5 Capacity Mechanism
156. The aim of a capacity mechanism would be
to provide an insurance policy to reduce the likelihood of future
blackouts and to ensure a reliable electricity supply to consumers.
At the moment, generators are only paid for the electricity that
they produce. A capacity mechanism would change this by making
payments for the availability of capacity in order to ensure
there is sufficient spare capacity on the system to avoid blackouts.
Need for the mechanism
157. DECC believes there is no immediate threat
to the security of electricity supply, with 83 GW of generating
capacity available at the end of 2010 compared to a peak demand
of 61 GW.[184] Beyond
this its analysis suggests a risk to security of supply as a large
amount of existing generating plant is due to close while an increasing
amount of low-carbon, intermittent or inflexible generation is
needed to meet the UK's carbon reduction targets. Renewables and
nuclear plant have low running costs, and future fossil fuel plant
such as gas will therefore only run to supplement this generation.[185]
This will create uncertainty of revenues for fossil plant, and
DECC is concerned that this could lead to under-investment and
uncomfortably low levels of reliable capacity.[186]
158. Although the central scenario in DECC's
modelling indicated that a capacity problem would not occur until
the 2020s, its "stress test" (i.e. worst case scenario)
suggested that a capacity problem could occur in the second half
of this decade.[187]
DECC argued that this uncertainty meant the legal framework for
a capacity mechanism needed to be put in place as soon as possible,
so that the first capacity auction could be held in 2014 for capacity
to be in place "by 2015/2016" if necessary.[188]
Its modelling suggested that "in some years" we could
see blackouts affecting up to 2.5 million homes unless action
was taken.[189]
159. The Minister told us that because DECC does
not envisage the mechanism being needed "for a couple of
years at least", the detail of its operation does not need
to be finalised.[190]
Chapter 3 of the draft Bill (Clauses 20 to 30) therefore only
provides enabling powers for the Secretary of State to design
and introduce a capacity market in Great Britain.[191]
With many details of the market still lacking, our scrutiny of
the proposals embodied in the draft Bill was unavoidably limited.
However, we do have some high-level comments based upon the evidence
we received during this inquiry.
Uncertainty over the mechanism
160. The draft Bill would give the Secretary
of State powers to introduce a capacity market, but these would
only be used if and when Ministers decide a market is needed.
This decision will be based on analysis provided by the System
Operator - National Grid - and possibly other technical experts
including Ofgem.[192]
Although not all of our witnesses were convinced that the case
has been made for a Capacity Mechanism, others were supportive.[193]
In any case, there was general agreement that now the Government
has proposed the mechanism, clarity is needed to avoid a hiatus
in investment in new capacity.[194]
Ian Marchant of SSE, for example, told us that:
the biggest issue at the moment is the uncertainty:
effectively, the Government has created a known unknown. They
have said there will be a capacity mechanism but not what it will
be, and once you've gone down that road you've got to get it certain
quickly so that any investments can be decided, because boards,
my board included, will say, "We will wait until we see what
that mechanism is." We have created a situation where we
now need to get a capacity mechanism in.[195]
161. The Secretary of State told us that DECC
has "tried to give a very clear signal" that there need
not be such a hiatus, because any capacity built since publication
of the draft Bill will be categorised as "new" in any
future capacity auction.[196]
Nevertheless, there is a risk that the need for a capacity mechanism
may now become a self-fulfilling prophesy - that an investment
hiatus caused by policy uncertainty will deliver the precise capacity
problem that DECC aims to avoid.
162. We heard that a standard of reliability
could provide helpful clarity over what a capacity market would
be aiming to achieve.[197]
This is the approach taken in some US markets, where decisions
on the required level of capacity are based on a minimum standard
of reliability, such as "interruption of electricity supplies
due to insufficient capacity on no more than 0.1 days per year".[198]
Indeed, National Grid, who would run the proposed auction, told
us that "one would have to define what output we are trying
to have" and that an "objective way of discussing security
of supply would be useful to everybody".[199]
163. The Secretary of State told us that he is
"open-minded about the role of targets", and DECC is
considering defining and using an enduring "reliability standard"
to inform Ministers' decision on the amount of capacity needed.
