. That
was not about hard shoulder management.
Chair: Who gave you the advice then?
Ginny Clarke: As I said, it was
our decision about what went in the OJEU in respect of what we
were being asked to do, which was to widen the M25.
Q188 Mr Bacon: You said that
it was Halcrow that gave you the advice.
Ginny Clarke: I said that they
were our procurement advisers. I said quite clearly that the decision
Q189 Mr Bacon: The Chairman's
question was, "Who gave you the advice?". You answered
by saying, "The decision was". The answer to the question,
"Who gave you the advice?" is your advisers, Halcrow.
Ginny Clarke: In terms of procurement,
yes. In terms of legal advice, it was Denton Wilde Sapte.
Q190 Mr Bacon: And you paid
them several million pounds as well£2.3 million in
one year, and £1.5 million in the next, £600,000 and
technically, excluding design, £1.6 million. You paid them
a lot of money as well and yet you end up in this idiotic position.
Ginny Clarke: This contract was
four times the size of any previous PFI that we had done in terms
of cost. We need to recognise that.
Q191 Mr Bacon: That is an
interesting way of putting it: four times the size of any PFI
contract that wewe, the Highways Agencyhad done.
It wasn't four times the size of any PFI contract that was out
there. We have, for years on this Committee, looked at really
big PFI contracts. The cash value of MOD building alone is £2.5
billion. There was lots of experience to draw on right across
the PFI sector in government to get it right.
Ginny Clarke: And presumably you
have the OGC involved.
Graham Dalton: I absolutely accept
that the need to word an initial OJEU notice as widely as it can
be to avoid this technicality later on. That doesn't change the
question. We would still have a decision. Was active traffic management
sufficient to develop? Had we entered into a contract then, we
would have been buying significantly lower benefits and had less
throughput on a busy piece of motorway. Even now, while we are
thinking that it's probably going to work for the later upgraded
sections, for one of the two being widened down we don't think
it would have been suitable.
Chair: David Finlay, then Stephen.
David Finlay: I have two points,
if I may. First, just on a point of information, within the sheets
that were circulated yesterday, it says, under the legal advisers,
that they gave advice on procurement strategy. So, that was certainly
within the legal advice. Secondly, the evidence that Mr Dalton
gave at the beginning of this section was that part of the reason
for the high advisers' cost was that the advice dealt with not
only the two sections that are being widened, but the prospect
that other sections would be widened. It is worth noting, of course,
that those other sections are now liable to be used for hard shoulder
running. That may bring you on to the point that you wanted to
explore about whether the agency could have come to a decision
quicker on hard shoulder running.
Chair: We'll come back to that. Stephen.
Q192 Stephen Barclay: I just
wanted to clarify who was actually managing the legal relationship
with Denton Wilde Sapte and how often their bills were challenged.
In paragraph 20, it says that "The Agency's reliance on advisers
reflects
insufficient commercial and technical skills within the Agency",
and "The Agency risks advisers controlling projects".
That is one of the findings of paragraph 20. What I am interested
in is this: if it was a commercial client and they were putting
in fees of £13.8 million over six years, someone would be
going back to the lawyers and saying, "Let's challenge that,
let's question that". How robust was the challenge? How frequently
were those bills challenged?
Graham Dalton: Each of the streams
of work was led by a member of the Highways Agency staff, so it
wasn't consultants managing consultants in that respect, but it
was a high proportion in there.
Stephen Barclay: I was not suggesting
it was.
Graham Dalton: We have very rigorous
and audited systems and internal control, so I would hope that
there is no suggestion that any bill was just sent in and not
checked and validated for work that had been done.
Q193 Stephen Barclay: People
may have checked it and signed the cheque. What I am trying to
understand is that there must have been some negotiation done.
I cannot believe that Denton Wilde Sapte putting in a bill for
£13.8 million was its actual submission. Presumably, it put
in fees and someone went back to them saying, "No, we don't
accept that bill" and had some sort of discussion.
