4 Minimising the number and impact
of events on our roads
Road and street works
35. There are two types of road repair works:
those carried out by the highway authorities, who have a duty
to maintain their roads under Part 4 of the Highways Act 1980;
and those carried out by public utilities and cable companies,
which have to comply with the New Roads and Street Works Act 1991.
When the 1991 Act was passed, only a few utilitiesmany
of which were only recently out of the public sectorwere
allowed to dig up the road; when the Traffic Management Act 2004
was introduced, the number of companies had grown, especially
in the telecoms sector. At the same time major programmes of mains
replacement and leakage reduction were under way in the gas and
water sectors. The TMA was, in part, a response to both the increasing
number of companies and to the increasing frequency of their works.
Parts 3 and 4 of the TMA give highway authorities greater powers
to improve coordination of works and to minimise unnecessary disruption
caused by poorly-planned works. Authorities have more control
over where and when works can and cannot take place; they can
put in place longer embargoes to protect streets that are repeatedly
dug up; and they have greater enforcement powers.
36. Witnesses did not call for more road and
street works legislation, but wanted scope to improve the way
existing legislation is used. The TMA requires local authorities
to co-ordinate various works on streets and, under Section 60
of the TMA, utilities are legally obliged to co-operate with local
authorities.[61] John
Pettigrew of National Grid told us there was "a spectrum
of implementation across local authorities", with different
authorities applying the law in different and sometimes inconsistent
ways, "which makes our ability to minimise the impact on
congestion more difficult".[62]
Roger Culpin, of the Joint Authorities Group, said that "communication
is the key" between local authorities and utilities companies,
to ensure they work together to minimise congestion.[63]
There are currently examples of best practice being disseminated
by different groups. The Greater London Authority's evidence described
TfL's development of "incentives for works promoters to apply
best practice and reduce the amount of time they spend digging
up roads and/or disruption traffic".[64]
National Grid outlined its work in sharing best practice:
We share best practice with companies across the
industry, through regional Highway Authorities and Utilities Committee
(HAUC) conferences and National Joint Utilities Groups (NJUGs)
Street Works Forums. We are fully supportive of NJUG's submission
to this inquiry.[65]
NJUG's written evidence described its Annual NJUG
Awards, which "provide examples of best practice, which are
converted into case studies and shared across industry"[66]
and highlights its work with other groups in sharing best practice:
NJUG has driven a number of voluntary initiatives
delivering real benefits through a step-change in the quality
and impact of street works, including improved safety, quality,
sustainability, communication and reduced disruption, as well
as extensive sharing of best practice.[67]
37. Useful work is being undertaken
to develop and promote good practice in minimising the number
and impact of road and street works. We recommend that the DfT,
working with the Highway Authorities and Utilities Committee (HAUC),
should ensure that examples of best practice are disseminated
to highway authorities and utility companies.
