4 Future investment
Rules and principles for the
use of private finance
72. As mentioned in the previous section of the Report
all PFI projects have to undergo a VfM assessment. In a paper
for the Lords Economic Affairs Committee the NAO made the following
comments about this:
[...] like any financial model, they [the VfM assessment]
cannot be relied upon as a sole source of assurance. They are
susceptible to manipulation and we often find problems with their
implementation.[143]
We consider some of the possible changes to the current
VfM assessment later in the report.
Any financial model, such as the current VfM assessment, can be
subject to manipulation so it should never be used alone as a
pass or fail test for the use of PFI.
73. In the 1980s the use of private or additional
finance was governed by what were known as the 'Ryrie Rules'.
These required that private finance could only be used if:
- there were no favourable risk
terms, such as a government guarantee;
- projects yielded benefits in terms of improved
efficiency and profit commensurate with the cost of raising risk
capital; and
- that use of private finance could not be additional
to public finance. In other words, public expenditure would be
reduced, pound for pound, in consequence of the use of private
finance. [144]
David Heald and Alisdair McLeod went onto explain
in their paper on the Ryrie rules that
The rationale for this provision was that there is
little macroeconomic difference between the government borrowing
on the market to finance public expenditure generally and the
private sector borrowing for essentially public projects. The
objective of the Ryrie Rules was to stop ministers from insulating
private finance from risk so that it could be used to circumvent
public expenditure constraints. [145]
74. The Private Finance Initiative was a departure
from the Ryrie rules as it allowed private finance which would
be additional to public finance. In 1992 the then Chancellor,
Norman Lamont, said in his Autumn Statement:
[...] we will allow greater use of leasing where
it offers good value for money. As long as it can be shown that
the risk stays with the private sector, public organisations will
be able to enter into operating lease agreements, with only the
lease payments counting as expenditure and without their capital
budgets being cut.[146]
The importance of risk transfer and value for money
were evident as PFI started. In a speech to the CBI Conference
on 8 November 1994[147]
the then Chancellor Kenneth Clarke emphasised that the guiding
principles of PFI were that:
- the private sector must genuinely assume risk
without the guarantee by the taxpayer against loss; and
- value for money must be demonstrated
for any expenditure by the public sector.
75. As the use of PFI has progressed there has been
more detail on the approach in regard to risk transfer. In 1995
HM Treasury noted that "risk should be allocated to whoever
is best able to manage it"[148].
This approach is detailed in HM Treasury's document Meeting
the Investment Challenge:
The Government's approach to risk in PFI projects
does not seek to transfer risks to the private sector as an end
in itself. Where risks are transferred, it is to create the correct
disciplines and incentives on the private sector to achieve a
better outcome.
Successful PFI projects should therefore achieve
an optimal apportionment of risk between the public and private
sectors. This will not mean that all types of risks should be
transferred to the private sector. Indeed, there are certain risks
that are best managed by the Government; to seek to transfer these
risks would not offer value for money for the public sector.[149]
76. Evidence
we have seen suggests that the high cost of finance in PFI has
not been offset by operational efficiencies. Much more robust
criteria governing the use of PFI are needed. These should take
precedence over the current VfM assessment. If and only if a project
is deemed to pass these criteria should the option of private
finance be considered. In our view PFI is only likely to be suitable
where the risks associated with future demand and usage of the
asset can be efficiently transferred to the private sector. We
recognise that this may over time sharply reduce the aggregate
value of remaining PFI projects but the higher cost of capital
that remains will be easier to justify to the taxpayer.
Different sectors and circumstances
77. When gathering evidence for this inquiry we posed
a number of questions. Two of these were: 'Are there particular
projects which are suited for PFI?' and 'In what circumstances
are PFI deals suitable for the delivery of services?'. We were
interested to understand whether PFI was more appropriate within
certain sectors and circumstances. Skanska told us that:
We believe that PFI is most suitable for the delivery
of services that contribute to whole-life costing benefits and
which are stable and predictable over the long term. PFI is less
suitable for services that need to flex significantly over time
to reflect changes in public service delivery, demographics or
technology.[150]
Others also expressed the view that PFI was suited
to operations where use was predictable over time and less suitable
for services that were likely to need change. The CBI told us:
"PFI works well when the risks of a project can be identified,
quantified and transferred appropriately." It considered
that "build and service contracts that have been used to
provide schools, simple healthcare facilities and housing have
been successful" as had "economic infrastructure projects,
which have seen roads, railways and airports built and maintained".
However it considered that schemes that "introduce complex
technology risk, or in which future outcomes cannot be readily
forecast may be less appropriate"[151]
for PFI.
78. Transport for London told us that "PFI may
be suitable" in circumstances where "the public sector
can define its long-term needs and wants a single integrator of
the delivery of that service". It also pointed out that projects
that were the "least successful were all bespoke".[152]
Steve Allen told us:
If you look at things like roads or new railways,
where once you have designed where the transport scheme is going
to go, you fundamentally are not going to change it, those have
been more successful examples of PFIs than things that are intimately
involved with the operations of transport; for example, the experience
of the London Underground PPP, where it was much too closely intertwined
with the day-to-day operations.[153]
Martin Blaiklock told us that in his opinion "Typically,
'accommodation'-type projects, where the underlying demand and
service output over 30 years does not change, are suitable for
PFI treatment."[154]
79. Owing
to the current high cost of project finance and other problems
related to PFI we have serious doubts about such widespread use
of PFI. There are certain circumstances where PFI is likely to
be particularly unsuitable, for example, where the future demand
and usage of an asset is very uncertain and where it would be
inefficient to transfer the related risks to the private sector.
