Introduction
1. The 2012 London Olympic and Paralympic Games was
the largest event ever held in the United Kingdom, and one of
the largest international sporting events ever held. Overall,
its organisation and execution was a triumphant success. It is
estimated that 10,500 competitors took part, the workforce across
all venues was around 200,000 people and 8.8 million tickets were
sold. [1] However,
the running of the Games was thrown into serious doubt two weeks
prior to the Opening Ceremony when the principal security contractor,
G4S, suddenly announced that it would not be able to fulfil its
contractual duties. In the following days leading up to the Opening
Ceremony, G4S's inability to deliver to its contract became the
largest challenge facing the London Organising Committee of the
Olympic and Paralympic Games (LOCOG).[2]
2. Thanks to robust contingency planning from an
early stage, and the recognition by LOCOG, Home Office officials
and the police that the problem might be far worse than G4S initially
suggested, arrangements were quickly made for armed forces personnel
to fill the gap left by G4S's shortfall. The security operation
at the Games passed off without any significant problems, and
the contribution of the armed forces and volunteers to the Games
was widely praised. It was just as well in the circumstances that
the military and police were able to be made available in view
of the failure of G4S.
3. G4S's failure to deliver on this occasion is a
significant matter of public concern. Uncertainty remains over
exactly how much of its £237 million payment under the contract,
including a £57 million management fee, G4S will seek to
claim. The contract provides for various penalties and remedies
in the event of G4S's failureLOCOG only pays for hours
delivered, it has the right to retain a proportion of the management
fee if G4S fails to achieve a specified proportion of the scheduled
hours, and G4S must meet the cost incurred in bringing in alternative
providers, such as the armed forces.[3]
However, there appear to be differences of opinion between LOCOG
and G4S about the level of service which was actually provided
during the Games.
4. The issue is also especially important because
of the lessons to be learned for the planning of future major
events, particularly from the effective contingency planning by
the Home Office and LOCOG which was activated successfully at
a very late stage in the process.
5. Perhaps the most significant area of public concern
flows from the growing role that G4S plays in the criminal justice
system, and in public contracts more widely. The company currently
holds contracts with the Home Office and police forces worth £585.2
million. These include the running of Brook House Immigration
Removal Centre (£53.5 million over five years), the provision
of accommodation, transport and related services for asylum seekers
under the COMPASS project,[4]
the provision of police custody suites for three forces, and the
provision of forensic medical services for another 11.[5]
G4S also holds a major contract to deliver middle and back office
services for Lincolnshire police, worth £229.7 million over
ten years, which covers a wide range of services including HR,
finance, custody services and fleet management. As Nick Buckles,
Group Chief Executive Officer of G4S plc, told us
"we deliver about four out of five notes in
your wallet, we are the largest cash-carrying company, we read
four of ten of your meters, we run your prisons, we run your hospitals,
so we do a large number of jobs to help British society".[6]
In this context, the performance of G4S on a contract
as high-profile as the Olympics is a significant matter of public
concern.
Early warnings
6. The
venue security contract was awarded to G4S in December 2010. The
company was originally required to manage a workforce of 10,000,
of whom 2,000 would be new staff recruited and trained by G4S
and the remaining 8,000 would be from other sources. Towards the
end of 2011as more details, such as the schedule of events
were finalisedit became clear that a much bigger workforce
would be required. In December 2011, a deed of variation was signed,
increasing the total size of the security workforce to 23,700,
consisting of 10,400 staff supplied by G4S, 5,000 armed forces
personnel, 3,000 volunteer Games Makers recruited by LOCOG, 3,700
students recruited through a programme called Bridging the Gap,
1,000 guards employed by Wilson James (another security company)
and various other, smaller groups of staff.[7]
7. The awarding of the venue security contract was
not the only involvement G4S had in the Olympic security programme.
