Network Rail - Transport Committee Contents


Examination of Witness (Question Numbers 1-74)

David Higgins

1 March 2011

Q1   Chair: Good morning, Mr Higgins. Welcome to the Transport Select Committee and congratulations on your new and challenging position. I understand, Mr Higgins, you want to make an opening statement to us, so would you like to do that?

David Higgins: Thank you for the opportunity to make an opening statement before I take your questions. As I assume the role of chief executive of Network Rail I would like to recognise that I am the custodian of a large amount of public trust. The rail industry matters hugely for the country, it matters hugely to millions of people that use it every day, it matters to the economy and it matters to our sense of national pride and purpose. So I would like to start by paying tribute to my predecessors John Armitt and Iain Coucher, who have led Network Rail over the last nine years.

Since 2002, significantly more people now use the railways. At the same time, safety, punctuality and cost efficiency have all improved. That is a record of which the whole rail industry can be rightfully proud, but I believe we are at a crucial moment for the rail industry and for Network Rail in particular. Key challenges in many ways are the same, but the environment in which we operate is now very different.

First, with regard to safety, railways have had a good safety record in recent years. That has not always been the case. We are still working through and learning the lessons from the tragedies that happened several years ago. The pain of relatives and friends affected is a reminder that, no matter what cost pressures we have on us in the future, safety must and will remain our number one priority.

Secondly, we must keep a relentless focus on punctuality and reliability. There has been a step change in performance in the railways in recent years, but there is more work to do. However, we have to recognise that we have reached the stage on some of our routes where the ability to squeeze extra capacity is becoming limited. Long­term investment is needed both to create reserve capacity and to cope with future growth. Crossrail, Thameslink, High Speed 2, the Northern Hub, electrification and the overhaul of our signalling system are all essential to meet public and industry expectations.

This leads me to the third challenge—cost control. In short, we need to do more for less. Network Rail receives a large amount of public subsidy. I believe this is absolutely right. We need to invest more in our rail infrastructure to create the modern railway that our country needs, but that comes with a responsibility to drive a culture of cost efficiency, to look at squeezing every penny out of everything we spend. This is taxpayer money and taxpayer value. We are stewards of public funds and we should never forget that.

Finally, to achieve all this and to benefit from the continued support of the public end of our industry, Network Rail must change. We must listen more; we must empower better. We need to be less defensive and more agile. Above all, we need to embrace openness. My vision for Network Rail is an organisation that blends the best of the public sector and the private sector. We need to have a "can do" dynamic entrepreneurial culture, but we also need to have an organisation that is firmly rooted in public sector values of accountability and transparency.

We have a brilliant workforce who work tirelessly for our industry. They work round the clock and they work every day of the year. They do a magnificent job for our industry and our country. I look forward to leading them and look forward to the exciting challenges ahead for our organisation. Thank you.

Q2   Chair: Mr Higgins, you have spoken about making Network Rail open, transparent, accountable and responsive. What do you think are the first steps you could take to show that you are serious about wanting to achieve that?

David Higgins: The first thing I am looking at is engaging particularly with our suppliers and with our customers. Our customers are the train and freight operating companies, as well as the customers that use our stations, particularly our 18 major managed stations. Then there is our supplier group. We need to listen more to both these groups of organisations, because we can learn a lot from them, and that is essential to creating a more efficient organisation. We have started that process. We have a series of conferences and workshops with our suppliers, starting within the next month.

Q3   Chair: I am surprised, Mr Higgins, that you haven't mentioned the current investigation taking place into allegations of bullying and other possible misdemeanours within Network Rail. Isn't that something that is very much at the front of your mind?

David Higgins: There is the White inquiry, which is an independent inquiry into the allegations that surfaced a while back in a number of newspapers. Those are the allegations of financial impropriety. They were investigated by our previous auditors and our current new auditors Pricewaterhouse and were reviewed. But, in order to show independence, the board and the chairman have set up an independent review, and we expect that to report at the end of March. I have had nothing to do with the briefing of that review and I don't know the progress of it. I know that it is going to come out at the end of March. All I want to know is that we get a clear decision. If there was impropriety, we will deal with it. If there wasn't, we need to put an end to that issue.

Q4   Chair: Will that report be made public?

David Higgins: As far as I know it will be, but as I say, I am not directly engaged in it. I did not commission the QC involved in it.

Q5   Chair: What would your view be on making the report public?

David Higgins: Why not? I think it should be made public. Why not, because the issues that circulated around that were quite publicly aired, yes?

Q6   Chair: You have spoken also, Mr Higgins, about the importance of safety. In fact, you say that must be an overriding priority.

David Higgins: Yes, indeed.

Chair: On 3 December 2005, clearly well before you were in your position, two girls—Olivia Bazlinton and Charlie Thompson—were killed at a pedestrian rail crossing at Elsenham. It now appears that Network Rail had carried out a risk assessment three years before the accident which had suggested that consideration should be given to locking the gates before trains passed. That clearly wasn't done or the accident presumably wouldn't have happened. It appears that Network Rail did not hand over that risk assessment to the appropriate authorities after the fatal accident. What lessons do you draw from that, and have you initiated any actions in relation to rail safety bearing in mind that information?

David Higgins: First, I would say I draw no conclusions from any of those statements that have been made. I have committed to the family members that I will fully investigate the chronology of events and the transfer of information between the various inquiries. There were three inquiries. I am actually meeting the family members this week. My first commitment to them is not to fuel media speculation on an issue that is their issue. I will give them all the files of the chronology of events, and then essentially it is up to their decision and mine, but I would propose that we make those files public. That will set out the chronology of events of releasing the information to those various inquiries.

Q7   Chair: Are you concerned there could have been other examples of situations where risk assessments were carried out but the recommendations were not put into practice?

David Higgins: Certainly, improvements were made after 2005, but there is no doubt that the training of risk assessors and the quality control of implementation of actions, across what is 7,000 level crossings, need to improve. We need to enhance all the services and all of our level crossings. So the simple answer to that question is, yes, we need to do substantially more, and we will.

Q8   Gavin Shuker: I am aware we might jump around this morning, so thank you for coming before the Committee and answering these questions. I want to ask you about the structure of Network Rail. You have obviously been in post for a short period of time. What do you believe works well about the structure of Network Rail and what do you believe works badly?

David Higgins: Enormous gains have been made in the last nine years by centralising a lot of the disciplines. Asset management is a very, very important discipline in this network. We have 9,000 km of embankments and 6,000 km of cuttings. We have 40,000 bridges in this asset base. Having a record of that asset base and how you upgrade it, what level of inspection you do on these various assets and where you put money both to get the best return for taxpayers and customers but also to cover safety is very important.

We are still in the early days of assembling that level of information and being able to make risk decisions on how we intervene on those assets. What has worked well is the centralisation of asset management, but a lot more work needs to be done. Bringing maintenance in­house was absolutely fundamental; it was really essential. Our national delivery service, which uses the buying power of the network, whether it be for buying sleepers or for planning blockades, are all tremendous improvements.