Re-examining the VfM assessment
80. Prior to commencing the procurement of a PFI
scheme, central government guidance requires the sponsoring authority
to draw up an Outline Business Case (OBC), in which the
rationale for the project is presented to ministers for approval.
The OBC includes details of a Procurement Route Comparison,
in which the projected Net Present Cost of the proposed PFI project
is compared with that of an identical scheme carried out on the
basis of conventional (i.e. non-privately financed) procurement.
81. Despite the significantly higher cost of private
finance, the vast majority of projects submitted to the Procurement
Route Comparison exercise continue to find in favour of the
PFI option. To a significant extent, this reflects the incentives
that public authorities (and their sponsoring departments) are
subject to which favour the PFI methods (see Accounting and
budgetary incentives of PFI), and the fact that the model
is, as the National Audit Office has noted, "subject to manipulation".[155]
We understand that the Treasury is making some changes to the
guidance which determines the current quantitative element of
this system, and will publish these in the autumn, but regards
the system as fundamentally sound. We
believe that a financial model that routinely finds in favour
of the PFI route, after the significant increases in finance costs
in the wake of the financial crisis, is unlikely to be fundamentally
sound.
The Treasury should seek to ensure that all assumptions in the
VfM assessment that favour PFI are based on objective and high
quality evidence.
82. In this report we are not able to examine every
part of the VfM assessment in detail. We have therefore chosen
to consider just two of the areas in more detailthe 'optimism
bias' and the adjustment for tax. In the quantitative assessment
component of the procurement route comparison, two models are
constructed (one for a PFI and one for a conventional public procurement)
where the specification of the facility is the same, as are many
of the projected costs and risks. However, risks that in the public
authority's view would be borne by them under conventional procurement,
but which in the PFI solution would fall on the private sector,
are valued and a percentage is added to the costs of the conventional
procurement route. In the Treasury spreadsheet,[156]
risks transferred to the private sector in this way are identified
as 'optimism bias'i.e. the likelihood that capital and
operating costs will prove to be substantially higher than those
estimated at the time of the OBC assessment.
83. This uplift is designed to reflect the fact that
there is "a demonstrated systematic tendency for project
appraisers to be optimistic".[157]
This uplift to the estimated cost of the capital expenditure undertaken
under a conventional procurement option, for example, is commonly
in the range of 15-20%. However, the evidence base on which optimism
bias adjustments are made is unclear. The key source appears to
be a study published in 2002 by a prominent technical advisory
firm within the PFI industry, Mott MacDonald.[158]
This study has been called into question by scholars due to methodological
concernspecifically, the non-comparability of projects;
small sample size and numerous source of measurement bias. They
noted that the "PFI sample contained only 11 projects, although
451 PFI construction schemes were completed" and there was
an "over-representation of atypical schemes in the conventional
procurement sample and under-representation of them in the PFI
sample".[159]
84. The Treasury
should ensure that guidance regarding Optimism Bias is based on
objective, high quality and, as far as possible, contemporary
evidence. The Treasury should not approve the PFI projects of
departments or public authorities that fail to produce such evidence
in support of their Outline Business Cases. We believe that the
comparison of procurement routes should take place on the basis
of the PFI model and a public procurement model, in which there
is a serious attempt to fix prices and therefore transfer risk.
85. Hardwired into the Treasury Value For Money Guidance
spreadsheet is an assumption that, owing to the use of private
finance, PFI will lead to additional tax being received by the
Treasury. The current guidance follows advice from the prominent
PFI financial advisory firm KPMG[160]
that corporation tax which would be received by the Treasury should
be deducted from the costs of the PFI option (or added to the
PSC, which has a similar effect). At the time of the KPMG report
corporation tax was 30%. It is currently 26% and is due to fall
to 23% by 2014.[161]
The corporation tax adjustment can be between 2% and 22%, of the
total costs of a project, depending on the assumptions in the
spreadsheet. These projected corporation tax levels are significantly
higher than would be expected by the companies involved in PFI
projects[162] and assume
a level of corporation tax exposure that is likely to be much
greater than Special Purpose Vehicles actually pay on average.
Corporation tax SPVs are normally a private 'shell' company with
no assets, and owned by the shareholders in the project. The SPV
typically borrows approximately 90% of the capital required to
develop the project, and receives income when the project is operational.
86. As well as the fact that interest paid by the
highly leveraged SPV is tax deductable the SPV is also likely
to adopt sophisticated tax limitation strategies. Indeed, an SPV
that can organize its tax planning efficiently, including the
use of transfer pricing and off-shore registration and claim all
possible tax allowances, might pay less tax than the conventional
alternative. For example, the STEPs deal, providing property and
premises for the two Departments which were to become HMRC, was
negotiated with Mapeley STEPS Limited, a property holding company
registered in Bermuda.[163]
A study of the early PFI highways projects found higher rates
of profit, and low payments of corporation tax, and questioned
the assumption that high rates of tax would be paid.[164]
Evidence we received shows that ultimate ownership of over 90
PFI projects has moved offshore.[165]
87. The current
'tax adjustment' is not based on the best available evidence and
acts to bias the assessment towards choosing PFI. Private companies
entering into contracts with the public sector will quite reasonably
seek to minimise their tax liabilities. Governments may also vary
tax rates. The assessment exercise which
evaluates the value for money
of different procurement routes must take this into account.