Ginny Clarke: I was just going
to explain the process. They, like our other advisers, had to
produce invoices every month, and they produced a detailed breakdown
against that invoice. The project teams, those are the people
who sat
Q194 Stephen Barclay: When
you say detailed invoiceI say this because I have produced
legal bills for firmsare you talking about something that
is one sheet or two sheets of paper?
Ginny Clarke: It would probably
be more than that, because they would be contracted on the basis
of levels of fees, so who was active in that month and against
what rate they were being charged against. That is the level of
detail that I was explaining.
Q195 Stephen Barclay: That
is the bit that is worrying me, because it sounds to me that it
is just sending a bill once a month saying, "Associate x
has worked 20 hours, partner y has worked 15 hours." I still
come back to the question: how often were those bills challenged?
Ginny Clarke: They were reviewed
every month. They have to be signed off by somebody in the Highways
Agency who says, "I agree this time was spent and these are
the appropriate rates". That is what the role of our project
staff is about, and it was done on a monthly basis.
Q196 Mrs McGuire: Were any
sent back?
Ginny Clarke: I can't answer that
question. It isn't
Q197 Mr Bacon: Do you know
what? I have met PFI lawyers at parties and I have said, "What
do you do?". "I'm a PFI lawyer", they say. Now,
people never used to answer that question with "I'm a PFI
lawyer", but they do now. They have talked to me about putting
in bills to the public sector and they say, "It's great,
you just send in the bill and they pay it. It's incredible. I'd
never get the sort of ease of payment with my private sector clients.
They go over it with a bloody tooth comb and put me through the
mill, but the civil service just pay. It's marvellous!"
Ginny Clarke: Perhaps they haven't
billed the Highways Agency then, because I suggest that we do
in fact check these things. What I cannot answer is how many times
did we throw it back.
Q198 Chair: Are you confident
that you got value for money for the £80 million you spent?
Ginny Clarke: I am confident that
we got value for money. I did not see everything that was spent
against that, but to the best of my knowledgeas I have
said, I was here throughout the projectwe have had good
advice. We have tried to get it at market rate. I take the point
on how much that was challenged, but it was against frameworks
and we have detailed how those services were procured. They were
in a competitive environment. That is the basis against which
we checked those monthly invoices.
Q199 Chair: There is one final
issue which we need to quickly go through, which is the hard shoulder
running principle. It has been used in Europe since 1996, yet
you spent 80% of your money simply on constructing roads, probably
because you like doing it. You started the trial in 2003 on the
M42 and you had evidence, so why on earth did you not save the
taxpayer between £400 million and £1.1 billion by changing
your mind and going for hard shoulder running?
Graham Dalton: Running on the
hard shoulder, as you would expect me to say, is not quite as
easy as it looks.
Q200 Chair: But you are doing
it now on the rest of the M25.
Graham Dalton: We are coming out
of trials on the M42. The NAO talked about an earlier report in
2004, and one of the recommendations was to be more innovative
and hard shoulder running is about that. We have tested and trialled
it in a controlled manner. We have done it very carefully, so
that we can demonstrate as we have gone through the phases how
that changes performance and how it changes risk.
Q201 Chair: Mr Dalton, I am
going to interrupt you. It has been used in Europe since 1996.
That is 15 years of usage. You have trialled it since 2003. You
signed this contract in 2009. It beggars belief that you could
not take advantage of the experience in Europe and your experience
here, however slow you were at getting off the ground, and save
the taxpayer up to £1.1 billion.
Graham Dalton: We have worked
closely with Europe, especially with the Dutch throughout the
time. I think it may help if Ginny explains what was being used
in Europe.
Ginny Clarke: In 1996, which was
when the Dutch and the Germans tried this first, they tried it
on two-lane motorways and on relatively low flows compared with
ours. They were flows in the range of 20,000 to 40,000, rather
than ours, which is 140,000. We also have three lanes. They did
it as a research project, on a short section outside Utrecht.