I have only been here a little time, although I have been a non­exec director for a bit longer, but what is obvious is that there are tailor­made solutions for different routes, our customers can give us information which we don't have and we can amend our management and improvement of the routes to the benefit of all. We need to be more localised in the decision making. Some of the really big decisions will never change, but for some of the smaller local decisions we can free it up.

Q9   Gavin Shuker: You will be aware that there is a lot of speculation about the structure of Network Rail going forward, perhaps with more regionalisation. You raised it yourself. How far can we go down the route of regionalising the work that Network Rail does while retaining it as a national asset?

David Higgins: I have already announced last week that we are going to devolve into route­based businesses. That means empowering the decision making at what I call a route managing director. These executives will run businesses. They won't just run a cost centre. They need to have a lot more authority to do that. They need to be far more aligned and incentivised from a business point of view with the train and freight operating companies with which they work. So that is important. But, as we do that, as we delegate more authority and power to the regions, we need to strengthen our central assurance, because to do that without at the same time strengthening at the centre would be risky.

Q10   Gavin Shuker: Just talking about the regions for a moment, what effect will that have on the wider rail industry by going to a regional structure? Will we see larger TOCs, for example, more alignment there? You must have looked at the effects that it would have on the wider companies that work on our railways.

David Higgins: It is a national network, and it is always important to remember that. On our biggest routes such as West Coast, there are six major operators that operate every day on that route. The reason for having a national network, and therefore Network Rail, is to balance all those competing demands, and that will always remain a key issue. But I think the great opportunity that comes up now is that there are a lot of franchise renewals coming up. We need to take that opportunity to re­craft those agreements so that they are less prescriptive and more outcome-based, therefore encouraging the entrepreneurs—the private sector—to be much more creative in how we put money into the network to get better returns for taxpayers.

Q11   Gavin Shuker: That is very helpful. I am sure other members will want to return to that. Finally, can I talk to you for a second about the corporate governance structure of Network Rail? There seem to be a couple of different models, one of which was in the coalition agreement, about slimming down the board to maybe 15 or 20 members. Another model would be to open out much wider—maybe a mutual model for Network Rail. Have you done any work since coming in to look at either of those options?

David Higgins: I personally am not doing that work, our Chair is, and he has advice on board already. He is in a lot of consultation with members about that, so that is work in progress. I believe it is coming to the annual general meeting in July as a next step, but I have nothing more I can comment on that at this stage.

Q12   Gavin Shuker: Will you express your personal view before July or at the July meeting?

David Higgins: Yes, of course, but it would have to be in the context of both our board and also the Department.

Q13   Kwasi Kwarteng: I want to ask a specific question relating to Mr Shuker's earlier question with regard to your asset base, because when you mentioned the assets you were not talking about shops or things that you own, which interested me, because presumably that is where, potentially, you can get a lot of return.

David Higgins: In terms of the property assets?

Kwasi Kwarteng: That's right.

David Higgins: Yes. The opportunity there is to look at the relationship we have with the various rail operators. There are thousands of stations.

Kwasi Kwarteng: That's right.

David Higgins: We manage the major 18, which are really critical, particularly the London network. But how you do repairs, maintenance and upgrades on the balance of the stations is something that I know the Department is looking at and considering it in the franchising exercise.

Q14   Kwasi Kwarteng: There are two things. Am I right in saying that, historically, you have not been very successful at getting top returns from your asset base?

David Higgins: I am not sure. I have not seen those figures. In terms of the property asset base?

Kwasi Kwarteng: Yes.

David Higgins: Always remembering property is there to support the main operating business—

Kwasi Kwarteng: Sure.

David Higgins: I am new to this, I have to admit, but certainly it seems very fragmented. A number of the key stations have some very, very complicated property ownership, with air rights, and there are multiple owners. If you look at Waterloo, for example, there are multiple organisations that own the asset that you would think is one station. Therefore, I think there are more efficient ways of doing that. Certainly, on assets that are primarily shopping, there is a role for bringing in the private sector both as investors and as managers.

Q15   Kwasi Kwarteng: That's right. Okay, that was the first bit. The second bit is that you talk about taxpayers' money and being more efficient. Would you not agree that looking at your asset base, and trying to make that more efficient in terms of the return, is a massively high priority with respect to your job as a custodian of public finances? Do you see what I'm getting at?

David Higgins: You are absolutely right. It is very important. There is a very large asset base. We also have to remember that there is a huge responsibility of upgrading the asset base.

Kwasi Kwarteng: That's right.

David Higgins: If you look at many of our stations, some of them were built in the 1860s. If you look at Waverley station in Edinburgh, there are £130 million of absolutely essential repairs needed to repair that station for very little financial return.

Q16   Kwasi Kwarteng: My worry with this is that you are looking at this purely in terms of the capital expenditure requirement, and I am worrying or concerned about whether there might be a strategy going forward to try and get a better return. Obviously, that is linked in with the capital expenditure.

David Higgins: Of course.

Kwasi Kwarteng: But all you are talking about now in the last few minutes that I have questioned you has been on the expenditure side.

David Higgins: Yes.

Kwasi Kwarteng: And I haven't got any indication from you, if you have a strategy, once the capital expenditure has happened, of getting a return. Are you going to sell some of these assets? Are you going to try and lease them out to private operators or—

David Higgins: Absolutely, yes.

Q17   Kwasi Kwarteng: Did you say yes? Because there is no—

David Higgins: No, indeed there is. Last week I was in Birmingham. We announced that John Lewis would take a major tenancy in that structure there. We have a great investment partner in Birmingham City Council. We will certainly look at institutional investment in there because it is logical. If you look at stations coming into London, there is spare land and car park land. I think there are opportunities there.

Q18   Kwasi Kwarteng: So there are dynamic possibilities?

David Higgins: There are, indeed.

Kwasi Kwarteng: I just wanted, for the record, to say that what you are saying I have prompted out of you. When I asked you, your initial answer was all about the capital expenditure side, the spending and the upgrade.

David Higgins: That is true, because property must support. We can't let property divert the core intention.

Kwasi Kwarteng: I understand that.

David Higgins: Network Rail is a £6 billion a year operating business where the stations are about millions of people that use it every day. That must be the core intention to get right. Yes, bringing in the private sector is absolutely what we should be doing, provided it doesn't damage the core role.

Q19   Kwasi Kwarteng: This is my last point. I just think it's significant that, if I was asking the CEO of any business what his growth strategy was, very few of them would be talking about capital expenditure as the first thing in terms of a growth strategy or trying to use their assets more effectively.

David Higgins: Sorry, very few would be talking about capital expenditure?

Kwasi Kwarteng: Yes. The first thing you mentioned in response to me was that, and that, to me, is significant and interesting. That is all.

David Higgins: One of the first things I did was to go to Birmingham and speak to our partners and say, "Can we bring in private investors into this asset?" because long term we need to bring in institutional ownership and free up their money. Certainly, that is a desire of our partner there but also from Network Rail's point of view. That is my background. My whole background has been private investment in property. I was in charge of the company that developed Bluewater. So I am very, very aware of how we bring in private institutional investment, taking risk. It is not our role to do what the private sector does better.