[200]
However, in Annex C to the EMR Policy Overview, DECC also said
that "if we did adopt a reliability standard, we would expect
Ministers to retain scope for their annual decision on the amount
of capacity to contract for to vary from the reliability standard
to ensure that costs and reliability can be balanced". This
would introduce a political element into the decision making process,
which could reduce certainty for investors.[201]
164. The deferral of a firm
decision to implement a capacity market creates uncertainty and
risks a hiatus in investment. The Energy Bill should be based
on a clear Government position on the circumstances in which a
market will be introduced, and how this will be reviewed and updated
over time. The Government should set out an enduring reliability
standard, which, along with a decarbonisation target for electricity,
would provide a clear framework for the System Operator to work
within when operating a capacity market.
Design of the mechanism
165. There are three steps involved in the design
of capacity mechanisms:
a) Analyse the risks to reliability that the
mechanism will need to address;
b) Determine the products or services that the
mechanism will need to procure; and
c) Decide how the required products or services
should be valued.
166. We heard that the focus of debate to date
has been on the third step: whether or not the System Operator
should run a market-wide auction for provision of future capacity
or procure "strategic reserve" capacity.[202]
However, the first two steps are also important because we cannot
assume that our traditional approach to ensuring reliability will
be appropriate in the future, for example in the case of an electricity
system with a high proportion of intermittent renewable generation.[203]
167. In Annex C of the EMR Policy Overview, DECC
said that the Capacity Market would be a competitive auction,
run by the System Operator, based on a forecast of future peak
demand and its role would be to deliver a total required volume
of capacity defined by Ministers.[204]
The European Climate Foundation told us that this "total
volume" approach is based on the assumption that system reliability
is most under stress at the time of peak demand, and that delivering
a total volume of capacity that sufficiently exceeds peak demand
will ensure reliability at all times.[205]
168. This assumption may not hold true for our
future electricity system. Modelling for the south of Great Britain
has suggested that the greatest challenge to reliability by 2030
will arise not at times of peak demand, but when consumer demand
and the varying output of intermittent renewable generation are
changing in opposite directions.[206]
This could occur at any time and to the greatest extent when demand
is increasing to a maximum while intermittent generation is reducing
to a minimum, or vice versa. The flexibility of the remaining
capacity on the system will thus become at least as important
as its total volume.[207]
Other witnesses have agreed that the characteristics of capacity,
such as how long it takes for it to respond and then remain available,
are crucial and need attention.[208]
169. DECC has stated that the market will not
specifically contract for flexible capacity.[209]
It anticipates that the electricity market will continue to provide
adequate signals to bring forward the right mix of flexible capacity,
and that the existing balancing mechanism will continue to ensure
moment-to-moment system balancing through services such as Short
Term Operating Reserve (STOR). However, DECC also said that it
intends to consider this further when developing the design of
the Capacity Market.[210]
Indeed, the Minister told us that "the capacity mechanism
[...] is actually something that needs to represent flexibility."[211]
170. In our original EMR inquiry we said that
the Government needed to analyse more fully the potential need
for flexible capacity and demand-side measures at all times, not
just at times of peak demand.[212]
In its White Paper of July 2011, DECC committed to outlining its
electricity systems policy in summer 2012, "focusing on challenges
around balancing and system flexibility". It is very unsatisfactory
that this policy was not published alongside the draft Bill to
be available for our pre-legislative scrutiny.
171. We are extremely concerned
that the capacity market proposals are based upon out-dated assumptions
and an insufficient analysis of the future risks to reliability.
We recommend that the Government undertakes much clearer analysis
of the problem that the capacity market is trying to solve, particularly
the integration of the large volume of intermittent generation
that is likely to be required to decarbonise our electricity supplies,
and of the role capacity payments can play in furthering demand
side response and reduction measures. The enabling legislation
in the Energy Bill must be able to meet our future reliability
challenges.
Minimising costs for consumers
172. At the initial consultation stage, the Government
stated a preference for a "strategic reserve" capacity
mechanism but subsequently decided, in light of representations
from industry and elsewhere, that a market-wide mechanism would
be better.[213] However,
RWE npower[214] has
since told us that a reserve would be more than ten times cheaper
- a cost of £300-650m over the period 2015-25 compared to
£7.5bn for a market-wide mechanism.[215]
DECC's own analysis, as published in its Capacity Mechanism Impact
Assessment, also found a strategic reserve to be cheaper. The
estimated net cost was £1.1bn over the period 2010-2030[216]
compared to a business as usual scenario, whereas the estimated
net cost of a capacity market was £2.5bn.[217]
However, DECC did not believe that these costs were representative
of the impacts of each mechanism, and so also compared them qualitatively.
