2 Future risks to value for money
12. The Department and the NHS expect to spend a
further £4.3 billion on the delivery of care records systems
by 2015-16.[40] This
estimate assumes that the Department will manage to reduce the
cost of the CSC contracts to deliver systems in the North, Midlands
and East by at least £500 million, which it is currently
negotiating with CSC. These negotiations began in November 2009
but have not yet been concluded. CSC accepted that the contract
renegotiations were necessary because the contract as it stands
is not working for either the NHS or for CSC.[41]
The Government has also initiated a review of the Programme by
the Major Projects Authority, the joint Cabinet Office-Treasury
body which oversees large public sector projects. The Prime Minister
has stated that no new contract can be concluded with CSC until
this review is completed.[42]
13. To achieve a reduction in the value of the CSC
contract of at least £500 million, the Department will have
to agree a substantial reduction in the number of systems to be
provided under the contract and in the functionality that they
will provide.[43] This
revised contract is being considered even though the Department
believes CSC to be in breach of contract.[44]
CSC reported that the focus of its negotiations with the Department
had not been around terminating the contract but had focused on
moving forward with the delivery of systems.[45]
The Department stated that if it was to terminate the CSC contract
it could be exposed to a higher cost than the cost of completing
the contract as it stands.[46]
14. To secure greater clinical support for the systems,
the Department undertook an engagement exercise with clinicians
in 2008 asking them what they wanted from their IT systems in
the acute care setting.[47]
This review identified five clinical areas of functionality and
certain departmental systems, such as maternity or A&E, as
being the minimum specification that would be acceptable to clinicians.[48]
The original vision will not be delivered and the Department is
now focused on delivering these five areas of functionality from
a 'menu of modules' which enables each NHS acute trust to select
those aspects of the system they need most.[49]
The Department is therefore funding the development of modules
which may not be taken by all acute trusts within the Programme
and is now creating a patchwork system which builds upon trusts'
existing systems.[50]
15. One of the key aims of the Programme was to avoid
each NHS organisation procuring its own system. The Programme
had originally been set up to address these issues, but organisations
within the Programme are now tailoring systems locally with different
levels of functionality being provided, and the many NHS organisations
now outside the Programme are again responsible for procuring
their own systems.[51]
16. The Department believes that its compromise of
a 'networked' approach of locally tailored systems will still
enable the Programme's aims to be achieved, but it has no means
by which to ensure interoperability between locally procured systems
and those delivered through the Programme.[52]
This approach, however, will require trusts outside the Programme
to fund the development of their own systems at a time when they
are being asked to make significant efficiency savings.[53]
The Department stated that it had made no assessment of the costs
to trusts outside the Programme of developing their own systems.[54]
In effect, some trusts will be getting systems that cost £31
million through the Programme, while others may or may not be
in a position to fund the development of their systems to the
same extent.[55] The
Department told us it did not expect differences in the funding
and development of systems to lead to any noticeable differences
in service from the patient perspective.[56]
17. The contracts for delivering care records systems
expire in 2015-16, by which time the strategic health authorities
that are responsible for the local delivery of systems will no
longer exist.[57] The
risks will transfer to individual NHS trusts.[58]
With all trusts expected to become foundation trusts responsible
for their own governance, the Department stated that it would
be difficult to shift management of the contracts into that environment.
It anticipated that, as an interim step, a body similar to Connecting
for Health would be created to manage the transition.[59]
18. It is not clear what implications the forthcoming
health reforms will have on how care records system will be managed
and governed in future, and who will take over from Connecting
for Health.[60] Those
NHS organisations receiving systems through the Programme currently
have no direct contractual relationship with the providers or
the subcontractors supplying care records systems.[61]
There is also considerable uncertainty about the mechanism for
transferring services from the Programme to new suppliers, and
in particular whether the costs of doing so will be prohibitive.
This could mean trusts will in effect be tied to using the system
they have taken through the Programme.[62]
40 Q 111 Back
41
Qq 60, 42-44, 208, 315 Back
42
Q 285; HC Deb, 11 May 2011, col 1163 Back
43
Qq 41-48 Back
44
Qq 310-313 Back
45
Q 41 Back
46
Qq 234-235 Back
47
Qq 130, 315 Back
48
Q153 Back
49
Qq 155, 315 Back
50
Qq 221-222, 291, 300 Back
51
Qq 214, 306 Back
52
Qq 212, 270, 298 Back
53
Q 288 Back
54
Qq 291-295 Back
55
Qq 286, 292, 296, 299 Back
56
Qq 213-219 Back
57
Qq 257-258 Back
58
Q 259 Back
59
Qq 262-265 Back
60
Qq 262-265, 273 Back
61
Q 242 Back
62
Qq 231, 316 Back
|