High Speed Rail - Transport Committee Contents


Written evidence from the Chiltern Ridges HS2 Action Group (HSR 46)

1.  This note is specifically directed to paragraph 6 (Impact) of the issues to be addressed by the Transport Select Committee (TSC) and in particular subparagraph 2 of paragraph 6 as follows.

Are environmental costs and benefits (including in relation to noise) correctly accounted for in the business case?

2.  Given that, on the recommendations of HS2 Limited, following their own recommended terms of reference,* on which the consultation paper on HS2 is based, HS2 Ltd indicate that there was no real alternative to avoiding the Chilterns AONB, the Committee are requested to examine in particular why the policies laid down in Planning Policy Statement 7 (PPS7) were not included within the terms of reference and why DfT accepted those recommended terms of reference** without requiring PPS7 to be included and taken into account or why DfT itself did not take them into account. More importantly, with particular reference environmental costs and implications, the Committee are further requested to consider the implications had the consideration of PPS7, a required public policy, been an absolute requirement of HS2Ltd's terms of reference, as it should have been, and why the policies laid down in PPS7 were not reported on or formed part of HS2 Limited's deliberations or of DfT's subsequent report and recommendations.

3.  PLANNING POLICY STATEMENT 7—SUSTAINABLE DEVELOPMENT IN RURAL AREAS

The following paragraphs from PPS7 are relevant in this respect

Nationally designated areas

21.  Nationally designated areas comprising National Parks, the Broads, the New Forest Heritage Area and Areas of Outstanding Natural Beauty (AONB), have been confirmed by the Government as having the highest status of protection in relation to landscape and scenic beauty. The conservation of the natural beauty of the landscape and countryside should therefore be given great weight in planning policies and development control decisions in these areas. The conservation of wildlife and the cultural heritage are important considerations in all these areas. They are a specific purpose for National Parks, where they should also be given great weight in planning policies and development control decisions. As well as reflecting these priorities, planning policies in LDDs and where appropriate, RSS, should also support suitably located and designed development necessary to facilitate the economic and social well- being of these designated areas and their communities, including the provision of adequate housing to meet identified local needs.

22.  Major developments should not take place in these designated areas, except in exceptional circumstances. This policy includes major development proposals that raise issues of national significance. Because of the serious impact that major developments may have on these areas of natural beauty, and taking account of the recreational opportunities that they provide, applications for all such developments should be subject to the most rigorous examination. Major development proposals should be demonstrated to be in the public interest before being allowed to proceed. Consideration of such applications should therefore include an assessment of:

(i)  the need for the development, including in terms of any national considerations, and the impact of permitting it, or refusing it, upon the local economy;

(ii)  the cost of, and scope for, developing elsewhere outside the designated area,or meeting the need for it in some other way; and

(iii)  any detrimental effect on the environment, the landscape and recreational opportunities, and the extent to which that could be moderated.

23.  Planning authorities should ensure that any planning permission granted for major developments in these designated areas should be carried out to high environmental standards through the application of appropriate conditions where necessary.

     This is also repeated in the Development Management Policies:

     Policy NE8: (taken from the draft Policy Statement for March 2010 entitled "Planning for a Natural and Healthy Environment") Policy principles guiding the determination of applications in relation to the natural environment;

     NE8.5 Nationally designated areas, comprising National Parks, the Broads; and

     AONBs, have the highest status of protection in relation to landscape and scenic beauty. The conservation of the natural beauty of these designated areas should be given great weight in planning policies and decisions. In National Parks and the Broads, their wildlife and cultural heritage should also be given great weight, whilst in AONBs they are important considerations. Planning permission for major developments should be refused except in exceptional circumstances. Major development proposals should be demonstrated to be in the public interest and subject to the most rigorous examination. Consideration of such applications should include an assessment of:

(i)  the need for the development, including in terms of any national considerations, and the impact of permitting it, or refusing it, upon the local economy;

(ii)  the cost of, and scope for, developing elsewhere outside the designated area, or meeting the need for it in some other way; and

(iii)  any detrimental effect on the environment, the landscape and recreational opportunities, and the extent to which that could be moderated.

     NE8.6 Planning permissions granted for major developments in nationally designated areas should be carried out to high environmental standards through the use of conditions where necessary.

4.  These policies reflect Government policy in implementation of the statutory protection measures of the provisions on Countryside and Rights of Way Act 2000 which reinforced the protection which already applied to Areas of Outstanding Beauty (AONB) and accordingly all Government Departments including DfT and HS2 Ltd, are subject to and are required to comply with this Public Policy Statement and the principles set out therein. These therefore applied for the purposes of examining and reporting on the High Speed Rail proposals and on the alternatives.

5.  Despite this, when HS2 Ltd established its terms of reference, including its absolute requirements,* and when DfT responded to and accepted those suggested terms of reference,** PPS7 was never included or referred to, let alone included as one of the absolute requirements - indeed the other required elements virtually excluded proper consideration of PPS7—so that the environmental implications involved in breaching and violating, in a material way, the protective principles for the AONB, including in particular those affecting the Chilterns AONB, were never, or were not able to be, properly considered or taken in to account in the context of the PPS7 requirements.

6.  It is submitted that was not appropriate for DfT or HS2 to ignore, and not take into account those requirements, and, even if it might have been considered that HS2 was in the public interest, it was not appropriate for HS2 Ltd or DfT to decide that this was the case, as PPS7 requires this to be rigorously examined and clearly demonstrated and, in any event, also requires careful examination of the cost of, and scope for, developing elsewhere outside the designated area, or meeting the need for it in some other way. It is only Parliament that can decide, after detailed consideration of the issues and an assessment of the possible alternatives that, notwithstanding the other factors, such a project as HS2 is in the national interest.

