5 Ministry of Defence Budget
Comprehensive Spending Review
2010
191. The 2010 Comprehensive Spending Review (CSR)
ran alongside the development of the SDSR. As part of the SDSR,
the MoD undertook some 40 individual studies which were tailored
to three scenarioszero
real growth and cuts of 10% and 20%.[191]
The MoD's settlement was
that defence spending in 2014-15 would be 1.8% higher in cash
terms than in 2010-11, but 7.8% lower in real terms.[192]
The total defence budget over the four years of the CSR was set
at:
Data Source:
HM Treasury, Spending Review 2010, Cm 7942
192. The CSR stated that "by focusing on
maintaining key operational capabilities and by cutting out waste
and inefficiency in the defence budget, the MoD will make at least
£4.3 billion of non frontline savings over the Spending Review
period".[193]
193. During our inquiry, Ministers commented
that it was not possible to agree to funding levels outside the
current CSR period and that this caused problems in planning for
Future Force 2020, which to be achieved would require real terms
funding increases from 2015 onwards (see paragraphs 174-190 above).
Therefore planning in the MoD was being based on a flat rate level
of funding from 2015. The MoD recognised that this created a difficulty
in planning. In his report on Defence Acquisition, Bernard Gray,
now the MoD's Chief of Defence Materiel, recommended that the
MoD should move to a 10 year rolling budget which should be enshrined
in law, in line with the French model, and it should encompass
manpower, estates, equipment and support funding.[194]
The previous Government did not accept this proposal but committed
that the equipment
programme would be planned to a longer time frame "with a
ten year indicative planning horizon for equipment spending with
the Treasury".[195]
194. Our predecessor Committee welcomed the commitment
to a ten year planning timeframe for defence expenditure but doubted
that the proposed ten year planning horizon would provide sufficient
certainty to stabilise the equipment programme.[196]
195. During our earlier inquiry into the processes
followed in the SDSR process, the Secretary of State for Defence
commented that:[197]
Moving to a ten-year current spending horizon [...]
makes a good deal more sense for defence. This is different from
most departments; our acquisition programmes tend to be much longer
lines and a ten-year budget would help us.
196. Bernard Gray, giving evidence to this inquiry
in his new role as Chief of Defence Materiel, reaffirmed his view
regarding ten year budgets for the MoD:[198]
Personally, my view is that Defence is significantly
different from many other Departments, most of which exist with
their cash flowing within a year or thereabouts. If they have
capital programmes, they are relatively small compared with oursnotwithstanding
Transport, which is still significantly smaller than the MoD for
these purposes.
My personal view is that it would give greater stability
to the planning of defence if we were able to give the long-term
certainty that we arekind ofdiscussing here. We
could then say, "Okay, what is the financial planning horizon
and how do we map against it?" That would allow us to plan,
and indeed order, with greater certainty than the current Whitehall
structure gives us. You must ask the Treasury for their opinion,
but clearly they tend to be reluctant to have their hands tied
in such matters.
He noted that the Treasury might respond:[199]
I suppose, to argue their case for them, they might
say, "Well, economic conditions could be significantly different
in 2015 and we should respond to those circumstances at the time.
It might create unfortunate precedents, with everyone else arguing
that we should be setting 10-year budgets." There are arguments
on their side, but my personal view is that it would be an advantage
and a useful discipline on all sides. But I am one individual.
197. We agree with our predecessor Committee
that the scale and nature of MoD contracts is quantitatively and
qualitatively different from other Government procurement and
its assertion that greater financial stability could help to control
and reduce the hundreds of millions of pounds of unproductive
costs which are incurred annually to keep the equipment programme
spend within each year's budget. We recommend that the MoD and
the Treasury should establish mechanisms for a ten year budget
for the MoD. It is vital that the MoD has greater certainty of
resources as it plans to implement Future Force 2020 which is
essential to the nation's security in an ever-changing world.
Over-commitment in the MoD Budget
198. The National Audit Office's Major Projects
Report 2009, published in December 2009, made the following observations:[200]
The Defence programme is unaffordable
2.3 The Equipment Examination and subsequent Planning
Round were successful in reducing the Defence budget's forecast
overspend by £15 billion. The Department estimate, however,
that the Defence budget remains over committed by £6 billion
over the next ten years; this assumes an annual increase of 2.7
per cent in their budget after the end of the current Comprehensive
Spending Review settlement in 2010-11. If the Defence budget remains
flat in cash terms after this time, then the extent of the over
commitment widens to £36 billion. In either case the budget
remains consistently unaffordable over the next ten years.
