Memorandum submitted by Alex Henney, EEE
Ltd
A SENSIBLE COMMERCIAL FRAMEWORK FOR NUCLEAR
POWER
SUMMARY
There has been much wheel spinning (and in the case
of the Renewable Obligation substantial waste of customers' money)
considering how to meld expensive low carbon plant into a market.
There should be a clear understanding that nuclear power
plants (and windmills) are not being developed for economic reasonsthey
are manifestly not economic compared with gas plantsbut
to meet government environmental policy. Consequently the energy
market as an investment mechanism is not a relevant consideration.
The financial risk of such plant should not be increased by exposing
them to irrelevant risks; rather the aim should be to insulate
their revenue from market price risk, and furthermore to minimise
the cost of capital.
The British government has a long and lamentable
history of incompetence in dealing with nuclear power, which has
led to wasting many tens of £billions. It should learn from
practice in other jurisdictions, notably Ontario and Georgia,
where there are significant nuclear developments:
- In Ontario the Bruce Power A nuclear plant is
being refurbished at a cost of Can$5.25 billion. The power is
being paid Can$63/MWh indexed by the Consumer Price Index. The
developer assumes the construction and availability risk. The
post-tax weighted average cost of capital (WACC) is reported as
being in a range 10.6% to 13.8% nominal. The contract is open
book to the Ontario Power Authority.
- Georgia Power Company (GPC) is the developer
and has a 45.7% share in the ownership of the Westinghouse AP1000
Vogtle 3 and 4 units (the other owners are municipal entities).
The construction cost of the contract is $9.8 billion while including
interest during construction the cost is estimated at $14 billion.
GPC's share of the plant is being built against a price approved
by the Public Service Commission of Georgia, and the cost will
be included in the rate base and allowed a WACC of 7.8% nominal
post-tax. The price is based on an Engineering Procurement Construction
contract, and the amount allowed in the ratebase will be subject
to a performance bonus/penalty. The contract is open book to the
Commission, who have recruited an experienced nuclear engineer
to assist with the formalized monitoring procedure. In December
2010 the Commission authorized expenditure of $1 billion on GPC's
share of the work so far. As of the first week in March both the
company and the Commission expressed satisfaction with the arrangements
Common features of both schemes is that they insulate
the plants' revenue from any market; they have open-book contracts;
and the resulting output is "blended" with other electricity.
In the Energy Market Review DECC set its face against
a regulated asset base approach for reasons that hold little water.
Unfortunately DECC officials do not appear aware that GPC's costs
(and costs of thermal plant in California) are incorporated into
the asset base on a regulated base. Mr. Atherton of Citigroup
reported to the Committee that EDF will be seeking a post-tax
nominal return of 10.5% (and other developers may seek more).
According to Citi Investment Research's model, using a construction
cost of 3200/kW (which is in line with EDF's claim of £9
billion for 3300MW) and their other assumptions, the resulting
cost of nuclear power would be £74/MWh. With the 7.8%
return of the Georgia Power financial framework, the resulting
cost of nuclear power would be £56/MWh, which is 24%
lower and allows significant cost overrun yet still leaves the
customers ahead.
It thus seems to me to make eminent sense to eschew
talk of markets and their imagined disciplines (particularly as
we have destroyed ours), but rather to follow the approach adopted
in Georgia. Plant should be developed to an agreed cost based
on Engineering Procurement Construction contracts which are open
book to the relevant authority (which may be the government or
Ofgem or a special agency set up for the purpose) and subject
to expert monitoring review, with a performance payment/penalty
at the margin. The cost would be the regulatory asset base on
which the company would earn an appropriatebut modestreturn.
The resulting electricity would be blended with other electricity.