Q20   Kwasi Kwarteng: Can I ask one more question on this? Is your principal focus in this upgrading the plant and equipment, as it were, the capital expenditure? Is that your principal thing at the moment? That is the most pressing need?

David Higgins: My main role is to have a safe and efficient railway, so that is the core business.

Kwasi Kwarteng: That is a general answer to my question.

David Higgins: You are right. In some of our assets, if you look at it over the last 20 years, decisions were made to release capital, but it has made it much more difficult then to upgrade the network or the major London stations because of the head leases we have inherited or the various easements or whatever that have been offered. In some cases we are trying to untangle those complicated property transactions which released short­term value but set up the network for long­term problems. When we unravel those, we then bring in the institutional investors that can own and operate these assets much better than we can.

Q21   Mr Leech: I was pleased to hear in your opening statement mention of the Northern Hub, and I hope it wasn't just because there are lots of members from the north on the Committee. How important do you think it is that funding for the Northern Hub is available in the next control period?

David Higgins: You would expect me to do my homework on the Committee members, but I did not put it in for that reason. I have already been up to Manchester and talked about that with Howard Bernstein. I did that about four months ago when I was a non­exec director. It is essential.

The challenging thing with our network is that you can spend money everywhere. The key is to spend money judiciously in certain areas to get greater capacity. The great thing about the Northern Hub—Leeds, Manchester and Newcastle—is that we can get a 50% increase in passenger utilisation and a return on investment of about four to one by investing the money in the Northern Hub. From my point of view, for control period 5, which starts in 2014—we don't have the capital money in our budget for this control period—we must make it our top priority to invest in the Northern Hub, because in terms of return, it will increase passenger movement in that northern area, and we know that is linked to economic growth. So I'm all for that. My previous job before the Olympics was all about economic development and regional development and regeneration, particularly in the north. So I do understand the critical link between transport, regeneration and jobs. So it's a priority.

Q22   Mr Leech: You actually said it was your top priority.

David Higgins: Yes.

Mr Leech: That would be your number one priority.

David Higgins: Absolutely right, yes. It has gone into our first work on our initial proposal and I personally think it is absolutely essential. But, like everything, we compete for resources. With regard to Control Period 5, it is absolutely crucial that we get the support of the public, taxpayers and Parliament for that.

Q23   Mr Leech: In terms of the shift to a regional structure for Network Rail, what impact will that have on capital investment priorities? Is there a potential for the different regions to have more localised priorities by moving to a regional basis, or are you very clear that overall spending priorities for Network Rail would still have a central basis?

David Higgins: Yes, they will: overall spending priorities, the determination of the control period and our overall investment plan for the five-year period, absolutely. What we do then is to start with utilisation strategies which feed into the control period. But then, on a yearly basis, we look at our various delivery plans. It is what we are going to spend our money on each year on the route that comes from the overall, centrally controlled budget process. There is good opportunity to deliver it locally, but what I have found, and I am sure the rest of our organisation knows it, is that our partners have as many ideas as we have on what investments we can make on particular routes to get greater productivity out of that.

We need to use all the best knowledge we have, both at the operator level and at a local level, informing those national plans. But we are not going to fragment the industry and fragment our organisation. I have heard all the war stories of the barons of previous years. We won't return to that. We will still keep a central investment management strategy.

Q24   Mr Leech: You also mentioned in your opening statement about High Speed 2.

David Higgins: Yes.

Mr Leech: Obviously the opponents of High Speed 2 claim that there is a strong case for there being no need to have a high-speed line and improvements on the existing main lines could increase the capacity. In your view and Network Rail's view, how long would the existing network be able to cope before it ground to a halt in terms of capacity, without High Speed 2?

David Higgins: Before I answer your question directly, I would just say that the result of transport on jobs and economics is obvious. If you look at Leeds, there has been a two-hour service there for years. If that was three hours and unpredictable, what would the commercial value of property in Leeds be? Ditto at Brighton. If Brighton had a service that was far less reliable and longer, what would it do to residential prices? The link of efficient, reliable and fast travel brings jobs.

With West Coast, it has been a tremendous success. £10 billion upgrading West Coast means that now that franchise is having customer growth of over 10% per annum. At Christmas it was up by 20% year on year. That West Coast line, within 10 years at the absolute maximum, and probably six years, will be at capacity, and that is with additional carriages included in the area. We can look at other tactical interventions in that line to put more capacity in there, but in the end it comes down to capacity: we will, across a number of key parts of our network, run out of capacity.

Q25   Mr Leech: How many years do you predict that it would be—

David Higgins: Six to 10 years.

Q26   Chair: Is that six to 10 years from when it runs out of capacity?

David Higgins: From today. If it keeps growing at the rate it is going today, and if petrol prices keep going in the way they are going, then in 10 years' time West Coast will be at capacity.

Q27   Chair: Do you anticipate that growth will take place?

David Higgins: I don't know, but all we can do is look at what has happened today. Looking at what has happened on West Coast with the more reliable service, over the last few years, with the new timetable, certainly the customers have responded.

Q28   Mr Leech: One last question, Chair. Do you have a personal view or a Network Rail view of vertical integration?

David Higgins: I would use the term "alignment". I think there is huge benefit to be achieved by aligning the interests. But it is very, very complex if you look at vertical integration, because the reason that we have a network is the UK is a very densely populated country. Our rail network is incredibly complex. It requires a great challenge all the time to weave the various train paths through the network, from freight to open access, to the various train operating companies. There are one or two areas where you can see the benefits of vertical integration, but across a large part of our network there is a challenging role of integrating it. That being said, there are many benefits that can be achieved by much closer alignment. The current structures are set up for conflict.

Q29   Mr Leech: Can I just ask one follow-up from that? I should declare an interest as the Chairman of the All Party Parliamentary Light Rail Group, but there is a case being made in the light rail industry at the moment for taking some lines out of heavy rail and converting them to light rail. There are claims being made that they could run the service and improve the service for less subsidy than is currently being found on specific lines that could be classed as being capable of being vertically integrated. Do you have a particular view on that?

David Higgins: I don't know. Intuitively, I think you are right. I don't know, I haven't seen the data on it. We set standards across the board, but there are different sorts of railways. There are high-speed railways, high-frequency railways and then the railways you speak about. I think it would be worth while exploring areas of whether we can convert heavy to tram. If you look at Germany, they do that effectively in areas there. There must be something we can learn from that.

Q30   Kelvin Hopkins: I must say many people in your industry welcome your appointment, and I look forward to a new broom and things improving myself. I met personally with Sir Roy McNulty and I put to the Secretary of State as well the simple point that our railways cost, some suggest, between 30% to 50% more than continental railways to operate. I put it to the Secretary of State and to Sir Roy that the major difference between their railways and our railways is that they are publicly owned and integrated whereas ours are privately owned and fragmented. You mentioned fragmentation in your introduction. Isn't that one of the fundamental problems that we have? It is fragmented and not an integrated, planned, publicly owned industry.