88. As part
of the Lords Economic Affairs Committee investigation into PFI
in 2009-10 the National Audit Office produced a paper which raised
doubts about the use of the VfM assessment financial model. In
particular the NAO noted that "we have yet to come across
robust cost analysis between procurement routes, that tests the
assumptions of cost efficiency set out in business cases."[166]
89. The National
Audit Office should perform an independent analysis of the VfM
assessment process and model for PFI. It should audit all of the
assumptions within the model, and report on whether or not these
are reasonable. This test of the VfM assessment model should,
where possible, be based on representative and up to date samples
of data.
Investment in public infrastructure
90. The importance of investment in infrastructure
was expressed in numerous submissions. Skanska's submission said
that there was "a proven need for infrastructure in the UK
that is currently unfulfilled".[167]
Balfour Beatty also made a similar point and considered that there
had been underinvestment in the past:
Balfour Beatty believes that sustained investment
in infrastructure is vital to the future of the economy. From
1999-2008, UK public investment as a percentage of GDP was lower
than almost any other OECD country and almost half the average
of G7 countries.[168]
This view agreed with a paper of December 2009 from
the Institute of Civil Engineers. This noted that:
The UK suffers from a historic under investment in
infrastructure, which the OECD has identified as a major factor
holding back our economic performance. This has also been acknowledged
by HM Treasury. As a result the World Economic Forum ranks the
UK 33rd in the world for the quality of its infrastructure.[169]
Dieter Helm agreed with the need for investment in
his additional submission to the Committee: "The UK requires
a very significant increase in infrastructure spending, reflecting
a combination of new policy priorities and the failure to maintain
and enhance existing assets."[170]
91. Balfour Beatty also pointed out in its written
evidence that "investment in infrastructure has a higher
economic multiplier than other types of government expenditure".[171]
The Office for Budget Responsibility own analysis agrees with
thisits estimates show that capital expenditure has the
greatest impact of the fiscal multipliers.[172]
Table 3: Estimates of fiscal multipliers
Impact multipliers
|
Change in VAT rate
Changes in the personal tax allowance and National Insurance Contributions (NICs)
AME welfare measures
Implied Resource Departmental Expenditure Limits (RDEL)
Implied Capital Departmental Expenditure Limits (CDEL)
| 0.35
0.3
0.6
0.6
1.0
|
Source: OBR, Budget Forecast, June 2010, p95,
Table C8
The UK Contractors Group made the point that "more
construction investment would help to stimulate the economy and
employment".[173]
92. As investment in infrastructure is so important
for the economy it is essential that the most efficient form is
pursued and also that any changes should be phased to keep disruption
in investment plans to a minimum. The most straightforward way
for government to phase out PFI while continuing and even increasing
investment is directly to fund capital spending. With the cost
of government borrowing at historic lows and at a significant
discount to other forms of finance there is a strong argument
to be made that this would be the most efficient form of financing
and therefore would release higher levels of investment at the
same cost.
93. Any increase in direct capital investment would
inevitably lead to higher borrowing figures in the short term
as debt would be fully transparentunlike with PFI where
most of the liability is not part of government borrowing figures.
However it is unclear why this should stop the government acting,
particularly if in the long term PFI is less affordable. Dieter
Helm considered that continuing with PFI would in effect be imposing
a tax on us all:
if [...] the conventional PFI approach continued,
the economy and society bears a considerable deadweight welfare
loss through the high cost of capital. A rule based and flawed
accounting methodology would be in effect imposing a tax on us
all.[174]
An increase in government borrowing to replace PFI
investment should not make it harder for the Government to meet
the fiscal mandate which the Office for Budget Responsibility
monitor. As the borrowing is for capital investment it will not
increase the cyclically adjusted current balance which the OBR
measure. Also if any increase in borrowing occurs before 2015-16
the supplementary target will also be unaffected. The coalition
government increased capital budgets at the Spending Review without
any direct impact on the fiscal mandate so this shows that such
an approach is possible:
[...] the Spending Review has increased the capital
envelope by £2.3 billion a year by 2014-15 relative to the
Budget plan in order to ensure that capital projects of high long
term economic value are funded. This change has no direct impact
on the fiscal mandate, which targets the cyclically adjusted current
balance, and will also not alter the year in which public sector
net debt as a percentage of GDP begins to fall.[175]
94. Sustainable
investment in public infrastructure is important for the long
term health of the economy. We also recognise the paramount importance
at the current time of stabilising the public finances. The Treasury
will need to consider using more direct government borrowing to
fund new investment. Replacing some PFI with direct public sector
investment would not necessarily result in a higher financial
liability for the Exchequer. It would mean that the debt was more
transparent, as it would be held directly by government rather
than through the intermediary of an SPV. An increase in government
debt to replace PFI investment should also not necessarily make
it any harder to meet the fiscal mandate. Continuing to use an
inefficient funding system such as PFI is likely in many cases
to increase the overall burden on taxpayers for the provision
of public sector capital projects. If, rather than using PFI,
the lower financing costs of government are utilised, we have
seen evidence that investment can be increased significantly for
the same long term funding costs.
95. PFI is a
procurement model where the private sector
manages the design, build,
finance and operation (DBFO) of public infrastructure. If the
public sector funds the investment this changes the financing
element of the project but this can still accommodate a high level
of private sector involvement. There may be merit in making more
use of a design and build (DB) model using a fixed price contract
to place risk with the private sector over the construction period.
There will be other circumstances where a design, build and operate
(DBO) model is most appropriate. Both the DB and DBO model allow
government to benefit from its lower cost of funding while transferring
significant risk to the private sector.