A DISASTROUS HISTORY
WITH NUCLEAR
POWER
The British government has a lamentable track record
of incompetence and wasting taxpayers money in dealing with nuclear
power, which I set out in detail in "The Economic Failure
of Nuclear Power in Great Britain";[34]
"A study of the privatisation of the electricity supply industry
in England & Wales";[35]
and "The British electric industry 1990-2010: the rise and
demise of competition".[36]
The economics of the Magnox reactors were fudged; most of the
AGR programme was an economic disaster; the Sizewell Inquiry was
intellectually fraudulent, if not downright dishonest; Sizewell
B cost 40% more than estimate and was written down by £800
million for the sale of British Energy. Following the debacle
of the withdrawal from the privatisation of the nuclear power
stations in November 1989 the House of Commons Energy Committee
conducted an inquiry into "The Cost of Nuclear Power"[37]
because:
"After years of official assurances that nuclear
power was (or could be) the cheapest form of electricity generation,
Parliament and the public are entitled to know why it was only
when faced with the commercial discipline of life in the private
sector that nuclear power (from both existing and proposed reactors)
suddenly became an expensive form of generation
we believe
the Department of Energy, as the CEGB's sponsoring department,
must share the blame for this, since it apparently made no attempt
to obtain realistic costings from the CEGB until it was seeking
to privatise nuclear power
The manner in which the Department
has supervised the CEGB over the years can only be described as
inadequate."
By the early 1990s it had cost the British taxpayer
and electricity customers more than £10 billion (in 2010
prices) in research and development and about £50 billion
in capital expenditure, with another nearly £4½ billion
for Sizewell B.[38]
Then came about £7.5 billion for the nuclear levy in the
1990s, then the government devised an unwise approach for British
Energy to pay for decommissioning, which contributed to its demise.
On top of this is a bill of an undiscounted cost of discharging
all future civil nuclear liabilities conservatively estimated
at about £100 billion.[39]
This is an awesome bill for "electrical energy in homes that
is too cheap to meter."[40]
If the British government is going to mess again
with nuclear power it behoves it to get its act together properly.
In particular it should learn from others.
NUCLEAR DEVELOPMENT
AND THE
CONCERN ABOUT
PRICE RISK
Over recent years there has been much discussion
about how to facilitate financially the development of nuclear
power plants because of the power price risk, see exhibit.

Source: Newbery.[41]
In addition to the obvious point that the lower the
gas price which drives the electricity price the less favourable
is the economics of nuclear, the graph also brings out the volatility
of gas and electricity price which are closely linked. Although
gas (and coal) plant are automatically hedged against the volatility,
as Professor Newbery has pointed out, nuclear is not:
"The price of electricity in the forward market
moves very closely with the cost of generating using either gas
or coal, allowing for the cost of CO2 required for each. Although
the prices of gas, coal, CO2 and electricity are separately highly
volatile, (gas prices have fluctuated between 20p/th and 110p/th
and coal has fluctuated from $50-200/ton between 2004-08) the
forward clean spark spread and the forward dark green spread have
remained far more stable. The reason is simple, the price of electricity
is set by the cost of generating using the marginal fuel and the
CO2 price moves to equate the marginal costs (including the EUA
cost) of coal and gas. Companies with fossil generation are therefore
naturally hedged against fluctuations in the input and output
prices, while low-C electricity, whether renewables or nuclear,
is exposed to the full volatility of the electricity price, as
its variable costs are low, predictable and stable."
The potential price risk to nuclear plant in a gas
price driven market was more than adequately shown by the demise
of British Energy in September 2002 following the collapse of
prices that began in the winter of 2000-01. The wish to mitigate
price risk has led to proposals for a carbon floor price and now
in the government's Energy Market Review a contract-for-differences.[42]
But in my view much of the discussion has been misplaced because
it has started from the stance that the nuclear plants should
operate within the framework of the market. Part of this storyline
is that exposure to the market price provides the conventional
incentives to construct and operate the plant efficiently.
In my opinion this approach is fundamentally flawed
and results in a higher cost of capital than needs be, and consequently
a higher cost of electricity. This has been illustrated by the
Renewables Obligation, which was a case example of an ill judged,
complex and expensive scheme based on ersatz market principles.
The starting point should in my view be that nuclear power
plants (and windmills) are not being developed for economic reasonsthey
are manifestly not economic compared with gas plantsbut
to meet government environmental policy. Consequently the energy
market as an investment mechanism is not a relevant consideration.
The financial risk of such plant should not be increased by exposing
them to irrelevant risks; rather the aim should be to insulate
their revenue from market price risk, and furthermore to minimise
the cost of capital. This approach has been adopted for both
the renovation of the Bruce Power A plant in Ontario, and for
the development of the Vogtle 3 and 4 units by Georgia Power Company
in the US.