2.4 Until there is a comprehensive review of defence
policy, it will be difficult for the Department to think radically
and rationalise the programme whilst limiting the impact on military
capability. The Equipment Examination has also enabled the Department
to shift some spending from future military requirements to support
current.
199. In the SDSR, the Government stated:[201]
2.D.3 The legacy of over-commitment in the Defence
programme amounted to around £38 billion. Some £20 billion
of this is related to unaffordable plans for new equipment and
support. Cancelling or changing major contracts to tackle this
problem itself creates further liabilities. Negotiation with industry
will reduce these as much as possible, but they will still make
the short-term financial challenge greater.
2.D.4 In addition, there are systemic pressures in
the two key blocks of Defence expenditureequipment and
personnel. [...]
2.D.5 This legacy of unaffordability, and these systemic
pressures, mean that a major focus of work in the Strategic Defence
and Security Review has been to eliminate over-commitment, to
the greatest extent possible by reducing running costs to allow
resources to be focussed on the front line.
one of the stated main objectives
of the SDSR was to bring defence policy, plans, commitments and
resources back into balance and establish an affordable defence
programme going forward.
200. We asked the MoD to set out how it had calculated
its estimate of a £38 billion over- commitment in the defence
programme and the effect of the SDSR in resolving it. In response,
the MoD stated:[202]
The gap in the Defence Budget is the estimated difference
between the cost of the Defence programme and the MoD budget under
the assumption that the budget would rise in line with inflation
over the ten years 2011-12 to 2020-21. The figures are based on
a number of assumptions including changes in fuel prices, foreign
exchange rates, and Armed Forces pay awards. It will, therefore,
change over time. A figure of £38bn was calculated before
the SDSR. The SDSR announced substantial reductions to the planned
force structure. The measures announced go a long way to eliminating
this excess but it will take time to work through the consequences
of the SDSR decisions and bring the Defence Budget back into balance.
[...]
The SDSR established the policy framework for our
Armed Forces and the capabilities that they will need to meet
future challenges and achieve success on future operations while
safeguarding Afghanistan. The spending review set out the resources
allocated to Defence for the implementation of the SDSR. This
will enable us to bring Defence policy, plans, commitments and
resources into better balance through our annual planning process.
The outcomes of the SDSR and the Spending Review
form the basis of the Department's annual Planning Round (PR11),
which is still ongoing. The Planning Round looks out over 10 years.
This process involves updating the estimated costs of the Department's
current activities and adjusting for the estimated costs and savings
arising from the changes announced in the SDSR. Until this process
is complete it is not possible to reliably estimate the size of
any residual shortfall. The Planning Round process routinely re-prioritises
the Defence programme to ensure that the Department lives within
its budget. PR11 is expected to conclude in spring 2011.
201. During our inquiry we explored the Government's
assertion of a £38 billion gap in the defence budget and
how this figure was arrived at and the degree to which it was
based on actual commitments and how much was aspirational. Professor
Malcolm Chalmers from RUSI stated:[203]
I think the key thing here is that it really does
depend on the assumptions you are making [...] Even in a space
of a few months, if the oil price goes up by $30 or $40 a barrel
and everything else is left unchanged in your assumptions then
you will probably have several billion pounds extra in your gap
over the next 10 years. My plea would be that we need a lot more
transparency on the assumptions being made in these numbers if
we are to understand what they mean. The Government, when they
came in last year, ordered a fresh look at our forward commitments
and introduced what they felt to be more realistic assumptions
in that forum. They came up with this £38 billion figure.
It will be interesting to see what the figure is today, after
a defence review, on the same assumptions.
Clearly, the assumptions will change, as we have
more information, so my assessmentI have published thisis
that if you take the same assumptions that underlay the £38
billion then we probably reduce that overhang over the next decade
to something of the order of £15 billion. But, of course,
some of those assumptions might changeservice pay or equipment
costs might rise less rapidly than we anticipatedso it
does depend on that.