David Higgins: You are right. The figure has been quoted somewhere between 30% and 40%, and that is before the 22% savings were made in this control period. The other thing is, are we measuring the same things? I am not sure we are. We don't really know what the European railways cost, whether they capitalise maintenance costs, renewals, how they treat interest costs, amortisation, so we can't work it out, but I will accept that it is more expensive to do things here than in Europe, and there are some good reasons why that is the case. Yes, it is more complicated—there is absolutely no doubt about that. We have a complicated railway network through where we are. However, the private sector brings great innovation. If you look at the innovation that has come from West Coast with Virgin, or if you look at what Chiltern Railways are doing on their ideas, they bring a lot of innovation and ideas that you would not get from a single integrated organisation.

Q31   Chair: Can you give us some examples of the innovation?

David Higgins: Sure. Just on timetabling for starters, but also you can look at the ideas of Chiltern in terms of tapping a new market. But I do want to come back to this question of yours of the 40%—

Chair: We would like to know more about the innovation.

David Higgins: Okay, okay.

Chair: The Committee has not always been satisfied that the system has produced innovation. Are there any other examples?

David Higgins: Just let me finish on the 40%. There are—

Chair: No, no. I am asking you a question, please, Mr Higgins. Are there any more examples on innovation?

David Higgins: The Northern Hub is an innovation, isn't it? It is taking an existing network and looking at getting a 50% increase in capacity by doing tactical investment in signalling systems and some upgrades. There are some areas where you can get a lot out of a network by a few—let's take freight. The work we are doing at Nuneaton on freight will allow for catering with the growth only in the line from Felixstowe there. It should have been done generations ago, of course. We have come up with ideas of doing that.

Look at the supply industry, the high output delivery on track renewals and remote monitoring on trains. Europe comes to the UK to look at how we monitor broken rails. If a rail cracks, it is a major safety issue. A train derailment is one of the highest risk issues. But with our technology, our measurement trains, and our helicopters that fly the routes with various technology, Europe comes to work out how we do that.

We are now moving to train­based monitoring on trains themselves that track all the defects in rails. That allows us to intervene on railways before a broken rail happens. The results are there because our broken rail statistics are substantially much better—

Q32   Chair: Those are all innovations that have taken place here in the UK rather than elsewhere?

David Higgins: Yes, they are.

Going back to the 40%, there are a few obvious reasons why it is more expensive to work on the railways here than it is in Europe. When we do capital works here, you have to look at our time to get access to the railways. We did a study on this and it will come out in the McNulty report. What it says is that, when we do capital works here, our input costs aren't higher than in Europe; in many cases they are cheaper. One or two areas are more expensive, such as aggregates. But the big difference is that, when we do an upgrade such as Reading, and we are going to expand Reading, we are only allowed on to the train access to take out the lines for a very, very limited period. In Europe, they take stations out for long periods of time. They take tracks and lines out for considerable periods, because they have a lot more reserve capacity in the network to do that. We can come in at very, very limited periods of time. That is the biggest reason why our capital works projects here, when we deliver the work on the ground, are more expensive.

Yes, our operating costs here of running the network are more expensive. The reason there is that, if over the next 15 years we spend £6 billion and replace the Victorian signalling system we currently have, that will get us to where every European country is today. We have a system here which takes 5,000 people to operate it, and they do an amazing job of keeping a creaking network together. So, yes, it does cost more to operate.

Then with regard to maintenance, to maintain our system is much more expensive because we have a network that was built essentially between the 1850s and the 1870s. We don't have the high-speed network that France, Spain or Germany has. We do not have the commuter network that Paris has—the RER service. We rely on a network that is doing something it was never built for. So, yes, it does cost more to maintain because you have to do a lot more inspections to maintain embankments that were built by entrepreneurs in the Victorian era. We do have to work through those issues. We are never going to solve them completely.

Q33   Kelvin Hopkins: If I can pursue this a little further, there was a report by a group called Catalyst about seven or eight years ago which concluded that under BR, actually, our railways were the most efficient in Europe. They had to be, because they were so desperately underfunded. As Tom Winsor, the former rail regulator, said, "They worked miracles on a pittance", but they actually kept the railways running. Since then, costs have mushroomed. Both fares and the public subsidy have massively increased as a result.

I have many friends inside the industry, on the engineering side, and one of the things they have put to me is that now there is a system of contracting and subcontracting, you get a decision to do a bit of rail work such as track renewal, a main contractor is brought in, a subcontractor, possibly even a further sub-subcontractor, and then a project manager takes the job of employing an engineer on a self­employed basis to do the work. In the past, it would have been dealt with in­house by a permanently employed engineer, who would be in charge of the whole project and within a cash-limited environment. That was much more efficient and much more cost-effective, and of course it cost a lot less for the taxpayer and the fare payer.

David Higgins: I won't enter into the debate about the history of BR. I have heard so many war stories, so I certainly don't want to polarise my first few days in Network Rail.

My whole background is contracting and design, and what the industry has learned is that there are specialist organisations. I worked over here in the late '70s for English contractors. I grew up here on the system, in the old days, where the client would document the reinforcing steel and then send it to the rolling factory that would then roll the steel. Nowadays we have all worked out that that is bizarre, because the organisation best suited to do that is the actual contractor that is laying the steel. They have their technology and the systems and they co­ordinate that in their own organisation, rather than relying on the client doing that.

Traditionally, in British contracting, there were an enormous amount of claims, contracts and waste. That was because of this culture of conflict. The Egan report recognised all that. The new NEC contracts were all an attempt to change an industry which was really disastrous in terms of how it was set up for conflict. Partnering is the answer, but that is not always straightforward. Let's look at track renewals. We now have four world-class organisations that do high-output track renewals. They are all global companies; they operate internationally. They do what we are doing here all around the world. They bring the best technology from around the world. That is something we could never do, but there are benefits and pluses.

To your question, "Can we improve it?", we can substantially improve our process of delivering projects. There is a process in Network Rail called GRIP. I asked the other day where the GRIP process came from, and it came from Winston Churchill when they were doing some mobile pontoons and he said, "Will someone get a grip of this process?" That is how they named it GRIP. But the GRIPs go from 1 to 8. GRIP 5 is when you start digging in the dirt. All the value is created between GRIP 1 and GRIP 3. That is when you think of what you want to do, you review the options, you work out how to procure it, and you finalise design. All the value is lost between GRIP 4 and GRIP 8 because that is when you start building and you think, "My God, they never worked out how this is going to go together."

Chair: I think, Mr Higgins, we are getting into a lot of detail.

Q34   Kelvin Hopkins: I have one more question about costs. Some four or five years ago the Department for Transport held an internal inquiry into why West Coast Main Line cost so much more than East Coast Main Line. They came to the conclusion that project management costs—and this was said by both sides—for West Coast Main Line in the years of privatisation were 50% of the total costs. Don Heath, who masterminded the East Coast modernisation, said that project management costs were 1% because it was integral. This was an internal inquiry by the Department for Transport and it has not been challenged. I have raised this before. There is a massive increase in project management costs rather than direct engineering costs, which is what this really should be about.