THE ONTARIO
APPROACH TO
FINANCING A
LARGE NUCLEAR
REFURBISHMENT
In 2005 the Ontario government announced that it
has reached an agreement with the owners of Bruce Power A to refurbish
the plant for a cost of Can$4.25 billion. Subsequently in 2007
the agreement was extended to extend the refurbishment for an
additional Can$1bn, resulting in a total investment of approximately
Can$5.25 billion. In return, the provincial government, through
the Ontario Power Authority (which is guaranteed by the provincial
government), agreed through a contract-for-differences to pay
an initial price for electricity of Can$63/MWh as of the date
the Refurbishment Agreement was signed. This price is indexed
by the Consumer Price Index. The Can$63/MWh is the only income
the generator receives; consequently the plant owner bears both
the construction risk and the availability risk.
According to the Office of the Auditor General of
Ontario "Bruce Power and the Ministry agreed to an 'open-book'
process, and the Ministry was given access to a data room containing
confidential documents provided by Bruce to support the refurbishment
plans, supplemented by management presentations, facility site
visits, and meetings with relevant government agencies".[43]
The weighted average cost of capital (WACC) was a post-tax return
in the range of 10.6% to 13.8% nominal.
THE VOGTLE
3 AND 4 REACTORS
IN THE
US
The US Department of Energy is offering a loan guarantee
to up to four nuclear plants in order to help pump prime development.[44]
The loan guarantee reduces the cost of development by lowering
the cost of debt, but is not by itself a critical factor in underpinning
development.
The first scheme for which conditional[45]
loan financing of $8.3 billion covering 70% of the construction
cost has been agreed for the Vogtle 3 and 4 Westinghouse AP1000
reactors with a total capacity of 2200MW in Georgia which is being
developed by Georgia Power Company, an investor owned utility.
It is taking a 45.7% share of the scheme and is the agent for
development on behalf of the other owners, who are municipally
supported generation production and supply entities. The construction
cost of the scheme is $9.8 billion ($4500/kW); the cost including
financing is $14 billion. The loan guarantee effectively reduces
Georgia Power's cost of borrowing by $15-20 million p.a.
Georgia Power will incorporate its share of the construction
cost of the plant in its rate base, where it will represent an
increase of about 34% of the current rate base (the financing
charges during development are paid off as incurred). When the
plants are operating their costs will be blended with the other
generation costs together with transmission and distribution costs
to construct the tariffs in the traditional US manner for a vertically
integrated utilitythere is little or no market based input.
The Public Service Commission has certified a sum of $6.11 billion
for Georgia Power's share of the plant including the interest
incurred during construction ($6080/kW) based on an Engineering
Procurement Construction contract for the plant which is described
as price defined turnkey contracts with Westinghouse and architect/engineer
Stone & Wesbter. (Stone & Webster is a subsidiary of the
Shaw Group, which also has a 20% interest in Westinghouse; Toshiba
has a 65% interest). In December 2010 the Commission authorized
expenditure of about $1 billion for Georgia Power's expenditure
thus far (representing about half of total expenditure) on procurement
of long lead time items; excavation and preparation of foundations,
and construction of buildings. The contract has provisions that
share cost overrun between the contractor and the company. Although
this is the first AP1000 built in the US it is benefiting from
the experience of the three AP1000s being built in China which
have similar nuclear islands and are three years in advance. There
is extensive interaction between people in Georgia and in China.
The staff of the Public Service Commission proposed
an incentive scheme for the company consisting of a bandwidth
of +$250 million. If the in service cost of the project
is less than the lower threshold, then the Company could earn
an incentive return of 10 basis points in the return on common
equity for every $100 million the in-service cost is less than
the lower threshold of the bandwidth. If the completed cost of
the project is more than the upper threshold, then the return
on common equity would be reduced by 10 basis points for every
$100 million the completed cost is over the upper threshold of
the bandwidth. The company objected to this, and the Commission
upheld it and asked the company to see if they could negotiate
a mutually agreeable incentive scheme. The negotiation is still
in progress, but is hoped it will be concluded by the end of March
2011.
The Public Service Commission has appointed an experienced
ex-Westinghouse consultant to monitor performance with an allowed
annual cost of $600,000. The Public Service Commission requires
a Construction Monitoring Report every six months that includes
actual expenditures for the January-June and July-December periods
together with a narrative of activities and a forecast of expectation
of final project cost. It must also include an analysis to show
whether it is cost effective to move forward. Costs are certified
in the subsequent 180 day period if deemed prudent. The contract
is open book to the Public Service Commission.