Current contracts and existing
deals
96. £60 billion worth of capital investment
(in 2010 terms) have already been committed to by PFI investors
under successive governments.[176]
One important question to consider is what is to be done with
the PFI contracts that have already been signed and the assets
which are already being delivered under PFI agreements. Andy Friend
suggested that refinancing was one option: "I think maybe
we are now in the territory where the public sector might contemplate
having a right to refinance the senior debt and the capital structure
of such propositions when you get into the operational stage."[177]
Dieter Helm also agreed that there should be a right to demand
refinancing once construction risk ends in a contract.[178]
97. Refinancing with government debt would be the
most straightforward way to allow renegotiation of contracts,
replicating what Steve Allen told us that TfL have been able to
do with some of its contracts.[179]
This refinancing would result in higher government borrowing figures,
but this would only be because the debt was visible rather than
hidden. As well as allowing for renegotiation, refinancing with
low cost government bonds would significantly reduce the PFI unitary
charge and make deals more affordable. The OBR estimate that the
"the total capital liability" of PFI deals stands at
around £40 billion.[180]
If government refinanced this debt at a lower rate of interest
then, for every percentage point the interest rate reduced, annual
savings of £400 million would be realised for taxpayers.
98. The most
straightforward way of dealing with current PFI contracts is for
the government to buy up the debt (and possibly also the equity)
once the construction stage is over. This would result in an increase
in the headline level of government debt but it would not increase
the structural deficit or prejudice the fiscal mandate as this
debt would score as government borrowing for investment in the
National Accounts. Interest rates on the financing of the deals
would fall significantly, releasing savings. Although government
debt levels would be higher the public finances would not be any
less sustainable. This is because it would become more affordable
to service the visible government debt rather than the hidden
PFI debt. Every one percentage point reduction in the interest
rate paid on the estimated £40 billion of PFI debt would
realise annual savings of £400 million.
99. In most cases, PFI projects involve significant
and long-term financial commitments for the public authorities
involved. Given the fiscal challenges faced by government, and
the degree to which public expenditure is currently being scrutinised
for potential savings, there is pressure on public managers to
secure a better deal from existing PFIs. A high-profile review
of public sector efficiency recommended that the government audit
all procurement contracts with a concession value of over £100
million, and explore ways of breaking contracts where these represent
poor value for money. [181]
At the time of writing, the Treasury was
consulting with major DBFO investors on plans to introduce a code
of conduct[182]
on reducing the costs of existing deals,
and individual public authorities are being encouraged to work
with investors to identify where and how reductions in their charges
might be achieved.
100. However, it should be recognised that there
is a limit to the savings that can be achieved on existing contracts.
Any attempt unilaterally to reduce PFI payments could have negative
side effects. Mr Friend noted the potential for:
the hazard that it creates in terms of UK reputation
[...] I think these things need to be borne in mind as we play
the larger game, which is: how do we finance and fund the nation's
infrastructure needs over the next decade?[183]
Mr Wardlaw also noted that:
I think there is a really important issue here about
the perception of political and other risk around the UK and the
UK's infrastructure, because those investors, those contractors,
those utility companies outside the UK who are making these decisions
have alternative places to put their capital.[184]
101. Mr Friend did however consider that it might
be worthwhile looking at the contracts on a case-by-case basis:
What I think is more feasible is a vigorous, taskforce-based
approach that would require the Infrastructure UKs, the Local
Partnerships of this world and the local authority bodies, on
a case-by-case basis to work through: what is the potential for
varying scope? What is the potential for increasing productivity?
What is the potential for taking back risks that were transferred
at a price, like insurance risk, the energy risk I referred to
earlier, and literally cutting a deal case-by-case? My perception
is that there would be a willingness in the private sector on
a case-by-case basis.[185]
Mr Rabin agreed telling us "I think that renegotiation
is always feasible and, potentially in some cases, desirable."
He added "I do very strongly believe that that should be
at a local level between the buyer of services and the provider
of services rather than at an omnibus global level."[186]
102. Where the return to an investor is significantly
higher than the level projected at the time of contract signature,
there may be an opportunity for such gains to be shared. If equities
are sold by 'primary' to 'secondary' investors after the risky
construction period has been completed, this can give rise to
a capital gain, the post-tax value of which will under current
arrangements accrue entirely to the primary investor. Similarly,
it has become evident that
the price paid for maintenance (which
is agreed when the contract is signed) has often become unrelated
to the actual cost for the provider[187],
which can also generate significant additional
investor cash-flow. Currently, the price paid for maintenance
is locked in once the long term contract is signed and is therefore
not subject to competitive pressures over its life.
103. We explored the issue surrounding sharing the
capital gains on the sale of equity stakes. Mr Friend expressed
a concern:
I think the problem with renegotiating at the equity
level, as Richard has referred to, is that I think the current
Treasury estimate is that 55%perhaps slightly moreof
the original equity has moved on, and it has been brought across
a wide variety of institutions now, and that is the problem.[188]
Canmore Partnership did not believe that "calls
to share investors' gains on disposing of their equity interests
[...] is reasonable or practical" as:
these procurements are presumably already deemed
to represent better VfM than alternative procurement models (ie
Full Business Case approvals will have had to show this to be
the case) and so profits on disposals are surely part of investors'
reasonable "upside".[189]
104. Where the actual return on private capital is
much higher than that projected return it is possible that the
government could use its purchasing power to negotiate gain-sharing
arrangements without eroding its credibility. There is, indeed,
a precedent for this. In 2002, the Office for Government Commerce
and several major investors in the PFI programme signed a code
of practice[190] which
committed the latter to share gains made via refinancing their
debt (which significantly accelerates cash-flow and increases
investor returns), even though contracts did not stipulate any
such sharing.