38. The Traffic Management Act, and the Permit
Scheme Regulations made under it, provided for a new system for
highway authorities to manage street works from April 2008, to
enable authorities to be more proactive in the management and
control of activities taking place on their roads. Permit schemes
provide for utilities to book occupation of the street for an
allocated period of time, for a specific purpose. Conditions can
be attached to permits that impose constraints on the how the
work is carried out and they can allow the local authority to
direct the timing of the work. To date, permit schemes have been
introduced only in London, Kent and Northamptonshire. In London
the scheme applies to all roads; in the other two areas permits
relate only to certain roads (Northampton's permit scheme went
live in January 2011 and focuses on strategic roads, amounting
to around 19% of their road network).[68]
39. The limited number of schemes and the short
time in which they have been in existence means that there is
not yet a consensus on what constitute the essential elements
of a good permit scheme. The Chartered Institution of Highways
and Transportation(CIHT) supports the permit scheme:
[B]y applying the Permit Schemes a greater degree
of congestion reduction has been achieved (Kent County Council
verbal statement) and despite an increase in costs to the community,
all the Permit Fees costs may be 'passed on', there should be
a corresponding reduction in congestion costs.[69]
Norman Baker MP was also enthusiastic about the permit
scheme:
I am very keen to push the permit scheme arrangement,
which has been successful. The initial findings in Kent, which
has adopted it, are that roadworks have decreased 26%. That was
the initial finding; 1,389 days in the last year have been saved
on roadworks. The London figure is a 32% reduction as a consequence
of the permit schemes there. You may know that, recently, seven
further London boroughs have signed up to permit schemes in the
last few weeks. That is a way of driving performance, co-ordinating
roadworks better and making sure that there is ownership at local
authority level for those particular works.[70]
40. The National Joint Utilities Group (NJUG)
had concerns about some local authorities' operation of permit
schemes, citing the London example, which "is not targeted
to prioritise works on the most traffic-sensitive parts of the
network," but requires permits for all works in all streets
of those local authorities that have introduced it, regardless
of whether the street is busy, so is "unlikely to reduce
congestion, as intended whilst imposing significant additional
costs on utilities and customers".[71]
In contrast, it described the Kent scheme that concentrates on
the most congested roads, thereby prioritising those works, and
resulting in "a 50% reduction in complaints about street
and road works".[72]
41. The Local Government Technical Advisers Group
(TAG) commented that permit schemes do not remove all the operational
problems connected with certain types of works:
[I]f a Distribution Network Operator (DNO, or Electricity
Company) makes a supply to a property, then the DNO are responsible
for obtaining the permit to open the road and lay the cables.
If the supply is to a lighting or traffic sign then the permit
would relate to 'Works for Road Purposes' and the highway authority
becomes responsible for seeking the permit, but without any ability
to control or influence the work programme of the DNO.[73]
National Grid's evidence highlighted the inconsistency
in the way in which key performance measures are available for
highway works covered by permits schemes to demonstrate that highway
authorities are being even-handed in the treatment of works promoters:
"In order to ensure effectiveness Key Performance Measures
(KPMs) need to be developed and applied equally to all works promoters
including Street Authorities".[74]
NJUG stated that differing schemes add additional costs to utilities,
customers and local authorities, and result in inadvertent non-compliance
because of variations between schemes. John Pettigrew, of National
Grid, also highlighted inconsistencies in their application and
the impact they are having on congestion.[75]
He argued that an independent assessment of the effectiveness
of the London and Kent schemes should be carried out, as was agreed
by the previous Government.[76]
42. It is clear from our evidence that while
there is a good deal of support for permit schemes and some promising
early results, questions about their impact remain. It is therefore
important that permit schemes are monitored and reviewed, to give
local authorities relevant data and examples of best practice.
NJUG recommended that "mechanisms are in place to share best
practice so that individual local authorities do not all 'reinvent
the wheel'" when devising permit schemes.[77]
The DfT's stated that "local authorities will be responsible
for evaluating their performance"[78]
and the Government is bringing forward proposals by April 2012
to allow schemes in England to go ahead without the Secretary
of State's approval.[79]
Norman Baker MP told us that "[l]ocal knowledge certainly
is best in terms of the specific solution for each individual
congestion point or each individual high street. Obviously a local
council know its high street better than the DfT, which has probably
never even seen the high street".[80]
43. The wider adoption of permit schemes by local
authorities could result in the emergence of a single 'best-practice'
approach, or a limited number of approachessay for predominantly
urban and rural areasto managing street works. However,
devolving permit schemes to local authorities could lead to significant
variations between the schemes, resulting in a patchwork of different
local authority approaches to street works, which could prove
particularly burdensome to the utility companies. It is the role
of Government to ensure that where there is variation between
local authorities' approaches to permit schemes, that variation
is warranted given the potential cost implications. The
Government should commission an independent assessment of the
London and Kent permit schemes, as was agreed by the previous
Government. This assessment should assess whether the initial
permit schemes are following the right approach and make recommendations
about improvements, in order to inform other local authorities
considering implementing their own permit schemes. The Government
should also put in place arrangements to monitor the uptake of
permit schemes and the variations between local authorities' approaches.