173. One of DECC's key qualitative concerns,
not modelled in the net costs, was the "slippery slope"
problem.[218]
This would occur if, by preventing high prices at times of system
stress, the strategic reserve reduced the market-based incentive
for investment in new capacity. As we discussed in our previous
inquiry on EMR, more and more capacity would then be required
in the reserve to ensure the reserve remained effective.[219]
174. Evidence we received suggested that if the
proposed capacity market delivers insufficient flexible capacity,
there is a risk that the System Operator would have to use additional
mechanisms to ensure reliability, leading to unnecessarily high
costs.[220]
The European Climate Foundation told us that the Energy Bill should
include a mandate for the Regulator to establish an incentive
framework for the System Operator to minimise the costs of delivering
reliability.[221]
175. We recognise that a more
thorough assessment of cost-effectiveness must await the publication
of detailed capacity market proposals. DECC should conduct further
analysis on the costs of the capacity market to ensure it is not
significantly higher than alternative options such as a strategic
reserve. The Government should clarify how the Energy Bill will
ensure that the capacity delivered by auctions will have the appropriate
characteristics, such as flexibility, and how this relates to
the System Operator's existing system balancing role, in order
to ensure that costs are minimised.
Technology options for providing
capacity
176. Clause 20(3) of the draft Bill states that
"providing capacity" to the capacity market means providing
electricity or reducing demand for electricity. The market would
be open to new or existing generating capacity as well as non-generation
approaches such as demand response, storage and interconnection.
GENERATION TECHNOLOGIES
177. In terms of generation technology, we heard
two conflicting stories of what EMR will achieve: some said not
enough gas power stations; some said too many. We discuss the
future role of gas further in Chapter 9 (paragraphs 221 - 223).
178. Intergen, an independent generator operating
gas-fired power stations, told us of a range of issues that need
to be addressed for the capacity mechanism to support both existing
and new generation.[222]
Among these, it highlighted that to build a new combined cycle
gas turbine takes around seven years - three to gain consent,
one to tender and contract, and three to construct. If the Government
identifies a need for new generation capacity this decade, Intergen's
evidence suggests that it is unlikely to be brought about by capacity
auctions that may or may not be held from 2014, as the Government
currently suggests.
179. Stag Energy, a company with interests in
gas generation and storage, argued that it will be challenging
to maintain a 15 - 20 % capacity margin without the construction
of 12 - 15 GW of new gas generation over the coming decade.[223]
Its analysis showed that existing coal and gas plant has "much
higher running costs" than new combined cycle or open cycle
gas turbines. These new, more flexible plant are more expensive
to build but have a lower overall running cost at reduced levels
of demand. Stag Energy warned that the proposed capacity market,
with its single clearing price model, risks penalising new, more
efficient plant while rewarding existing plant.[224]
180. Indeed, experience in the USA suggests that
while capacity markets are attractive to existing resources, they
do not encourage investment in new generation. The New England
2010 Annual Report notes that with the looming possibility that
some of the region's older resources will retire, the ability
of its capacity market to attract timely investment in new generation
"remains largely untested".[225]
181. The Committee on Climate Change has said
that investment in around 10 GW of new unabated gas generation
over the next two decades, and a total gas-fired capacity of 30
GW in 2030, would have an important role in balancing intermittent
renewable generation by generating at low annual load factors
(less than 10% on average in 2030). However, the Committee has
expressed concern that EMR proposals - particularly the Emissions
Performance Standard - will allow a greater role for gas generation.[226]
It said that if 30 GW of gas plant were to generate at baseload
(i.e. the majority of the time) in 2030 instead of only as balancing
plant, average emissions would be 200 gCO2/kWh - well
over what we need them to be to meet our statutory carbon budgets.
182. A number of our witnesses shared the concern
that EMR, as embodied by the draft Bill, will lead to a "dash
for gas" that will make it harder to achieve our statutory
emissions reduction targets.[227]
183. As we recommend in paragraph
223, it is vital to have an understanding of the likely impact
of EMR of the future role for gas generation. DECC should conduct
modelling work to assess the combined impact of the capacity market
and the EPS on emissions and security outcomes under different
scenarios. This should include both a "dash for gas before
2015" scenario and a "no new gas before 2015" scenario
184. Related to the issue of new investment in
generation Stag Energy highlighted the need for gas storage, both
to ensure security of supply and to minimise fuel price volatility.[228]
In our energy security inquiry, we concluded that the UK needs
to significantly increase its gas storage capacity.[229]
We recommend that the Government, in its forthcoming Gas Strategy,
considers the interrelationship between electricity market reform
and the capabilities of the gas infrastructure, in particular
the potential need for more gas storage.