105. We welcome
the work that the Treasury is doing with the PFI industry on drawing
up a code of conduct. We believe that it is in the interest of
the PFI industry to cooperate as fully as possible with the government
in this regard. In 2002 the government reached a voluntary agreement
with industry to share refinancing gains with the taxpayer. Therefore
in principle there is no reason why a non-obligatory gain-sharing
arrangement could not also be considered in relation to the gains
on the sale of equity stakes.
106. As well
as the numerous PFI deals which have already been committed to
there are also many deals already in procurement and others are
in the pipeline. If the public sector wants
to reduce costs it must ensure that the prices and profit margins
charged by the private partner are at the market level at the
start of the contract and also that efficiencies can benefit the
taxpayer over the life of the contract. These issues are considered
in more detail in Box 3.
Box 3: Returns on PFI investment
Analysis by Mark Hellowell - Specialist Adviser
to the Committee
There are currently 61 projects in procurement,
representing projected capital expenditure of £7 billion.
In this context, it is essential that the government ensures that
the ongoing revenue costs to the public sector of new PFI projects
are minimised. This can be done in two ways: (a) ensuring that
the prices and profit margins charged by the private partner are
at the market level (and the market should be defined more broadly
than PFI alone), and (b) that the likelihood of productivity gains
throughout the contract period is recognised in contracts, so
that there is a mechanism for sharing such gains. In respect of
(a), it is important to consider both operational and financial
costs. In terms of operational costs, it is clear that the costs
of construction, maintenance and service provision must be benchmarked
against best practice in the market more generally. As the National
Audit Office has pointed out, this will require the compilation
and active use of much better data than has been utilised by departments
hitherto[191].
Treasury officials have made the observation that
the cost of primary equity was too high as far back as November
2005.[192]
However we have seen no evidence that equity rates of return have
come down since that date. The cost of equity quoted by major
investors in terms of constructing discount rates for valuing
their portfolios of PFI projects is typically in the range of
7-9%.[193]
The rates of return targeted by primary investors are around double
those normal on the secondary market, and the risks borne by equity
investors during the construction and early operational stage
of contracts do not justify this. There is a case to be made for
action to be taken to ensure that Equity Internal Rates of Return
cluster around their efficient level, which should be close to
the cost of equity quoted by PFI investors, and much closer to
secondary market discount rates.
In respect of (b), a private company in charge
of services over a 30 year contract is likely to find opportunities
to reduce costs over this period. Of the services included within
the PFI structure, only "soft" facilities management
services, such as catering and cleaning, are benchmarked or market
tested during the contract period. Currently, there is no mechanism
under which the gains from such efficiencies in maintenance can
be shared with the public sector-and thus the gains accrue to
equity-holders in their entirety. Although maintenance services
are subject to competitive tension in the tendering process, the
standard PFI structure does not allow sharing from any efficiencies
in building maintenance which contractors achieve over the contract's
life.
This is because these services are not value tested
and contractors do not share with public authorities information
on their maintenance spend. This is both undesirable in its own
terms, but is also likely to lead to opportunistic behaviour.
Currently, because "soft" facilities management services
are benchmarked/ market tested, there is an incentive for a bidder
(working within the context of a strict public sector budget constraint)
to under-price this element of the services at the point of financial
close, and over-price the hard facilities management services
(i.e. build in a profit margin above the market level). When,
in subsequent years, the price of the soft facilities management
services are benchmarked, this will lead to the price going up.
The public sector will, in this event, pay a market price for
the soft services and an above-market price for the hard facilities
management, and it will pay this above-market price for the entirety
of the contract period.
One option would be to examine the potential for
broadening the benchmarking/market testing process to include
all services. However this is complex. For example, there would
be a need to consider how the price paid for hard facilities management
payments interact with the costs of life-cycle replacement. In
practice, this may not be possible. A simpler, and likely more
effective, method would be to ensure that any free cash-flow (i.e.
cash in excess of that required to pay operational or debt costs)
in excess of that required to provide equity investors with the
rate of return projected at financial close is shared with the
public sector. This would ensure that the private sector retains
an incentive to invest in productivity gains in maintenance (as
under PFI now) but that the benefits from this are shared with
the public sector (as is not currently the case).
It may also be useful to examine the experience
of the "hub" private finance model in Scotland, in which
similar principles are in operation. |
107. We
recommend that HM Treasury collates and compares data to ensure
that it gets a good price on any deals already being negotiated.
It should benchmark operational costs of PFI projects with market
prices outside PFI. It should also compare the equity returns
of investors with other investments with a similar risk profile.
It should publish as much of this information as is commercially
possible. Far more transparency is required. The Treasury should
consider whether this should extend to publishing data and costings
on existing contracts, where commercially possible, in addition
to what is already published. The Treasury should also consider
introducing a mechanism for deals in procurement to ensure that
any productivity gains are shared with the taxpayer over the life
of the contract. Based on the analysis presented in this Report,
we ask the Government to give further consideration before proceeding
with the procurement in its present form of the Royal Liverpool
and Broadgreen Hospital in particular.
Improving procurement and project
management skills
108. As part of our inquiry we received evidence
about the importance of improving procurement and project management
skills in the public sector. The CBI pointed out that:
For complex procurements to be successful it is essential
that project teams have the appropriate skills and experience
and are adequately supported by central bodies with strategic
oversight.[194]
Mr Friend told us that of the many reports written
about PFI projects "I reckon a good two-thirds of them refer
to the need to invest seriously in commercial skills in the public
sector, and I do not believe that we have done that consistently".