David Higgins: I have not seen that report. What I would say is that, if you compare East Coast to West Coast, West Coast is a £10 billion rebuild. If you look at the real cost that was spent on that, £2 billion to £3 billion was spent probably on major enhancements, major new works. A lot of it was renewals—there was a massive amount of renewals. Remember, West Coast is a very different railway line from East Coast. West Coast was built by people who went round a hill if there was one. So it is very circuitous and curved. You had to move whole junctions. East Coast was always built as a much straighter line. East Coast has had nothing like the level of capital upgrade that West Coast has had, and unfortunately, the comparison and results bear that out.

Project management, delivery management costs, 1%: that is a remarkably low figure. I have worked for 10 different companies that have been involved in project management in four countries around the world. That is an extraordinarily low figure.

Q35   Chair: When you spoke before about costs, you referred to the nature of the network of the rail here compared with other parts of Europe. Does that mean that you are rejecting the interim report from Sir Roy McNulty looking at the costs, because he didn't relate it to that?

David Higgins: No, I am certainly not doing that. I believe there are substantial changes. What I am saying is that, if you compare us directly to Europe, you are comparing different networks.

Q36   Chair: But you are not saying that is the sole reason for the higher costs in the UK.

David Higgins: No, but it is an important part of it. We need to look at the trade­offs. We make decisions here all the time which add costs. At the moment we are doing major upgrades through Thameslink. If that was Europe, we would be prepared to take out stations for considerable periods of time and explain to the public, "This is going to be extremely inconvenient, but the result is it will be cheaper and it will be quicker." We need to have that public debate, and we need to challenge that. I have talked to Sir Roy on many occasions and he is fully aware of that. Much of the cost we build into our projects or our decision making is in those first three steps. We need to challenge all those steps and challenge how we go about the work, not how we do it on the ground. We create a lot of cost in how we do projects.

I was down at Farringdon two days ago and I was looking at a tunnel that is 200 metres long and 2 metres in diameter that takes all the signalling. It has to be hand dug. It is like mining. The reason is because of the history. We are leaving all the heritage facade there, which is an interesting decision. The consequences are substantial in terms of how we do that. We are leaving the existing structure. All these decisions have logic. Transport—

Chair: I am sure we will come back to that. I just wanted to clarify that you weren't saying that was the sole reason.

David Higgins: No, not at all.

Q37   Steve Baker: Mr Higgins, you mentioned the need for an increased culture of entrepreneurship. If I may, I would like to ask you three questions about financial incentives, risk taking and then capital investment. First, do you accept the McNulty review's finding that Network Rail is "generally subject to weak financial incentives" and what real incentives do you have to reduce costs?

David Higgins: CP4 is the control period we are in going from 2009 to 2014. The base case of that is taking out £5.2 billion worth of costs from our business. That is on top of the costs that we have taken out in CP3. From an operational point of view, if you put that into the perspective of running the railways, the cost of running the railways, the operations and maintenance costs and renewals, that means a real cost saving of £800 million a year.

As a non­exec director, when I applied for this job, they said, "What is the biggest challenge?" I said, "Hitting CP4." If you want my honest opinion, I think doing it in a sustainable way is going to be incredibly difficult to get it right in such a way that, when you go to CP5, you can take another £2 billion worth out of the cost. We should all remember the target that Network Rail and the rail industry—our suppliers and our partners—have been set in this existing control period, because we have had some windfall benefits. The financial recession, difficult as it has been, has benefited us from cutting inflation, and it has cut the margins of our suppliers and contractors. That is not going to be something we can replicate in the next period.

Q38   Steve Baker: When it comes to entrepreneurship, it seems to me it is mostly about individual employees' creativity, the choices they make, and how they find opportunities to create value and cut costs. What do you plan to do to incentivise individual employees to be more creative?

David Higgins: I probably can't teach anyone at Network Rail anything about the rail industry, I have to be honest, because I am not an expert on it and they are all experts. The only thing I have learned from bitter experience of being a manager is that clear accountability for executives and for teams is really, really important. I believe I can bring an increase in that discipline to Network Rail. You need to be able to be very, very clear about what a business leader has to do and it needs to be clear to them. But if you give them accountability, you have to then give them authority because there is nothing worse than someone being accountable. If you give them authority, they also have to have the resources to do it, the money and the people. Then you have to have a process to make sure they do what they are supposed to do. That is what I call performance management. You have to set clear, basic targets and come back and check they are done at each period. It is just simple management logic and I have used it through years. That is what I intend to strengthen in Network Rail.

Q39   Steve Baker: Moving on to risk taking, within an entrepreneurial culture there is commercial risk taking. The question is, who will bear those commercial risks? It seems to me, that with the taxpayer guaranteeing Network Rail's debt, there is a risk that the firm becomes more entrepreneurial but the taxpayer carries the can if it goes wrong.

In a related question, we know that safety is the top priority, but could you just sketch how you will manage safety-related risks in a more entrepreneurial culture?

David Higgins: With any organisation that relies heavily on taxpayer subsidy, which is what we are—which is the public sector—and provides a public service, the ultimate risk will always be there, and eventually the Government gets caught with that, because in the end we are not a business that can shut the railways: if they break down, we overrun or there is a major blockage, then it is a huge public issue and a very important political issue.

In terms of risk—and I had this in the last job and in the job before—in the end the public sector, as lender of last resort, is always taking risk, all the time. I think, often, the public sector forgets that. It always takes the ultimate risk of failure to perform. What we are obligated to do as Network Rail is to take judgments on that risk. Where do we spend money to get better value? Where do we put money—in improvements or on renewals? We renew 1% to 2% of the track every year. Where should we renew track? Where is the best place from a safety point of view? Which track is most likely to fail? Which is most expensive if it fails? Where is the greatest utilisation?

It is easy running a brand new network. This network is a challenge because you could put money in all areas. Our responsibility is to work with the Department and the regulator to agree, from a safety point of view, where we should be investing the money. The biggest skill is assessment of risk and of asset condition—knowledge of what in the hell we are dealing with. To know about rail quality, for example, we need monitoring. Great improvements were made by things like the measurement train. What a fantastic innovation. But now, why not have 6,000 trains that run on the track every day measuring our train conditions? That is the next step. The more information we have, the quicker we are able to know where to intervene.

Q40   Steve Baker: Finally, it is very good of you to remind us that the railways were built by Victorian entrepreneurs. You said how well 5,000 staff are doing to cope with a creaking, Victorian signalling network.

David Higgins: Correct.

Steve Baker: We are talking about monitoring a very old network. Forgive me because I am not a railway historian, but is it fair to say that the great age of capital investment was that entrepreneurial phase, and if that is the case, what are we going to do with the structure of Network Rail now to recapture that entrepreneurial investment in rail?