202. In March 2011, we explored this further
with the Secretary of State for Defence.[204]
In response, he promised us a note which would set out various
pieces of information concerning the MoD budget over-commitment.
We were disappointed with the response we received particularly
as the Secretary of State had made a public commitment to provide
the information.[205]
We wrote again to the Secretary of State on 8 June requesting
the following information on the MoD's budget:
- A breakdown of expenditure
approved at 'initial' and 'main' gate, including contract costs
and running costs;
- A breakdown of running costs
such as Service Pay;
- Details of the remaining budget
gap; and
- Details of the PR 11 settlement.
203. A response was received on 7 July which
did provide some additional information but was still not as comprehensive
as we would have expected.[206]
As part of the response the MoD told us that the "gap was
substantially in excess of £38 billion":[207]
However, this figure merely provides a snapshot based
on the Department's understanding of the programme at a particular
time. There are things that are now better understood, which had
we known them at the time, would have affected the analysis of
the position, and which indicate that in fact the genuine size
of the gap was substantially in excess of £38 billion. For
example, Bernard Gray's report in October 2009 had identified
that a range of equipment programmes had not been accurately costed.
Since coming into post as the Chief of Defence Materiel, and reviewing
the equipment programme, Bernard has judged that a further £5.5
billion should be added to the overall cost of the equipment programme.
In addition, the £38 billion figure did not take into account
the fact that the MoD will now be meeting the full cost of paying
for the successor deterrent, which is estimated at £8 billion
over the next ten years, and for which at that time no part of
Government had assumed they would pay.
204. We were disappointed by the MoD's response
to our requests for a breakdown of the MoD's financial commitments,
including details of the components of its estimate of a £38
billion gap in the defence programme and the size of any remaining
budget gap after the SDSR. We note that the MoD now state the
genuine size of the gap is substantially in excess of £38
billion. However, we also note the Secretary of State's assertion
that the "for the first time in a generation, the MoD will
have brought its plans and budget broadly into balance, allowing
it to plan with confidence for the delivery of the future equipment
programme". Without proper detailed figures neither statement
can be verified. Given the difficulties the MoD has had in responding
to our requests for a breakdown of the over-commitment in the
MoD budget, we expect the Government in its response to this Report
to set out in detail the basis for these statements.
205. We note the Secretary of State for Defence's
commitment to carry out an assessment of the affordability of
the equipment programme alongside an independent audit by the
NAO. We are surprised that this assessment has not yet begun and
expect to receive a timetable for this exercise in response to
this Report.
MAJOR PROJECTS REVIEW BOARD
206. On 22 February 2011, during a speech on
value for money in the MoD, the Secretary of State for Defence
announced the establishment of a Major Projects Review Board.
The Board would be chaired by the Defence Secretary and would
receive quarterly updates on the MoD's major programmes to ensure
that they are on time and within budget. This would begin with
the 20 biggest projects by value and will expand to the 50 biggest
projects. The Board met for the first time on 13 June 2011. Following
the meeting, the MoD asserted that:[208]
Any project that the Board decided was failing would
be publicly 'named and shamed'. This could include a project that
is running over budget or behind expected timelines. This will
allow the public and the market to judge how well the MoD and
industry are doing in supporting the Armed Forces and offering
taxpayers value for money."
207. We welcome the establishment of the Major
Projects Review Board. The Board faces a major challenge and we
will monitor its effectiveness in ensuring the MoD's programmes
are on time and within budget. We recommend that the MoD consider
the appointment of suitably experienced independent members to
the Board.
Defence Reform
208. In parallel with the SDSR process, the Government
also announced in summer 2010 that it would conduct a full organisational
review of the Ministry of Defence. The Review had two strands:
structural reform to reorganise the MoD into three pillars: Strategy
and Policy, Armed Forces, and Procurement and Estates; and a "cultural
shift" towards a leaner and less centralised organisation
combined with devolved processes which carry greater accountability
and transparency. The scope of the Defence Reform review was wide
ranging and examined in detail all major areas of defence.