There is no target load factor in the contract, and
so at first sight the ratepayers assume all of the load factor
performance risk. But the company has a performance based ratemaking
scheme with a target allowed return on equity of 11¼% pre-tax
nominal and a deadband of +1% within which the company earns what
it earns. If the company earns over 12¼% in a year it keeps
1/3 of the earnings and returns 2/3 to customers; if it earns
less than 10¼% it can request a filing to raise tariffs.
Thus since the plant will represent about a third of the company's
rate base its operating availability will have a noticeable impact
on the company's profitabilitythus implicitly there is
a link between plant availability and company profitability.
The company's capital structure is approximately
43% debt; 10% preferred; and 47% equity; its cost of debt is about
5.8%; its cost of preferred stock is about 6.1%; its allowed pre-tax
return on equity is 10¼-11¼% so its post-tax WACC is
about 7.8% nominal.
As of the beginning of March 2011 discussion with
officials of Georgia Power Company and the Public Service Commission
found satisfaction both with the arrangements in place and the
progress on the plant.
THE FOREIGN
LESSONS FOR
A COMMERCIAL
FRAMEWORK FOR
NUCLEAR
In both Ontario and Georgia the market price risk
is removed from the developer. In Ontario the construction and
availability risk remain entirely with the developer, while in
Georgia the developer bears some of the construction risk at the
margin through a profit incentive scheme, and the company has
an incentive to achieve a good level of availability through its
general performance based ratemaking scheme. The Georgia approach
results in a lower WACC (8.1% cfr 10.6% to 13.8% for Bruce Power).
The Energy Market Reform Consultation paper argues
against the Georgia approach, which is effectively a regulated
asset base (RAB), commenting "It would represent the most
fundamental change to the current arrangements of all the options;
making such a radical change would be high risk. Moving to a RAB
system would require the Government to sacrifice all market benefits
and competitive pressures for greater efficiency, optimal operation
and innovation that could be retained under other options considered
as part of this project. The generation sectorwhere competition
is viable and a key feature of the current marketis different
to the natural monopoly market for the provision of transmission
and distribution networks. As such, the Government does not consider
this an attractive option for reform" (p66). The paper
also argues that "the approach transfers construction risk,
which generators are better able to manage, to customers."
In my opinion this rejection is not a soundly based
regarding nuclear plants:
- 1. It is not at all obvious that this approach
would in fact "sacrifice all market benefits" because
those of optimal operation can be retained by a suitable contract
structure.
- 2. Innovation in nuclear design is a slow
process pioneered by manufacturers working for an international
market and subject to an elaborate licencing process; it is not
influenced by the British power market.
- 3. I do no consider that "competition
is viable and a key feature of the current market." With
(i) the development of the complexities and economic distortions
of NETA/BETTA; (ii) the vertical and horizontal consolidation
of the industry into an oligopoly; (iii) the lack of liquidity
in the contract market; (iv) the subsidies for renewables and
quasi-planning for so much wind/4 CCS plants/possibly nuclear,
the market long ago lost the semblance of competitiveness. It
is overdue time we gave up the pretence that we have much of a
generation market, let alone a competitive one, and recognize
that flooding it with subsidized windmills, nuclear plants and
CCS plants will destroy it entirely.
- 4. The claim that the approach transfers
construction risk is a statement of hope, rather than of realization
which will depend upon the eventual CfDs. It is perhaps noteworthy
that not so long ago EDF Energy was claiming that it could bear
the market price risk. Then it wanted a carbon floor price to
mitigate part of the market price risk; now with a CfD it has
probably got rid of the market price risk. Will it negotiate to
the wire, then say that in the light of the cost overruns of the
two EPRs being built,[46]
it needs help with construction cost risk? Then as the government
increased the ROCs for offshore windmills to get the London Array
going, it requires little imagination to work out the government's
response.
- 5. The 7.8% of Georgia Power's development
of the Vogtle 3 and 4 plants compares with the 10.5% that Mr.
Atherton reported EDF as seeking. (Other developers may seek moreDECC's
consultant (Redpoint) assumes an 11.2% hurdle rate for a nuclear
plant with a CfD). According to Citi Investment Research's model,
using a construction cost of 3200/kW (which is in line with
EDF's claim of £9 billion for 3300MW) and their other assumptions,
the resulting cost of nuclear power would be £74/MWh.