David Higgins: It was, of course. I am sure you have heard the 10 times multiple. Canals were 10 times more cost-efficient than travel by road at the time, and rail is 10 times more cost-efficient than travel by canals. It was a fantastic era, of course, and the entrepreneurs built railways to compete with each other. They built three lines to Cambridge over peat bogs and expanding clay platforms, which we still have today. It was a fantastic period, and many of them went broke, as we know, quite famously. It was a very, very important era.

The era now is that we have 50% more people using the rail network in the last 12 years than there were 12 years ago. There was a period of great decline, of course, when railway usage went down dramatically. We carry 100 million tonnes of freight every year. All of our forecasts on freight, particularly big container freight, are going up substantially. Of course, with the price of petrol, the densities of our cities, and carbon, the use of railways is in a whole new era. Our challenge is to do it a lot more cost-effectively now. At Network Rail we need to be much more entrepreneurial and open to ideas from our suppliers, designers and our partners, because we need to use the power of the network and our suppliers to get the best solutions.

In my last job we ran a project. We had 250 people managing it and running an organisation of 12,500 people. But we use the industry for everything.

Steve Baker: I am most grateful.

Q41   Chair: Do the incentives you talk about include the big bonuses for senior management that have been so unpopular?

David Higgins: On the issue of bonuses, first, you will be aware that our Chairman announced a review of all bonuses, which is in the process of consultation now with our members. It is also in the process of consultation with our regulator, the ORR, and the Department, and that will be going back to members in the coming months. What I would say, and I won't shy away from it, is that performance management is absolutely essential to get an organisation to work. Whether it be the workforce on the tools, on the railway lines, or the engineers that won our major projects, there must be cause and effect. I am talking about outperformance. If someone does a good job, outperforms, they should be rewarded. There should be a clear link between performance, but there needs to be transparency. Transparency is essential.

Q42   Chair: Does public hostility to major bonuses for senior managers concern you?

David Higgins: I am not tone deaf to the public concern about bonuses in this environment.

Q43   Chair: What does that mean? Does it concern you?

David Higgins: Yes, it does. Neither is senior management tone deaf to the public concern, but we do need to have a culture and environment where we do pay for performance.

Q44   Gavin Shuker: Crewe, Manchester, Clapham, Warrington, Barking, Preston, Luton, Liverpool, Wigan and Stockport: what links those places?

David Higgins: That is a real challenge. I am never any good at these things.

Chair: You don't have to answer quizzes, Mr Higgins.

David Higgins: I don't know. Is it the railway?

Kwasi Kwarteng: It's got something to do with it.

Gavin Shuker: I believe the term is "touché". No, they are the 10 worst stations in the country. Why won't Network Rail take that issue seriously?

David Higgins: I didn't know that, I have to say. So this is customer performance?

Q45   Gavin Shuker: The Better Stations report, if this helps, recommended that we should spend a considerable more amount of money on category B railway stations and named those as the 10 worst stations in the country. The previous Government identified a programme of £50 million to spend on those. Network Rail rolled over very quickly after the coalition Government—

David Higgins: Now I am aware of what you are talking about; correct, that's right.

Gavin Shuker: My question is, is Network Rail taking that issue seriously?

David Higgins: You are obviously aware that in a request from the Government at the time of the CSR we released £50 million worth of savings by stopping a programme on some station upgrades, which, if I remember, had been started by Lord Adonis. Is that right?

Gavin Shuker: That's right.

David Higgins: Obviously, we work with our Department in the end, and the regulator. They tell us where they want to spend their money. That was a programme that they initiated, and in the end it is their right to tell us to stop. We will look at those stations. I can come back to you on what our plans are to upgrade those stations. Having returned that money to the Government, I can see what our next plans are.

Q46   Gavin Shuker: Do you think that passengers should be concerned that you are not bringing forward plans at this stage, nine or 10 months after cancelling the programme, to upgrade the 10 worst railway stations in the country?

David Higgins: I will come back and write to you and say what we are doing. Passenger Focus is very important. We monitor our customer response closely to make sure that we are responsive to those. I am concerned why they were put in the category in the first place, but I will come back on that.

Q47   Gavin Shuker: Finally, I am concerned that you don't appear to be fully briefed on that particular issue. What I would ask, though, is are you aware, within the construct of greater retail space, of the greater revenue-raising opportunity, which other members of the Committee have raised, that the Better Stations report said would be released by an upgrade of those stations?

David Higgins: I will look at that particular report. I am all for releasing value and I have already started working on one or two station opportunities with a major private developer already to see if we can release some value on existing stations, but if there are opportunities we will look at them.

Gavin Shuker: Thank you. We will appreciate you writing to us.

Q48   Kwasi Kwarteng: I would like to ask you a question which stems from questions that my colleagues have asked. Mr Shuker referred to the structure of Network Rail and the Chair referred to your bonuses. This seems to me to come to something that is fundamentally at the heart of your dilemma. On the one hand, you talk the language of a businessman in the private sector, talking about entrepreneurial culture, talking about getting a better return on your assets, and defending quite lavish bonuses, or the idea of bonuses, but on the other hand you talk of yourself as a public sector organisation, jealously looking after the interests of the taxpayer and looking at value for money. Mr Hopkins has gone, but his view is that it should be a public entity, and other people's view is that your function should be essentially just given to the actual operators. I want to know what your view is on that dilemma. Where do you see yourself maybe in five years' time as an institution? Will you be fully nationalised? Is that something you want to do, or would you like to divest your function to private sector operators? It seems to me that the problem the public have is that you are neither fish nor fowl. You are neither a private business, giving yourself big bonuses, nor are you a public business. That is why people are very angry about big bonuses and things like that.

David Higgins: It would be very heroic of me, within four weeks into the job, to give my opinion on the structure of Network Rail. Of course we are in the middle, so I don't have a position which I would be prepared to state publicly. I have not even made up my own mind where it is, and ultimately it is not my decision anyway. Ultimately, it is a decision for Government and Ministers who are elected by the public.

Q49   Kwasi Kwarteng: But, with respect, you have a wide experience in the industry. Have you never thought about what the optimal structure for Network Rail would be?

Chair: You were non­executive director, were you not? So you are not really new to this at all.

David Higgins: No, indeed. The very, very first thing that I have done within weeks of getting in, as I say, is that we are going to devolve authority and we are going to work much closer with our train operating and freight operating partners to find solutions. The biggest blockage today is the way that our contracts are written. So we have already started a process with a number of those operators, saying, "When the new franchising comes up, can we have a much more flexible approach to that?" I think we can achieve many of the benefits in our current entity.

As to the issue of bonuses and performance, I don't think there is a conflict. I don't think there is a problem with an organisation that is paid by taxpayers paying bonuses. I had this debate when I first came to the Olympics. I remember going to the first Minister and the various Treasury officials and I said, "We can take this two ways. We can either pay all of our people here in this organisation standard salaries, departmental salaries, and then we can go outside, as we often do, and hire extremely expensive consultants, investment banks, major consulting companies, programme management companies and contractors, and pay them an enormous amount of money, but they will take no accountability and no risk and they won't report to you, and the people we hire who manage them are going to have rings run round them. Or we can hire the people that we are going to hire"—because they are going to hire the same people that we can hire—"at a substantially reduced cost than the private sector will hire them and have them manage the private sector." That is what we did.