NON-GENERATION TECHNOLOGIES
185. In the supporting documentation to the draft
Bill, DECC says it is keen that non-generation technologies and
approaches, such as demand-side response, storage and interconnected
capacity, "can play a fair and equivalent role to generation
in a DSR Capacity Market".[230]
However, many of our witnesses criticised the draft Bill and its
supporting documentation for its lack of detail on these approaches.[231]
186. Friends of the Earth told us that:
it is unlikely that the existence of a capacity market
alone will provide sufficient incentive for investment in innovative
storage and DSR technologies to be developed to the point that
they can deliver capacity with complete certainty and be bid into
a capacity market auction at a cost that can compete with established
fossil fuel supply technologies. Getting technologies to this
point requires significant R&D, early deployment support and
preference within the capacity market.[232]
187. Green Alliance reported that experience
from the USA demonstrated the risk that the market would not incentivise
innovative technologies like demand-side response. It said that
in the USA's PJM market:
much of the capacity payments initially went to existing
fossil power stations and a 'clean first' priority system had
to be introduced to ensure that DSR was able to compete fairly.
As with demand reduction, given the immature nature of the demand
response market, it is likely to be necessary to proactively seek
out demand response to ensure that the maximum economic level
of DSR is developed.[233]
188. A number of our witnesses agreed that, as
innovative technologies, DSR and storage would need support to
enable them to develop and compete in the market.[234]
This could be achieved by amending the Bill to require the System
Operator to procure minimum volumes in the capacity auction, and/or
to seek out and prioritise them over other approaches.[235]
Such support would help kick-start
the market in the provision of these services and ensure the System
Operator develops the necessary systems and expertise to exploit
the benefits of demand response.[236]
RWE npower told us that it is vital that the legislation sets
out a clear mechanism for the demand-side to contribute, because
otherwise the £12bn that energy companies will invest in
smart meters (ultimately at consumers' expense) will be a substantial
lost opportunity.[237]
189. However, two of our witnesses did not think
extra measures to support demand-side measures were necessary
in the Bill, since it is already complex and because demand-side
policies exist elsewhere already.[238]
Professor Newbery also warned us of "unsubstantiated claims
that all demand-side is necessarily cost-effective".[239]
190. On storage specifically, the Electricity
Storage Network (ESN) highlighted that existing legislation does
not explicitly define or address the role of storage in the electricity
market, and that this causes confusion and uncertainty about its
treatment.[240]
The ESN suggested that it is not appropriate to include electricity
storage simply as a generation activity, as it can provide other
services such as absorbing power at times of excess production
by wind and other intermittent generation. ABB, with experience
of deploying the UK's first battery energy storage device, also
identified "significant legal challenges" that need
to be overcome in relation to the treatment of energy absorption
and resupply to the grid.[241]
191. As innovative technologies,
demand-side response and storage technologies should be recognised
and defined explicitly in the Energy Bill. Support for innovation
is given to the supply-side, for example by the banding of the
Renewables Obligation, and the Bill should provide similar support
to demand-side and storage technologies. DECC should investigate
the legislative and other barriers to storage identified by our
witnesses, and remove any that prevent it from competing fairly
in the market.
192. Witnesses warned that it is unclear how
the proposed capacity market would work with the move to a more
integrated European electricity market, and potentially larger
balancing areas. Simon Skillings told us that if a neighbouring
market does not have a margin of spare capacity, "all that
happens is that you need to keep running to stand still, because
every time you build something to get your margin, they will shut
something next door to keep their price going up".[242]
This is another area the Government said it is considering as
part of its detailed design work for the capacity market.[243]
193. The Government should clarify
how the capacity market will be made compatible with increased
interconnection and the move to a more integrated European electricity
market.