44. Another option for managing street works
is lane rental, which was provided for in the Transport Act 2000
and which involves utilities "renting" lanes when they
carry out works in the street. DfT's written evidence describes
its proposals "to pilot a 'lane rental' approach for the
most traffic sensitive roads (legislation brought forward by December
2011)"[81] and Norman
Baker MP told us that lane rental would "give an incentive
directly for utilities to co-ordinate their works because they
would have to share the cost of the lane rental rather than having
to have the scarce bit of road dug up again and then bearing the
whole cost of that particular operation".[82]
On 22 August 2011, the DfT published a consultation and draft
guidance document for local authorities, outlining how lane rentals
can be implemented.
45. The Greater London Authority (GLA) and London
Councils support the lane rental scheme,[83]
with the GLA arguing that:
lane rental would incentivise the streetworks industry
to deliver real behavioural change and encourage it to change
working practices, develop innovative working methods (eg more
joint working and shared contractors) and new technology (eg 'no
dig' technologies; more sophisticated bridging and plating systems;
application of new materials for trench reinstatement that do
not need 24 hours to 'cure') to reduce the footprint and duration
of works.[84]
Halcrow also argued in favour of lane rental:
By developing the lane rental scheme in such a way
that drives a better consideration of the planning of works it
will place the ownership for minimising unnecessary delay and
obstruction back with the undertaker. [...] By focussing on works
and/or reinstatement category and an estimate of traffic volume,
it will drive the correct behaviour from the undertaker to reduce
the duration of works. Additionally, including punitive lane rental
charges that tackle unnecessary occupation relating to defective
workmanship and/or multiple phase works will reinforce that correct
behaviour.[85]
46. In their 2003 Report into local roads, our
predecessors were not enthusiastic about lane rental schemes:
We do not believe that lane rental offers a sensible
way to reduce disruption caused by street works. The works undertaken
by utilities are necessary. The objective of any charging scheme
should be to charge for inefficiency in carrying out the work,
not for carrying out the work in the first place. The overrun
charging system already provides a mechanism to achieve these
objectives and should be made to work properly.[86]
A number of witnesses in this inquiry also had reservations
about the widespread use of lane rental. NJUG wrote that lane
rentals would be an additional charge imposed on utilities for
every day they occupy the highway, regardless of how efficiently
the work is undertaken, and that
given the myriad of regulation already available
and the numerous voluntary measures introduced by NJUG, we do
not believe that lane rental will necessarily deliver significant
additional benefits over and above the existing legislation, whilst
increasing utility costs considerably.[87]
John Pettigrew summarised the inherent problem of
the lane rental scheme:
If there is a gas leak, we have to go and respond
to it and we have to dig up the road to repair the pipe. Quite
often that job will be a two-day job. However efficiently you
do it, it is a two-day job. Therefore, to have to pay for those
two days in addition to fixed penalty notices and overrun charges
provide no incentive on us to look at the ways we are working.
It just seems to penalise us for having to do what we have a statutory
duty to do.[88]
47. Our predecessors were not
convinced about the merits of lane rentals, and we are yet to
be convinced that the scheme is the best way of tackling congestion
from street works. We recognise the potential of lane rental to
target more directly changes in the behaviour of utility companies,
which will potentially reduce disruption. However, we also recognise
the fact that there will be costs attached, which will be passed
on to customers. We want reassurance that the scheme achieves
the right balance. The Government should monitor the London lane
rental scheme, in order to assess its wider application.
48. Utility companies emphasised the discrepancy
between the treatment of work carried out by utilities, and work
carried out by local authorities themselves, notably in relation
to performance and sanctions. NJUG supported the adoption of an
independent road works commissioner, as in Scotland, who is able
to penalise both utilities and local authorities for failure to
coordinate and cooperate, writing that the commissioner role "has
proved to be effective at encouraging a more collaborative approach
to reducing disruption".[89]
The Government should study
ways of ensuring that local authorities' own works on roads are
subject to the same rules and penalties as the utility companies'
works, so as to produce the same improvements in reducing disruption.