I went out and hired a combination of people—50:50 public and private sector. I hired the best private sector people I could have, who the private sector were going to hire and then sell to me. I had them manage the private sector, and the results, I think, are clear now, and we paid bonuses. But I said to the Government, "If we are going to do that and we are going to attract these people off the street"—they will take risk; I take risk in this job—"we are going to have to be prepared to pay them for performance."

But the issue in all this and why everyone is confused is that it comes down, in the end, to transparency. In my last job I was paid a very substantial bonus, but it was pretty transparent whether we succeeded or not. The objectives were very, very clear, and in the end the press made a meal of it for one day or a one­liner, but it didn't get a lot of traction, because there was a lot of transparency about everything we did—we operated in a goldfish bowl, frankly. I am a strong believer in transparency. I can't say it any clearer than that.

Q50   Kwasi Kwarteng: If someone asked you why there was such a public outcry about the bonuses last year, you would say that was because there was no transparency. You don't think the fact that you are a national company whose principal money is coming from the Treasury had anything to do with the outcry about the bonuses.

David Higgins: There are lots of companies today that are owned by the Government that pay very, very substantial bonuses.

Q51   Kwasi Kwarteng: Yes, but they are cutting back. Even with the BBC, I was reading something about Jeremy Paxman's salary. There is a wide perception that under this current economic climate people are cutting back on these lavish payments.

David Higgins: That is right. The issue with everyone is that it must be very clear what they had to do to get that—it wasn't just coming to work and getting a large bonus for doing something they were being paid for anyway. They were being paid for outperformance.

On the Olympics, when I started the project in mid-2006, the experts gave written reports and said, "It can't possibly be finished a year ahead of schedule. It is impossible to do." That was what all the experts said. We said, "If we do that, is that seen as outperformance?" They said, "Yeah, that would be outperformance because we don't think it can possibly be done." Are the objectives, whether it be the BBC or a bank or ourselves, in this case equally as clear as that, so that the public can say, "Yeah, we grudgingly get this. They have outperformed"?

To me, our only way at Network Rail of dealing with that is to be a lot more open about how we deal with the public, how we set our objectives and how bonuses are reviewed. I am all for openness and transparency. I have lived with that for the last eight years. Most of my life was in the private sector, with eight years in the public sector. I have been subject to all the scrutiny of public sector accountability and information that has come with my last two jobs, and I welcome that.

Q52   Mr Leech: Can I just return briefly to the restructuring and the regional centres? How long will this restructuring take, how much is it going to cost and what impact will it have on jobs?

David Higgins: We are not going to have a line called "restructuring" in our accounts, which is often the trick that happens with these things. That is not going to be a cost.

How long will it take? We are starting with two areas. We are starting with Scotland and Wessex, and we are doing that because they are relatively self­contained. They are operating well, we have good partners in those areas there and our performance is good. So that is why we are starting on those. We are going to have a hybrid organisation for a period of time, and during that time, on these first pilots, we need to make sure all our systems and control, our safety case and our asset management, is such that we can then extend it across the organisation. What I am not going to do is put at risk the network, safety or performance. How long? Eighteen months.

Q53   Mr Leech: You are saying there is no cost implication for that at all?

David Higgins: There will be no additional cost for carrying this out. We will eventually get efficiency gains. I am not saying in CP4 we are going to make substantial new savings. The main thing I am looking to do is to set up Network Rail for control period 5. We need to have a much more efficient, quicker, more agile organisation that works with our partners in a much better way as the new franchises come into force.

Q54   Mr Leech: What about jobs? What impact will it have on the number of staff?

David Higgins: In terms of our staff, we have a gradual process of reduction in staff in our organisation. We also have a substantial increase in our current control period. Our renewals go up fairly substantially in the last two to three years. Also, our enhancements, our major projects division, grow substantially as well as big projects like Thameslink gets under way.

Q55   Mr Leech: But with regard to the actual restructuring itself, I assume, going to nine regional areas, there are expected to be some savings in terms of staff costs.

David Higgins: There will be changes. There will be changes in our organisation. There will be new people coming in, too, because that is the way to bring in entrepreneurial behaviour. We have put ads out now for a new managing director. So there will be changes. Some people will leave by natural attrition and some people will need to be hired.

Q56   Mr Leech: You seem a bit reluctant to suggest that there will be an overall reduction in head count.

David Higgins: Traditionally, with restructuring, you draw a line and declare a large loss, because you are saying, "This restructuring is going to cost a lot of money." You fire a lot of people and then you say, "But trust us, in 18 months' time things are going to be fine." You write back the losses over that period, and then, hopefully, the company recovers. We are not doing that. This process is going to be more organic in the organisation, because we can't afford to put at risk all the gains. We are in the middle of a control period. We have to get £5 billion out of this business, so I can't afford to have our organisation caught in the headlights and to stop doing what they are currently doing. They have to keep on doing everything they are currently doing and get all the savings out of it so it is not going to be a big disruption to our organisation.

Q57   Mr Leech: Would you imagine, though, in the long term you will have fewer middle managers and senior managers, and perhaps more people on the ground, or fewer people on the ground and the same number of middle managers and senior managers?

David Higgins: Longer term we will have less people on the railway. The whole idea of putting in more technology means we will have less people. But our great challenge for our railway is that we have an ageing workforce. That is one of our biggest challenges. People keep this system going as it is currently worked because they know the history of the place, so we've got to be less reliant on that. We have to build, whether it is new technology, or we have to train a whole new generation that can operate the system.

Q58   Chair: How are you going to maintain your priority on safety, which you spoke about before, and, in particular, stop a repeat of the cover­up of accidents on rail?

David Higgins: If you look at the last 10 years, substantial progress has been made on safety. If you look at—

Q59   Chair: Yes, it has. But this issue of non­declaration, non­reporting of accidents, is now a key issue. How are you going to deal with the issue of safety and proper reporting of accidents, given the reductions in costs and the changes that you are going to bring about? How can you assure us that that is indeed going to be a priority?

David Higgins: The non­reporting related to RIDDORs on construction—that is a part of our network and it is very, very important. But the biggest safety risks relate to running the train network, so running the train system and the infrastructure. As for RIDDORs, they are important; they are an indicator. Our RIDDOR has been going up for the last six months, which is good, because that is getting us to our current RIDDOR rate. This is a three­day reportable accident—if someone gets hurt and they are off for three days away from work. Our indices at the moment are 0.22. Where does that sit? It is about what Terminal 5 was when it finished, which is best practice. It is where the Olympics are today.