209. To oversee implementation, a Defence Reform
Unit was established within the MoD to help plan and execute any
structural/organisational changes. The Defence Reform Unit's report
was published on 27 June 2011.[209]
The Report made 53 wide-ranging recommendations. According to
Lord Levene of Portsoken who chaired the review, the key recommendations
were:
- create a new and smaller Defence
Board chaired by the Defence Secretary to strengthen top level
decision making;
- clarify the responsibilities
of senior leaders, including the Permanent Secretary and the Chief
of the Defence Staff, to strengthen individual accountability;
- make the Head Office smaller
and more strategic, to make high level balance of investment decisions,
set strategic direction and a strong corporate framework, and
hold to account;
- focus the Service Chiefs on
running their Service and empower them to perform their role effectively,
with greater freedom to manage, as part of a much clearer framework
of financial accountability and control;
- strengthen financial and performance
management throughout the Department to ensure that future plans
are affordable and that everyone owns their share of responsibility
for this;
- create a 4 star-led Joint Forces
Command, to strengthen the focus on joint enablers and on joint
warfare development;
- create single, coherent Defence
Infrastructure and Defence Business Services organisations, to
ensure enabling services are delivered efficiently, effectively
and professionally;
- manage and use senior military
and civilian personnel more effectively, with people staying in
post for longer, and more transparent and joint career management.
210. An implementation plan setting out how the
Defence Reform Unit's review would be delivered is expected to
be published in September 2011, with a view to overall implementation
being completed by April 2015.[210]
211. We welcome the empowering of the single
Service Chiefs, but are concerned that removing them from the
Defence Board may result in an increase in the tensions between
the three Services and encourage individual Service Chiefs to
fight for their particular Service without consideration of overall
defence requirements. It means that the Chief of Defence Staff
will be the only Service representative on the Board, and could
in turn leave them open to accusations of favouritism of their
"home" Service over the others, whether justified or
not. We intend to return to the command, control and accountability
processes between the Chiefs of Staff in future inquiries. We
will monitor the impact of this and the other reforms recommended
by the DRU over the coming months as they are implemented. In
addition we look forward to seeing in the near future greater
detail from the MoD as to the budgetary implications of the changes
being made.
212. We recognise the pace and quantity of
change occurring within the MoD is considerable and understand
how disconcerting this has been for the Armed Forces and MoD civil
servants, particularly at a time when UK Armed Forces are conducting
two major campaigns in Afghanistan and Libya. While we recognise
that reform of the MoD is long overdue, change on this scale requires
exceptionally careful management. In response to this Report we
require that the MoD inform us of how it will ensure that reform
is not derailed by the speed of its implementation. We note the
recent publication of the Defence Reform Unit Report and will
monitor the implementation of its recommendations. The MoD should
provide updates on work to implement the recommendations in its
Annual Report.
191 Defence Committee, First Report of Session 2010-11,
The Strategic Defence and Security Review, HC 345, para
16, Q 11 and Q 16 Back
192
Adjusted using the OBR November 2010 forecast GDP deflator. House
of Commons Library Research Paper 11/10, UK Defence and Security
Policy: A New Approach, January 2011, p 28 Back
193
HM Treasury, Spending Review 2010, Cm 7942,October 2010,
para 2.84 Back
194
Bernard Gray, Review of Acquisition for the Secretary of State
for Defence, October 2009, p 10 Back
195
HC Deb, 15 October 2009, col 35WS Back
196
Defence Committee, Sixth Report of Session 2009-10, Defence
Equipment 2010, HC 99, paras 84-86 Back
197
Defence Committee, First Report of Session 2010-11, The Strategic
Defence and Security Review, HC 345, Q 62 Back
198
Q 548 Back
199
Q 550 Back
200
National Audit Office, Ministry of Defence: Major Projects
Report 2009, December 2009, HC 85-I, paras 2.3-2.4 Back
201
HM Government, Securing Britain in an Age of Uncertainty: The
Strategic Defence and Security Review, Cm 7948, paras 2.D.3-2.D.5 Back
202
Ev 126 Back
203
Q 42 [Professor Malcolm Chalmers]. Also see Ev 121. Back
204
Qq 128-149 Back
205
Ev 136 Back
206
Ev 156-158 Back
207
Ev 157 Back
208
"MoD's Major Projects Review Board stands up", Ministry
of Defence press notice, 13 June 2011 Back
209
Defence Reform Steering Group, Defence Reform: An independent
report into the structure and management of the Ministry of Defence,
June 2011 Back
210
Ministry of Defence, Business Plan 2011-15, May 2011, p
13 Back
|