In such circumstances, the Government should explore the possibility
of ways of ensuring that resulting fines are not simply a transfer
of resources from local authority department to another, rather
than being a real incentive to change.
Incidents
49. Incidents, in the form of crashes, broken-down
vehicles and shed loads, are seen as one of the key sources of
unreliability on strategic and local networks. Jack Semple, of
the Road Haulage Association (RHA) spoke about the time the police
take to investigate road accidents:
We understand that there needs to be a proper investigation
when there is an accident, but there needs to be a much clearer
idea about the impact that an extended closure has. We would be
interested to see what the benefit is that the judicial system
and society gets from a major closure against doing the job more
quickly, which appears to happen elsewhere in Europe.[90]
A review into the investigation and closure procedures
for motorway incidents was carried out by the DfT, the Association
of Chief Police Officers (ACPO), the Highways Agency and the Home
Office, to investigate how the duration of motorway closures due
to incidents could be reduced, in order to keep motorways moving.[91]
The review has ten recommendations, including exploring the role
of emergency responders and other parties in motorway incidents
(other than the police and the Highways Agency), analysing the
causes of regional variations, producing more accurate and useful
information on delays, producing a collection of case studies
and good practice models, exploring the use of technologies in
incident management, and providing more police training for on-road
and collision investigation. Of particular concern is the significant
regional variation of motorway closure, despite the similarity
of accident types, dues to the regional and national autonomy
that police forces have, which results in individuals applying
and interpreting procedures differently, and due to a lack of
the dissemination and sharing of good practices.[92]
The DfT plan to carry out further analysis to help to understand
the causes of regional variations by December 2011.[93]
The DfT's written evidence stated that "we are committed
to ensuring that any improvements identified from the review are
taken forward by December 2012.[94]
Supplementary evidence submitted by the DfT revised that date
and stated that:
The majority of the reviews recommendations are
expected to be completed by the end of the year, and we remain
on track to deliver on a further business plan commitment to set
up and implement measure[s] to reduce congestion by incidents
by December 2012.[95]
50. We support the Highways
Agency in its joint initiative with the police and the Home Office,
to speed up the time taken to clear major roads, following an
incident. We particularly support the Highways Agency's work in
analysing the regional variations of motorway closures. The review
was published in May 2011, but some of the recommendations will
not be taken forward until December 2012. There needs to be continued
commitment from all parties, with maintained urgency in addressing
all of the outcomes of the review.
61 Ev 38 Back
62
Ev 23. We did not receive many submissions from local authorities
on this issue and so do not have specific examples of variations
between local authorities. Back
63
Dave Turnbull, of the National Joint Utilities Group, described
TfL's "workathons", where streets are closed and different
utility companies are invited in to carry out routine work at
the same time, rather than sequentially (Ev139). Back
64
Ev 188 Back
65
Ev 129 Back
66
Ev 137 Back
67
Ev 137 Back
68
Ev 139 Back
69
Ev 118 Back
70
Ev 65 Back
71
Ev 139 Back
72
Ev 139 Back
73
Ev w130 Back
74
Ev 130 Back
75
Ev 29 Back
76
Ev 139. We did not receive evidence on specific examples of permit
schemes in operation. Back
77
Ev 141 Back
78
Ev 122 Back
79
Ev 122 Back
80
Ev 64 Back
81
Ev 122 Back
82
Ev 66 Back
83
Ev 188 and Ev 193 Back
84
Ev 188 Back
85
Ev w49 Back
86
Transport Committee, Fifth Report of Session 2002-03, Local
Roads and Pathways, HC 407, para 112 Back
87
Ev 140 Back
88
Ev 29 Back
89
Ev 137 Back
90
Ev 4 Back
91
DfT, Review of Investigation and Closures Procedures for Motorway
Incidents - Preliminary Report, May 2011 Back
92
Ibid, p20 Back
93
Ev 127 Back
94
Ev 122 Back
95
Ev 127 Back
|