The company was involved in planning the security operation for
the London 2012 bid. In the early stages after the bid was awarded,
it helped to design the security operation, and then won the contract
which resulted from that design.[8]
Once it had won the contract, the company paid £5 million
to LOCOG for marketing rights, which allowed it to advertise its
connection with the Games.[9]
8. LOCOG and the Home Office were concerned about
the development of the security operation from an early stage;
naturally so, given its unprecedented scale. The concerns were
not focused on G4S specifically, but on the overall operation
including Games Makers, the police and the armed forces. The Home
Secretary told us that she commissioned Her Majesty's Inspectorate
of Constabulary to conduct a review of the security arrangements
on 25 August 2011, to determine whether they were on track to
deliver a safe and secure Games.[10]
The Report, which was produced on 30 September, identified some
potentially serious problems. LOCOG was 18 months behind in the
production of security policies and standard operating procedures,
which was having a knock-on effect of LOCOG's delivery of venue
security plans. This, in turn, was causing delays in establishing
an accurate picture of the number of staff who would be required.
The Report noted that it was usual to devise security plans first,
and to determine the number of staff required on the basis of
the plans, but the size and scale of the Olympic security operation
meant that LOCOG had adopted a concurrent rather than a more conventional
linear approach to security planning.[11]
Sir Denis O'Connor, HM Chief Inspector of Constabulary, summed
up the findings:
"This plan is not detailed enough at this point.
[LOCOG] have had a lot of other things to do. It is now time to
have a detailed plan so that the numbers make sense, the roles
are clear, and you can recruit and train people with an end in
mind".[12]
LOCOG had lead responsibility for dealing with the
Inspectorate's recommendations, but responsibility for venue security
planning was shared with the Home Office, the Centre for the Protection
of National Infrastructure and the police, with the Venue Security
Delivery Board as the principal decision-making forum.
9. The HMIC Report in September also noted that:
"the workforce project requires frequent and
intrusive performance monitoring across all four of the interdependent
workstreams (demand, source, train and deploy)".[13]
Charles Farr, Director-General of the Office for
Security and Counter-Terrorism at the Home Office and Chair
of the Olympic Security Board, and Paul Deighton, Chief Executive
of LOCOG, described to us in some detail the new monitoring arrangements
which were put in place in response to this recommendation.[14]
10. HMIC conducted another review in February 2012
to follow up its recommendations.[15]
The Review Team was satisfied that LOCOG had plans in place to
resolve all the problems identified in its earlier Report, although
some standard operating procedures, which were needed before some
of the training for security staff could be developed, were still
outstanding. Sir Denis told us that the Inspectorate had been
satisfied that LOCOG had a plan, but they identified residual
risks that he suggested were in "the nature of the business".[16]
One of these was the delivery of the manguarding capability which
was, by the nature of the task, a risk area. Nobody has suggested
that the delays in producing venue security plans were in any
way responsible for the failure of G4S to deliver its contract.
Mr Deighton rejected this suggestion in unambiguous terms when
it was put to him.[17]
11. In addition to the two HMIC Reports commissioned
by the Home Office, LOCOG commissioned two reports of its own,
an internal audit report, prepared by staff of KPMG reporting
to the LOCOG Head of Internal Audit, in December 2011 and a report
by Deloitte in May 2012.[18]
The Deloitte report was commissioned because LOCOG was concerned
about the quality of the management information it was getting
from G4S and about the way that G4S was communicating with applicants.[19]
Deloitte identified serious problems with G4S's management information
and their overall operation:
"The current management information provided
by G4S is fragmented, inconsistent and of variable levels of integrity
in respect of sources, ownership and management ... it is difficult
to offer a high degree of confidence that end data figures provided
in final reports to LOCOG provide an accurate picture of reality".[20]
"It appears that the Recruitment programme is
currently failing to generate the required throughput of quality
candidates to the Pass Complete stage ... There is a significantly
higher attrition rate than anticipated by the G4S training team
between the Pass Complete and Training Attendance stages ... Training
delivery slippage ... is generating concerns around capacity".[21]
The Report also criticised G4S's communications with
its applicants and recruits, indicating that its approach lacked
detail, did not provide an understanding of the key messages which
needed to be communicated at each stage, and was failing to address
high attrition rates by engaging effectively with applicants.[22]
12. This cannot have come as welcome news to LOCOG,
barely two months before the start of the Games. Mr Buckles told
us that G4S implemented all of Deloitte's recommendations within
a week: "put in a new governance structure, put in a new
management information reporting template and make sure the meetings
were more formally organised on a weekly basis".[23]
G4S and LOCOG agreed a new set of management data and a new format
for presenting it.[24]
13. Reports
commissioned by LOCOG in the months preceding the Games indicated
clearly that there were problems with G4S's recruitment, training
and communications. They also found that the management information
presented to LOCOG by G4S were fundamentally unreliable. G4S,
meanwhile, continued to insist that it was in a position to deliver
its contract. Although Mr Buckles claims to have acted on all
the relevant recommendations, the final outcome suggests that
the changes to the data G4S were reporting to LOCOG were more
presentational than substantial. The data were at best unreliable,
if not downright misleading, and the most senior personnel in
the company must take full responsibility for this.