We looked at it, and they were doing it on the basis of trialling
it on the ground. They did little preparatory work for it, and
they did it on a section of motorway where they had technology
and control systems in place. We did not have that. That is how
it started.
When we were looking at it in 2000, which is
the study noted in the NAO report, and when we identified the
need to do a trial section, it was on the basis of that learning
experience. It was not the system that is actually being used,
and was potentially considered in 2004-05, when this contract
was put in place. The evidence that we now have is much more substantial
than we ever had at the basis. In the progression from 1996, with
those trial sites on short sections in Utrecht and Germany, which
had very different characteristics and were on a type of motorway
that did not exist in this country, we have caught up with the
technology that is available. We have related the results of what
the Germans and the Dutch have learned into using it on larger
motorways with much higher flows with a variable system of control.
Q202 Chair: You wasted £1
billion.
Ginny Clarke: No, I do not think
that we wasted it. At the various stages, we tested it against
the knowledge that we had at that time.
Q203 Chair: It seems to me
that you refused to use the knowledge from Europe, although the
systems that you have in place use the technology they use in
Europe, as Richard has told us.
Ginny Clarke: Effectively, ours
is more advanced than what is used in Europe. We leaped from their
knowledge.
Q204 Chair: At a cost. At
an opportunity cost of between £400 million and £1.1
billion on this bit of motorway. If you had done it earlier on
the rest of the motorway, the benefits to the economy would have
been greater.
Graham Dalton: We wanted something
that worked. The German trial in 1996 involved putting a sign
up at the side of the motorway saying, "Use the hard shoulder
between these hours."
Q205 Chair: Some 15 years
on, the Germans have presumably moved their technology on.
Ginny Clarke: Yes they have, but
effectively they are picking up on things that we are doing, which
they were not doing. The important aspect about how this learning
has happened over that time is that as it has changed incrementally
as each country has tested different things. I accept that we've
all learned from that, but the basis is that we have operated
a system under active traffic management that ensures that we
can deliver the 80% of the benefits that the national study showed
for Ministers in 2008. The value of what we have done is that
we have got more benefits out of the systems that we are using.
I say again that the PFI was about buying the benefits as well
as paying the cost for that.
Q206 Mr Bacon: Ms Clarke, may I ask
a quick question? Your CV says that you are responsible for technical
services procurement and network performance and planning, that
you're board champion for safety, that you've been in the road
workers' safety forum and that you were the delegate to the World
Road Association for seven years. It says that your job title
is chief highway engineer, but it does not say that you're an
engineer.
Ginny Clarke: I am a chartered
engineer and have been for 30 years.
Q207 Mr Bacon: That is encouraging.
Can I encourage you to include that in your CV in future?
Ginny Clarke: Certainly. I probably
just didn't want to tell you my age.
Q208 Mr Bacon: We don't like
to assume things in this Committee.
Ginny Clarke: Sorry for omitting
that. I should have said so.
Q209 Chair: A final question.
Reflecting on this contract, are you proud of it? Are you satisfied
with it? Do you wish you'd done it differently?
Graham Dalton: The most telling
thing is that, unlike some earlier PFIs, we have a lot of visibility
in respect of what goes into the contract and we can put a lot
of pressure for performance on an important piece of the network.
Connect Plus for the contractor means having to work hard and
it looks like it is working hard to comply with conditions of
the contract. It is not finding it easy to comply with all conditions
and give the performance we expect. From that point of view, we
think we've contracted something that they are having to sweat
to deliver and that is good.
Q210 Chair: Are you proud
of it?
Graham Dalton: Yes.
Q211 Chair: Are you satisfied
with it or would you have done it differently?
Graham Dalton: On the whole, I
would have done it the same again.
Q212 Chair: You're proud of
it?
Graham Dalton: Yes.
Chair: Thank you very much indeed.
|