[195] Dr Chris
Lonsdale from the University of Birmingham noted in his submission
that "Risk transfer under the PFI, and in public sector procurement
generally, has been further affected by limited public sector
commercial skills." He noted that there had seemingly been
a lack of understanding in the higher levels of the civil service:
In terms of commercial skills and capabilities, the
UK public sector has spent the 20-year life of the PFI attempting
to create the necessary capacity. For many years, there seemed
to be too little appreciation in the higher civil service ranks
of the extent of the difficulties of complex procurements.[196]
109. TfL's submission pointed out that "TfL
invests heavily to ensure that it has the right skills to manage
its risks". It considered that there was a case for other
organisations to be "supported by others that have the resources
and experience, rather than having to buy the experience more
expensively from the private sector".[197]
Skanska agreed that there should be a "focus on development
of public sector in-house skills"; this they believed would
encourage "the public sector to take ownership of projects
rather than relying on external advisers".[198]
The NAO reported in 2007 that the "average cost of external
advice for all projects was just over £3 million per project
or approximately 2.6 per cent of the capital value of the projects".[199]
We asked Mr Abadie how much PwC had received as financial advisors
on PFI procurements. He explained that for a school they would
"probably get £250,000 to £400,000"[200]
and for a hospital it "may be £500,000 to £800,000"[201].
Mr Abadie also told us that PwC often had people on secondment,
including himself, to the government.
110. The head of PFI policy at HM Treasury has often,
like Mr Abadie (a partner at PwC), come from a banking or accountancy
background rather than having design or construction expertise.
Many have also been on secondment. Geoffrey Spence who preceded
Mr Abadie as head of PFI at the Treasury was seconded from Deutsche
Bank in 2001. Mr Abadie was succeeded by Charles Lloyd in 2009another
secondee from PwC. The current outgoing senior official at HM
Treasury responsible for PFI is Andy Rose who also has a background
in finance. PFI is a DBFO (design, build, finance and operate)
procurement method. The expertise of those responsible for PFI
policy at the highest levels in government has been primarily
on the financing element of the project.
111. The need
to improve procurement and project management skills in the public
sector is something that all are agreed on. In some ways PFI may
have exacerbated problems in this area. Rather than focussing
on improving procurement methods and project management, public
sector clients' attention has been diverted to financing arrangements
and the other requirements unique to PFI. Owing to the complexity
of PFI, the public sector has become too reliant on expensive
external advisers. We are also concerned that PFI may have resulted
in the balance of expertise within the centre of government being
tilted too heavily towards financial skills with less input from
those with experience in design and construction.
Other ideas
INFRASTRUCTURE ACCOUNTS
112. The need for a national set of accounts was
raised by some of our witnesses. Dieter Helm told us "we
have no national balance sheet to set against our assets and liabilities"[202]
adding that this meant "we are not interested in the question
of what level of investment we should carry out to set against
so we can set assets against liabilities".[203]
He explained in his written submission in further detail the benefits
of this:
A national balance sheet would enable rational decisions
to be made about borrowing and investing, and hence allow the
low public cost of debt to be translated into lower costs of capital
for infrastructure projects. The absence of proper balance sheet
accounts therefore has a real deadweight welfare cost: the higher
cost of capital on highly capital-intensive projects. The private
returns on PFIs reflect this deadweight loss to society.[204]
He explained that without national accounts "I
have no idea what our financial deficit in this country is, because
I don't know whether we have just been eating up assets and depleting
our infrastructure or not."[205]
113. Other evidence we received agreed that a set
of national accounts would be an positive step. A joint submission
from KPMG LLP, John Laing PLC and Lloyds Banking Group said:
We believe government should invest in systematically
collecting and analysing evidence on the comparative performance
of all procurement approaches.[...]
The single biggest step in this regard would be the
institution of a set of national infrastructure accounts, which
would show both asset investment and asset depreciation. Such
accounts would provide a starting point for inquiries such as
this to get under the skin of the infrastructure challenge and
to compare like with like, and would force the public sector and
its partners to think long-term.[206]
We asked Professor Helm how easily a set of national
asset accounts might be created. He said that if you want a "perfect
set of accounts, then it is really difficult". In his opinion
it was therefore "best to just get on with it". He added
"Let's have a look at what has happened to the oil. Let's
see what electricity networks looks like. Let's have a look at
the water networks. Do it pragmatically." This he explained
would allow government to get a "handle on the big items
pretty quickly and we can tell whether we are depreciating rapidly
or not. So, the answer to that is it is not difficult."[207]
In a recent Committee hearing on the Bank of England inflation
report The Governor emphasised the importance of understanding
both assets and liabilities. He explained that the sustainability
of the public finances should "be judged in the context not
just of future liabilities, whether it be pensions, PFI projects
or any other kind of liability, but also assets."[208]
114. On 13 July 2011 the first summary of the Whole
of Government Accounts (WGA) was published. This is an unaudited
summary report for the year ended 31 March 2010. The audited version
of the accounts will be published later in the year. The WGA is
a consolidation of the financial accounts of about 1,500 public
bodies and therefore does not include a value of all of the infrastructure
of the country.
115. While there
is an understandable focus on the current high levels of government
debt, the government and the citizens of the country have no proper
understanding of the assets which accompany these liabilitiesthere
is no national balance sheet. The audited Whole of Government
Accounts will be published for the first time later this year.
This will provide further understanding of public sector organisations
assets' for financial reporting purposes.