14. Assistant Commissioner Chris Allison, the senior
Metropolitan Police officer in charge of Olympic security, told
us that he had seen only the HMIC reports, not the internal audit
report prepared by KPMG staff or the Deloitte report.[25]
He suggested that this might be because the consultants' reports
were commissioned by LOCOG, a private company, and produced by
private consultants. Similarly, David Taylor-Smith, Chief Operating
Officer of G4S, told us that the company had never been given
access to the internal audit report or the reports by HM Inspectorate
of Constabulary, although it had been given the Deloitte Report.[26]
It is surprising that
the four reports on the Olympic security plan were not shared
more widely among Olympic Security Board members, and it may well
be that, had this been done, the potential scale of the problems
might have been realised sooner. We recommend that the presumption
should be, when planning for major events, that any reports commissioned
from external bodies be shared with all stakeholders.
The problem becomes apparent
15. Although there had been some earlier warnings
that all was not well with the G4S contract, G4S management remained
confident throughout that it was on track to meet its targets,
and all the management information it produced appeared to confirm
this. The scale of the problem with the G4S contract therefore
became apparent very suddenly, 18 months into the contract but
only a few weeks before the Games (see Annex for a detailed timeline
of events). Nobodynot even, it would appear, G4S's senior
managementwas aware of any problem with G4S's recruitment
or scheduling until a meeting of the Olympic Security Board on
Wednesday 27 June, when G4S reported that it was experiencing
"scheduling problems".[27]
This was mainly due, it told the Board, to staff being unavailable
for work until 27 July, the day of the opening ceremony.[28]
The Board was assured that the problem was "small-scale,
resolvable and temporary" and that the total shortfall would
be fewer than 1,000 staff.[29]
16. Over the following days, LOCOG and the Home Office
were given "very strong and very clear" assurances by
G4S that the problem was small and manageable.[30]
However, this did not stop Mr Farr from deciding, subject to ministerial
approval, that it would be necessary to prepare to activate the
contingency plan, and on 28 June a small number of armed forces
personnel from the Military Contingency Force were put on standby
to be ready to step in to help out at the Games at 24 hours' notice.[31]
Mr Farr told us that he was getting indications from other sources
that G4S's operation was not running as smoothly as the company
appeared to believe. He told us that, by 5 July it appeared to
him that G4S was not resolving the problem:
"I was basing this on data we were getting from
the ground, rather than data I was getting from G4S ... I certainly
wouldn't have relied on [information from G4S] by this stage as
a single source of truth".[32]
The Home Secretary spoke to Nick Buckles on 6 July
and met him on 10 July, and on neither occasion did he suggest
that the problem was any more serious than it appeared to be on
27 June. According to Mr Farr, on both occasions Mr Buckles reassured
the Home Secretary that the contract would be fulfilled.[33]
The Home Secretary had been made aware previously of concerns
regarding security arrangements, and indeed had as a result commissioned
the report of the inspector of constabulary back in August 2011
(see paragraph 8). Meanwhile, Ian Horseman-Sewell told Reuters
on 6 July that "We are delivering a London Olympics now.