184 DECC, Electricity Market Reform: Policy Overview,
Annex C, Electricity Market Reform: Capacity Market-Design and
implementation update, May 2012, p 4 Back
185
Steggals W, Gross R, Heptonstall P, Winds of change: How high
wind penetrations will affect investment incentives in the GB
electricity sector, Energy Policy, 2011, Vol:39, Pages:1389-1396 Back
186
DECC, Electricity Market Reform: Policy Overview, May 2012, p
15 Back
187
DECC, Electricity Market Reform - Capacity Mechanism , Impact
Assessment, IA No: DECC0076, 15 December 2011 Back
188
DECC, Electricity Market Reform: Policy Overview, May 2012, p
16 Back
189
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, p 5 Back
190
Q 399 Back
191
Note that capacity payments already exist for Northern Ireland,
as part of the all-Irish Single Energy Market Back
192
DECC, Electricity Market Reform: Policy Overview, May 2012, p
16 Back
193
Ev 178, Ev 206, Ev 151, Ev 193 Back
194
Ev 206, Q 1 [Ms Vaughan], Q 2 [Mr Marchant] Back
195
Q 2 [Mr Marchant] Back
196
Q 528 [Secretary of State] Back
197
Ev w143 Back
198
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, p 10 Back
199
Q 338 Back
200
Q 386; DECC, Electricity Market Reform: Policy Overview, Annex
C, Electricity Market Reform: Capacity Market-Design and implementation
update, May 2012, p 10 Back
201
Ev w64 Back
202
Ev w143 Back
203
Ev w143 Back
204
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, pp 5-11 Back
205
Ev w143 Back
206
Ev w143 Back
207
Ev w143 Back
208
Ev w14, Ev 193, Q 140 [Professor Newbery]; Oral evidence taken
before the Energy and Climate Change Committee on 25 January 2012,
HC (2010-12) 1781-i, Q 2, Q 29 and Q 30 [Ms Kruisdijk] Back
209
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, p 11 Back
210
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, p 11 Back
211
Q 538 Back
212
Energy and Climate Change Committee, Electricity Market Reform,
para 192 Back
213
Oral evidence taken before the Energy and Climate Change Committee
on 25 January 2012, HC (2010-12) 1781-ii, Q 116 (Mr Hendry) Back
214
Memorandum submitted by RWE to the Energy and Climate Change Committee,
Electricity Market Reform Technical Update, EMRT 07, section 15 Back
215
Present Value 2015 to 2025, real 2010. Back
216
DECC states that "all costs occur between 2024 and 2030 because
that is when a Capacity Mechanism would be triggered under the
central scenario." Back
217
DECC, Electricity Market Reform - Capacity Mechanism , Impact
Assessment, IA No: DECC0076, 15 December 2011, p 22 Back
218
DECC, Electricity Market Reform - Capacity Mechanism , Impact
Assessment, IA No: DECC0076, 15 December 2011, p 36 Back
219
Energy and Climate Change Committee, Electricity Market Reform,
p 51-52. Back
220
Ev w143 Back
221
Ev w143 Back
222
Ev 193 Back
223
Ev w14 Back
224
Ev w14 Back
225
ISO New England, 2010 Annual Markets Report, 3 June 2011, p 21
Back
226
Committee on Climate Change, 27 March 2012, Public letter from
Lord Adair Turner to the Secretary of State Back
227
Ev 137, Ev 172, Ev w94, Ev 187, Ev w133 Back
228
Ev w14 Back
229
Energy and Climate Change Committee, Eighth Report of Session
2010-12, the UK's Energy Supply: Security or Independence?
HC 1065, October 2011 Back
230
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, p 16 Back
231
Ev 137, Ev w37, Ev w50 (Association for the Conservation of Energy),
Ev 172, Ev w86, Ev 187, Ev w142, Q 2 [Mr Marchant] Back
232
Ev 137 Back
233
Ev 172 Back
234
Q 135 [Mr Skillings] Back
235
Ev 127, Ev 137, Ev w37, Ev 172, Ev w143 Back
236
Ev w143 Back
237
Ev 178 Back
238
Q 135 [Professor Newbery], Q 235 [Ms Kelly] Back
239
Q 135 [Professor Newbery] Back
240
Ev w118 Back
241
Ev w86 Back
242
Oral evidence taken before the Energy and Climate Change Committee
on 24 January 2012, HC (2010-12) 1781-i, Q 7 [Mr Skillings] Back
243
DECC, Electricity Market Reform: Policy Overview, Annex C, Electricity
Market Reform: Capacity Market-Design and implementation update,
May 2012, p 16 Back
|