INFRASTRUCTURE FUND
116. One idea proposed to us to lower the cost of
capital for projects was an infrastructure fund or bank. Professor
Helm gave a hypothetical example of how such an fund could be
beneficial:
Supposing the Government wants there to be 10 nuclear
power stations in this country at £5 billion each. That is
£50 billion over the next 10-15 years. Supposing it borrowed
a fund called the Nuclear Bond Fund, and it borrowed £50
billion and it just asked the builders of those stations to bid
for that money. So, it is the Government borrowing but the private
sector is doing the CAPEX and the OPEX thereafter.
He explained that such a scenario would lower the
cost of capital significantly:
It [the Government] would currently borrow probably
[...] [at a] negative real interest rate. The private sector [borrowing
cost] for a nuclear power station may be 10% or 15% real. It doesn't
take first year undergraduate maths to work out there is a colossal
difference between those numbers [...][209]
117. A 2009 paper to which both Dieter Helm and James
Wardlaw contributed recommended that "The UK should establish
an infrastructure bank (UKIB)". In the paper Mr Wardlaw gave
some detail about the benefits that this could bring:
The prize is an institution which facilitates the
introduction of private sector capital without crowding it out,
finances itself with a government guarantee, aims to break even
with any dividends reinvested, and whose liabilities do not score
in the National Accounts but whose activities are defined by national
priorities.[210]
Another witness, Richard Abadie of PwC, agreed telling
us: "I am supportive of an infrastructure bank as well".[211]
Healthcare Audit Consultants explained that "Just as the
European Investment Bank helped finance the new Barts' and the
London Hospital so a UK infrastructure bank could make funding
easier for needed capital expenditure within the public sector".[212]
118. We explored the idea with Mr Wardlaw in more
detail. He considered that the UK had "suffered" without
such a bank:
Well, I think to some extent we have suffered without.
Many other countries in Europe have benefited from having a national
infrastructure bank or a state development bank: KfW, Eco in Spain,
and CDC in France. I think that it has been an important part
of the armoury of tools to enable infrastructure to be constructed
in a public sector context.[213]
However he considered that part of the solution was
already being planned. He told us: "I think we are sort of
getting it. It is called the Green Investment Bank."[214]
Dieter Helm however pointed out a difference between the Green
Investment Bank (GIB) and an infrastructure bank:
The GIB is essentially a project finance vehicle,
and hence it needs capital injections and equity finance. The
infrastructure bank would be a debt vehicle, and would conform
to the old-fashioned idea that an investment bank is all about
matching savers with investors [...][215]
RAB AND LABV
119. One potential avenue for lowering the cost of
capital is to use a Regulatory Asset Base (RAB). In a RAB an asset
earns a regulated return for the investor. We asked Dieter Helm
about this:
You do your capital project [...] it is finished,
and that is the refinancing point. That in the utilities is the
point where the asset goes into a regulatory asset base and then
earns just a marginal cost of debt, which is very much lower than
the marginal cost of debt that is being done in these businesses
[...][216]
He provided more detail in a supplementary submission
for the Committee about how the RAB model could apply to PFI.
There are a number of ways in which the PFI framework
could be brought into a RAB-based model. The optimal approach
would be to create an infrastructure "bank". The bank's
role would be to match savings (in practice largely pension and
life funds) with investments in infrastructure projects such as
those currently included in the PFI contracts. The bank would
"buy" completed projects, put a RAB-wrapper around them,
and then sell them onto the pension and life funds.
He explained that this would "would capture
the returns from the assumption of the financing requirement,
and therefore limit abnormal profits to the construction phase".
If however there was not an infrastructure bank he said that another
approach would work.
The obvious starting point is to separate out the
PFIs into three separate contractual parts: the construction phase,
the operating phase and the financing phase after project completion
[...]
For the financing phase (strictly the refinancing
phase after project completion), there could be a separate contract,
with an associated cost of capital and a repayment profile. This
could be subject to a guarantee that the revenues will in fact
be forthcoming. [...]
The advantage of the separation out of the contracts
is that it provides a focus and opportunity to zoom in on refinancing
on project completion. If the private sector demands a high return
on the completed asset, then one of two possibilities arises:
either the government can clarify the commitment to remunerate
the capital; or the government itself could buy-in the completed
asset at a lower cost of capital (or some part of it).
Once separated out, the capital cost can be accounted
for in the same way as the utility RABs - for that is in effect
what they have become.[217]
120. Some evidence also mentioned the possibility
of using Local Asset Backed Vehicles (LABVs) to allow local authorities
to use their assets to attract long-term investment from the private
sector. Skanska explained that the LABVs "are dependent upon
the public sector having appropriate land or other assets to transfer
into the joint venture vehicle and upon the market value of the
land/asset that is available".[218]
KBR International Government & Defence believed that LABVs
provided "attractive option for outsourcing of non core activities
of government departments". They suggested this form of additional
financing would:
- Encourage a business management
perspective where contracting authority and contractor work together
to a common goal rather than creating an adversarial contracting
environment. [...]
- Avoid the lengthy procurement periods and start
up costs of PFI models
- Create a business relationship that can cope
with a changing and dynamic environment.[219]
Equility Capital suggested an alternative form of
financing which would be done "by employing lease-based funding
programmes". They explained that the debt "will appear
on the balance sheet but, as the funding is lease based, so will
the asset." Also "at the end of the lease period the
asset reverts in its entirety to the borrower". As the cost
of capital would be much closer to the cost of government gilts
they calculated the change would release significant savings.[220]
121. The Treasury
should consult on the possibility of using other financing models,
including the Regulatory Asset Base (RAB) and Local Asset Backed
Vehicles (LABV), as a way of financing capital projects in competition
or in preference to PFI.