An indicator as itself is just an indicator. The point on safety is, "What in the hell are you going to do about it?" The issue on safety is behavioural safety. Much of our challenges on accidents come from our supply chain. We need to work much much closer with our contractors and suppliers, but we also need to start at front-line supervisor level. My experience of this over many years is that you need to train and educate the front-line supervisors in behavioural safety. Get leadership from the top absolutely right, but sometimes targets distort behaviour. We have to take away any targets that distort reporting because it is only in reporting three­day accidents or, even more importantly, near misses, which are actually a much more important element to get reported, that we are going to understand what the risks are that we need to eliminate.

Q60   Chair: That will still be there in the restructuring you are doing?

David Higgins: Absolutely.

Q61   Chair: That will be high priority?

David Higgins: It is a high priority of myself.

Q62   Kwasi Kwarteng: I am interested in your relationship with the train operating companies, because McNulty pointed out that there was mistrust between the train operators and Network Rail. What would you say to someone who suggested that there is no need for Network Rail to do what it is doing at the moment, that train operating companies should be running the tracks and the signalling as well, and that your role should be downscaled? What would you say to someone who said that?

David Higgins: I would say I am open to train operators taking a greater role. Merseyrail have been interested in taking a greater role in terms of infrastructure. Fine, I am open to that. The challenge is that I have not talked yet to a train operating company that wants to take over Network Rail or take the full risk, because you've got to remember when things go wrong the train operator needs to put their balance sheet at force majeure risk, tested to destruction, to carry out that work. I am not sure that any train operator today wants the capital risk of that.

Q63   Kwasi Kwarteng: But do you see the benefits of train operating companies running tracks and signalling, or perhaps even running railway stations?

David Higgins: They do today.

Kwasi Kwarteng: Yes, but could you describe—

David Higgins: Absolutely. I think there is great benefit in train operating companies running stations. I think there is even more benefit in them doing long­term maintenance and upgrades on them. They can do it in areas that suit the customers; they can perhaps do it cheaper than us. Of course, absolutely, I have no issues with that whatsoever. But the fundamental thing is that we run a very complex, ageing network where, with asset management knowledge after nine years of intensive work, we are only getting up the learning curve. Everything we have learned in the last nine years has only made us smarter. There is a huge amount to go. If we lost what we have learned in nine years, we would have to be crazy.

Q64   Chair: How are you going to find the £185 million additional efficiency savings?

David Higgins: Which efficiency savings are those?

Chair: The £185 million identified in the spending review.

David Higgins: That is through a combination of capital works and some of our renewals programmes. Internally, we have identified where those areas are.

Q65   Chair: What involvement have you had in the discussions taking place on structural change of the rail industry?

David Higgins: Extensive. We have been extensively involved with the Department and the regulator, and of course we have inputted into the McNulty review. I don't think there is any concern that we haven't been consulted on that. In fact, I know Sir Roy McNulty well from my past jobs, so I am sure we have plenty of access to make our points.

Q66   Chair: Have you been discussing the future of rail itself with Ministers?

David Higgins: Yes. There are a lot of working groups, and a lot of outside consultants that have come in and done various studies in this stage of it. So, yes, they have talked about where rail fits, the role of operators, wide­ranging topics.

Q67   Chair: What points have you been putting?

David Higgins: I think it is up to McNulty. He is about to report this month. I think it would be presumptuous of me to try and pre-empt what Sir Roy is going to say.

Chair: I am not asking you to pre-empt what he is saying. I am asking you what you have been saying.

David Higgins: What we have been saying? We have inputted into various consulting reports. I have not been in many of those reports myself personally but we have put in lots of reports. I just don't think it is in any way constructive to give small parts. Ultimately, it is a report which the industry needs to own, which we will welcome and implement. It is a matter of weeks away now and I am sure he will come and present to your Committee here. I leave it to Roy to communicate his own findings.

Q68   Chair: But what about outside the McNulty report? There is a ministerial working party, isn't there, looking at the whole future of the industry?

David Higgins: There is a working party at a director level of the Department, including ATOC—the Association of Train Operating Companies—the regulator, and myself. I have sat on the first of those meetings. That is looking at a wide range of topics but it has drawn no conclusions yet.

Q69   Chair: Are you going to make cuts in the capital programme or in any other part of the programme to meet those spending review targets?

David Higgins: No, we are not changing any outcomes. We will look at efficiency gains, besides the earlier statement about the £50 million on the station upgrades.

Q70   Gavin Shuker: On a slightly separate note, when will Network Rail be subject to freedom of information?

David Higgins: That is a decision for Ministers, and I think it is on hold until after the value for money and the White Paper that comes out at the end of this calendar year. Ultimately, it is not a decision of Network Rail, but it is a decision that the Government and Ministers need to make. If they so do it, I welcome it. I have operated under FOI for years and I don't have any problem with it at all.

Q71   Steve Baker: As Dr Kwarteng said, neither fish nor fowl, neither public nor private; subsidy, taxpayer guarantees, heavy regulation.

David Higgins: The best of both worlds.

Q72   Steve Baker: Marvellous. In such a world, is it possible that we actually overproduce rail transport?

David Higgins: Sorry, that we overproduce?

Steve Baker: Is it possible that we subsidise it to such a degree that people make choices to travel by rail that they otherwise wouldn't make?

David Higgins: It is a very valid point. I think greater transparency and greater cost allocation to route will open that issue up for debate. That is very important. In some cases, absolutely not, and we could not keep up with demand on the commuter network coming into London. In other areas, the level of public subsidy is very substantial. Whether that is proper value for money and whether the public and politicians want to do that, it is up to them to make that decision. But you need the information.

Q73   Steve Baker: With that in mind, I am conscious that high-speed rail is likely to serve the top quintile of the income range. What is your view on high-speed rail?

David Higgins: Why get into that debate? I suppose all I would say is, forget about the speed—this is an interesting debate—and think about capacity, because within six to 10 years West Coast is full, even with other trains. You know the only way then to cope with demand is that they should just push the prices up. That is the challenge. We have the challenge now. You look at Thameslink. It is a great project. Thameslink is absolutely undersold. What it will do for the commuters from Bedford through to Brighton is fantastic. Do you know why it was called Thameslink 2000? Because it was supposed to be finished in 2000, but it is going to be finished in 2018. That is because successive groups, Governments, you name, put it off. Do you know when the first study was done on Crossrail? It was in 1990. That is when it was supposed to start.

Steve Baker: I must just say I am extremely grateful to Mr Higgins for reminding us that Government projects with grand ambitions often slip.

Q74   Chair: But they are happening, aren't they?

David Higgins: They are happening. They are fantastic. No one understands the change that Thameslink will deliver to London commuters. It will take the pressure off the Northern Line. It is a fantastically complex project. I was down there the other week going through it all. At London Bridge the signalling is just amazing. In peak hours, through that channel, you get one to two trains an hour. That will move to 24 trains an hour when it is fully implemented. It will just change commuter patterns.

Chair: Are there any further questions from anyone? Thank you very much, Mr Higgins, for answering our questions and we look forward to questioning you again on rail matters. Thank you very much.


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2011
Prepared 11 April 2011