7.  Instead, HS2 Ltd set itself, and DfT had accepted, a brief which assumed the need for high speed rail as a new line without reference to the requirements of PPS7, which should itself have been one of the absolute requirements, but with, instead, an absolute requirement to provide an interchange with convenient access to Heathrow* which meant that, for this to be feasible, there was no realistic alternative but to breach the principles of PPS7 and cut through some part of the AONB. However there is now no commitment to create a high speed link to Heathrow as part of the consultation although a spur link is indicated a possibility. Furthermore, the value benefit of time saving claimed as justification for the high speed requirement has now been accepted as not valid given the increasing use of technology on the trains themselves during a journey. Thus the business case and claimed cost benefit put forward by DfT falls away once it was (grudgingly) admitted that time on the train can be and is now used productively, which meant that the predication for this preferred route was not relevant, so that any justification for breach of PPS7, by passing through the protected AONB, has been undermined and PPS7 now more than ever calls for detailed consideration of the alternatives.

8.  From the outset, there was therefore a conflict in the HS2 Ltd Brief, which limited and indeed prevented them from considering the alternatives as required by PPS 7. However, whilst DfT separately considered this, it was not done in the context of PPS7 either. And whilst they did nevertheless examine the alternatives, which in turn offered the ability to address the incremental passenger traffic problems, particularly those arising before the HS2 project would be completed, and also addressed the projected increases over time, all at considerable lower financial and more importantly considerably less environmental cost, all these have been subsumed to the DfT requirement for a newly built HS2 line, notwithstanding the potential financial and environmental cost benefits offered by the alternatives.

9.  It is true that other routes were considered by HS2 Ltd, but they were only considered by them as alternative High Speed lines, not in the context of PPS7, but in the context of the DfT requirements for a new line and the then required element of a high speed link to Heathrow, notwithstanding that this is now deferred and not now considered to be critical, so that all this coloured the alternatives, which were rejected mainly on financial and other grounds not related to the requirements of PPS7. In particular therefore neither HS2 Ltd nor DfT fully examined the real implications and costs involved in moderating the detrimental effect of the proposals in the AONB. Thus, for example, the question that appears not to have been asked or addressed is that, if the new line had to go through the AONB, how would the environmental cost of tunnelling right through the whole of the AONB, in order to seek not to breach the principles of PPS7, affect the overall cost and therefore the consideration of the preferred route as against the alternatives? Indeed, in this respect, HS2 Ltd have already admitted that they materially miscalculated the amount of spoil to be extracted, including because they calculated the tunnel spoil on the basis of a single bore not a twin tunnel. All this therefore affects the environmental costs which the TSC intends to examine.

10.   It is submitted that, in this respect, cost is not the only determining factor, except to the extent that, if the cost of HS2 through any route is prohibitive, or non commercial, then it should not be allowed to proceed at all in its currently projected form, particularly as there are other realistic alternatives which are themselves capable of further improvement to meet and address all the projected incremental rail transport requirements at a considerably lower overall cost.

11.   In terms of the accounting for the environmental cost and implications, there is separately a further concern about the lack of an environmental impact assessment (EIA) as part of the consultation exercise, as there are a number of additional matters which this will address and which are not part of the current consultation exercise, nor is there currently any relevant information as to the extent to which this will impact on the environmental costs The DfT claims that these issue are included as part of the Appraisal of Sustainability (AoS) as currently issued, but this Appraisal directs itself much more generally to the wider range of sustainability issues than the specific environmental impact issues that an EIA would address and therefore only in part considers these issues. Thus for example, noise contours and noise implications (a factor specifically mentioned in subparagraph 6) are not considered in the context of a full environmental impact assessment, The problem here is that, whilst DfT accepts that this assessment will be required pursuant to the Environmental Impact Assessment Directive (85/337/EEC), it only intends to produce the Environmental Impact Assessment (EIA) later on, as part of the Hybrid bill process. This will therefore be well after the current consultation will have been concluded, so that it will not have been possible for those consulted to have responded to or taken that information, and the environmental costs and implications, into account and these will undoubtedly prove to have been material factors to have considered as part of the overall consultation, particularly in relation to the overall environmental costs and implications. This is of concern to a number of bodies including the Chilterns AONB and the National Trust, in particular. Indeed the National Trust has already expressed the view to DfT and HS2 Ltd that, in their view, the Government should stop the consultation until the detailed environmental assessment and mitigation measures are made available. The Transport Select Committee is accordingly requested to make enquiries regarding the EIA and its likely impact and to consider recommending that the consultation process should be extended to enable the effect of any EIA and the environmental costs and implications to be considered as part of the current consultation process, particularly bearing in mind the commitment to an produce an EIA in any event.

12.  In relation to environmental cost, given that the Article 2 of the Strategic Environmental Assessment (SEA) Directive applies to plans and programmes subject to preparation at national, regional or local levels and which are required by legislative, regulatory or administrative provisions, the TSC is also asked to consider, separately in this respect, whether, given the regulatory requirements of PPS7 and the statutory protection of AONB, an SEA is required in any event pursuant to such Directive and, if so, what additional environmental cost and implications would result from complying with the requirements of any such SEA, in addition to the EIA as outlined above. Equally important is the timing of the same, given, in particular, that DfT have accepted that, as a minimum an EIA will be required. The problem is that whilst this EIA will inevitably throw up substantial additional environmental costs and implications, many of which could well be critical, the current position is that, apart from the very limited AoS environmental information, none of this will have been taken into account or responded to as part of the main public consultation and, given the now substantially undermined business case, these factors could well have finally tipped the overall balance against this current HS2 project.

May 2011


 
previous page contents next page


© Parliamentary copyright 2011
Prepared 8 November 2011