With the 7.8% return of the Georgia Power financial framework,
the resulting cost of nuclear power would be £56/MWh,
which is 24% lower and allows significant cost overrun yet still
leaves the customers ahead.
DECC's lack of understanding of the issue was perhaps
shown by a presentation on 3 March at the Policy Exchange which
included a slide which stated that nowhere was plant investment
based on a regulated asset basethis view is wrong (see
my submission "Capacity markets and reliability options").[47]
EDF definitely, and perhaps other nuclear developers,
have the government over a barrel if it seriously wants the development
of nuclear plants. It thus seems to me to make eminent sense to
follow the approach adopted in Georgia. Plant should be developed
to an agreed cost based on Engineering Procurement Construction
contracts which are open book to the relevant authority (which
may be the government or Ofgem or a special agency set up for
the purpose) and subject to expert monitoring review, with a performance
payment/penalty at the margin. The cost would be the regulatory
asset base on which the company would earn an appropriatebut
modestreturn. The resulting electricity would be blended
with other electricity.
March 2011
34 The Economic Failure of Nuclear Power in Great Britain,
Alex Henney, Greenpeace, 1989. Back
35
The privatisation of the electricity supply industry in England
& Wales, Alex Henney, published by EEE Limited, 1994. Back
36
The British electric industry 1990-2010: the rise and demise of
competition, Alex Henney, published by EEE Limited, 2011. Back
37
The Cost of Nuclear Power, Volume I, Energy Committee, Fourth
Report, Session 1989-90, HC205-II, HMSO, 7 June 1990. Back
38
In addition to the shambles over "conventional" reactors,
in current prices we wasted several tens of £bns on the fast
breeder reactor and on the Thorp reprocessing plant. Back
39
The assessment was provided by Professor Gordon MacKerron, former
chairman of the Committee on Radioactive Waste Management, in
an e-mail to Alex Henney dated 16/12/2010. Back
40
Admiral Lewis L Strauss, first chairman of the US Atomic Energy
Commission, 16 September 1954. Back
41
A Nuclear Future? UK government policy and the role of the market,
David Newbery, paper presented to the Beesley Lectures on Regulation
in London, 22 October 2009. Back
42
This is misleadingly referred to as a FIT CfD-presumably the "FIT"
part of the term is supposed be a semantic sop to the terminology
in the Conservative election manifesto. Back
43
Special Review for the Minister of Energy, Office of the Auditor
General,
http://www.auditor.on.ca/en/reports_en/brucespecial_en.pdf. Back
44
The Energy Policy Act of 2005 provides a number of incentives
for "Innovative Technologies" which apply to "advanced
nuclear energy facilities, including a loan guarantee for up to
80% of eligible project costs, http://www.ne.doe.gov/energypolicyact2005/neepact2a.html. Back
45
The guarantee is conditional upon the Nuclear Regulatory Commission
licensing the plant, which is expected late this year. Back
46
The performance of the two European schemes being built highlight
construction cost risk:
- The 1600MW Finnish EPR (European
Pressurised Water Reactor) being built by Areva at Olkiluoto is
four years behind its original target commissioning in 2009 and
the construction cost has increased from 3 billion in 2003
money to 5.7 billion (3,600 or $4,600/kW). Areva NP
is claiming compensation of about 1 billion for alleged
failures of Teollisuuden Voima Oy (TVO). TVO, in a January 2009
counterclaim, is demanding 2.4 billion in compensation from
Areva NP for delays in the project (Agence France Presse, "Setbacks
Plague Finland's French-built Reactor," 30 January 2009)
- In May 2006 EDF estimated that the
construction cost of its EPR at Flamanville would be 3.5
billion. Two years later An Areva official suggested that the
cost will be at least 4.5 billion, although it was not specified
whether this was an overnight cost (Nucleonics Week, "Areva
Official Says Costs for New EPR Rising, Exceeding $6.5 billion,"
4 September 2008, p. 1) Back
47
I provided DECC in August 2010 with a paper which clearly explained
in some detail that in the California energy market thermal generators
are being built to a return on a regulated asset base, and is
Georgia Power investment in Vogtle 3 and 4, "A multiclient
project on developing trading arrangements for a windy electric
industry", Alex Henney, EEE Ltd, July 2010. Back
|