143 National Audit Office, Private Finance Projects:
A Paper for the Lords Economic Affairs Committee, October
2009, p48, para 4.10 Back
144
David Heald and Alasdair McLeod, Constitutional Law, The Laws
of Scotland: Stair Memorial Encyclopaedia: Public Expenditure,
2002, para 502. Back
145
David Heald and Alasdair McLeod, Constitutional Law, The Laws
of Scotland: Stair Memorial Encyclopaedia: Public Expenditure,
2002, para 502. Back
146
HC Deb, 12 November 1992, col 998 Back
147
HM Treasury, Private Finance: Overview of progress, News
release 118/94, 8 November 1994 Back
148
HM Treasury, Private Opportunity, Public Benefit Progressing
the Private Finance Initiative, November 1995 Back
149
HM Treasury, Meeting the Investment Challenge, July 2003,
p35, 3.30 Back
150
Ev w42 Back
151
Ev w33 Back
152
Ev 37 Back
153
Q 108 Back
154
Ev w19 Back
155
National Audit Office, Private Finance Projects: A Paper for
the Lords Economic Affairs Committee, October 2009, p48, para
4.10 Back
156
HM Treasury, PFI value for money quantitative assessment spreadsheet
Back
157
HM Treasury, Quantitative Assessment User Guide, March
2007, p16, A55 Back
158
Mott MacDonald report for HM Treasury, Review of Large Public
Procurement in the UK, July 2002 Back
159
Public Money and Management: Pollock, Price & Player , An
Examination of the UK Treasury's Evidence Base for Cost and Time
Overrun Data in UK Value-for-Money Policy and Appraisal, April
2007 Back
160
KPMG report for HM Treasury, Report on Identifying and Measuring
the Differential Tax Receipts from Private Finance Initiative
Schemes for the Purpose of Economic Evaluation against a Public
Sector Comparator, 2002 Back
161
HM Treasury, Budget 2011, p2 Back
162
In 2010 Serco Corporation Tax was 1.3% of revenue and Balfour
Beatty's was 0.8%. Source: 2010 Accounts, Income Statement. Back
163
C&AG's report, PFI: The STEPS Deal, HC 530 2003-04,
p4-5, para 11-13 Back
164
ACCA Research Report no.84 - Edwards et al, Evaluating
the Operation of PFI in Roads and Hospitals , 2004, p.99 Back
165
Ev w125 Back
166
National Audit Office, Private Finance Projects: A Paper for
the Lords Economic Affairs Committee, October 2009, p46, para
4.7 Back
167
Ev w39 Back
168
Ev 32 Back
169
Institute of Civil Engineers, A National Infrastructure Investment
Bank: An ICE briefing and discussion paper, December 2009, p2 Back
170
Ev 40 Back
171
Ev 32 Back
172
Office for Budget Responsibility, Budget Forecast: June 2010,
p95, C.54-C.55 Back
173
Ev w67 Back
174
Ev 41 Back
175
HM Treasury, Spending Review 2010, Executive Summary, p5 Back
176
Committee analysis of HM Treasury, PFI signed projects list, March
2011 Back
177
Q 3 Back
178
Q 42 Back
179
Q 118 Back
180
OBR, Fiscal Sustainability Report, July 2011, p42, para 2.50 Back
181
Efficiency Review by Sir Philip Green, Key Findings and Recommendations Back
182
HM Treasury: Press Notice, Treasury launches pilot to achieve
savings in PFI projects,16 February 2011 Back
183
Q 62 Back
184
Q 63 Back
185
Q 62 Back
186
Q 115 Back
187
C&AG's report, The performance and management of hospital
PFI contracts, HC 68, 2010-11,
Back
188
Q 62 Back
189
Ev w25 Back
190
Public Accounts Committee, Twenty-Second Report of Session 2002-03,
PFI refinancing update, HC 203, p5, para 1 Back
191
C&AG's report, Lessons from PFI and other projects,
HC 920, 2010-11, p9, para 23 Back
192
Richard Abadie, as Head of Private Finance Unit, HM Treasury said:
"we do want to focus on understanding what an appropriate
price is for the primary market. We are seeing primary returns
around the 14% to 15% level, and put simply, we think that those
primary returns are high compared to the secondary yields. [...]
Government is watching with interest to see when primary returns
reduce" (City and Financial Conference, 8 November 2005). Back
193
See, for example, the 2010 annual reports of Carillion, John Laing,
Balfour Beatty or HICL. Back
194
Ev w32 Back
195
Q 67 Back
196
Ev w115 Back
197
Ev 38 Back
198
Ev w40 Back
199
C&AG's report, Improving the PFI tendering process,
HC 149, 2006-07, p4, para 4d Back
200
Q 30 Back
201
Q 31 Back
202
Q 1 Back
203
Q 2 Back
204
Ev 40 Back
205
Q 40 Back
206
Ev w28 Back
207
Q 60 Back
208
Q 11, HC (2010-12) 1326, 28 June 2011 Back
209
Q 7 Back
210
Policy Exchange, Delivering a 21st Century Infrastructure for
Britain, September 2009, p 9-10, Recommendation 7 Back
211
Q 53 Back
212
Ev w50 Back
213
Q 56 Back
214
Q 49 Back
215
Ev 41 Back
216
Q 20 Back
217
Ev 41 Back
218
Ev w40 Back
219
Ev w72 Back
220
Ev w126 Back
|