If there was a similar event going on in Australia, I would be
bullish that we could deliver this at the same time".[34]
17. G4S continued to produce data which appeared
to show that there was not a serious problem. Charles Farr told
us that, on 1 July, he was given data that showed that 37,000
people had passed the G4S interview, 25,000 had been security
screened, 21,000 had been accredited, 14,700 had been SIA trained
and 9,000 were ready to work.[35]
Given these assurances about the absolute numbers already ready
for work and still in the pipeline, it would be understandable
if everybody had accepted the reassurance that this was a minor
and temporary problem, so Mr Farr and ministers therefore deserve
credit for having begun to take contingency action notwithstanding
the assurances which they were still receiving from G4S.
18. It must be noted that at this stage complaints
were emerging about potential employees not being informed about
where they would be deployed, the expectation that they would
pay for their own uniforms unless deployed at a minimum level
by the company (a matter that was in the hands of the company
rather than the employee) and in general a lack of communication
from G4S. We were told that some experienced individuals, including
former police officers, took up other employment because they
were not sure whether G4S was going to make use of their services.
While this may be a part of the general failure which this Committee
is investigating, it also points to extremely poor management
and personnel practices within the company. We have no means
of knowing whether this was specific to the Olympic contract or
reflects general practice in the company.
19. After two weeks of repeated commitments from
G4S that the contract would be fulfilled and that the problems
they were dealing with were temporary,[36]
on 11 July, Nick Buckles and David Taylor-Smith, Chief Operating
Officer of G4S plc, arrived at LOCOG's offices in Canary Wharf
to report for the first time that they were not going to be able
to deliver on the contract. They then travelled to the Home Office,
where a meeting of the Olympic Security Board was due to take
place, telephoning Charles Farr on the way. Mr Farr notified the
Home Secretary before going in to chair the Board meeting.
20. It seems
that the penny finally dropped with G4S management on 3 July,
when Mr Taylor-Smith telephoned Mr Buckles to inform him there
would be a shortfall of staff. Mr Buckles was on holiday at the
time, which suggests that this was something more than a routine
call. But Mr Buckles did not mention the scale of the problem
to the Home Secretary when he spoke to her on 6 July, the same
day on which Mr Horseman-Sewell was boasting recklessly in the
press that G4S would have been more than capable of simultaneously
delivering multiple Olympic security projects around the world.
Neither did Mr Buckles disclose the scale of the problem when
he met the Home Secretary on 10 July. It is clear that by this
stage the Home Office had realised that something might be seriously
amiss, as Charles Farr had already begun to put contingency plans
into place. But it is astonishing that G4S took a further week
to tell its partners how bad things were.
The contingency plan
21. Following the Olympic Security Board meeting
on 11 July, the contingency plans which the Home Office had begun
to put in place on 27 June were scaled up. The number of troops
required from the Contingency Force for venue security was increased
from 725 to 3,500. The military contribution was concentrated
at the London venues and those nearby. At football venues outside
London, the police were called in.[37]
The Government had no alternative course of action. As Assistant
Commissioner Allison told us:
"... clearly the Olympics is going to happen,
we can't stop it happening. Unlike other matches that we could
delay for a period of time, we couldn't, it had to happen, so
this is where the contingency plan stepped in".
22. It was only thanks to this robust contingency
plan, which had been developed from an early stage of the planning
process, that London was able to deliver a safe and secure Games.
It was only thanks to the far-sighted planning of officials at
the Home Office, LOCOG and other Olympic security partners that
a catastrophe was averted. However, activating the contingency
plan came at a price for many of those concerned. Lord Coe, Chair
of LOCOG, told us:
"I am acutely aware that I displaced family
plans, the military came to the table, some of them had been on
active duty until relatively recently, some were expecting to
see more of their families during the summer months. I am very
aware of that, and I would put immediately on record my gratitude
to the contingency and the planning, and our ability to actually
draw down. The military became one of the defining characteristics
in the delivery of the Games".[38]
Thousands of Olympic and Paralympic tickets were
made available to members of the armed forces as a gesture of
thanks and G4S has donated £2.5 million to military charities.
23. The
contingency plan was by common consent a huge success. We commend
the contribution that the armed forces made to the Games. Their
ultimate success in delivering a safe and secure Games suggest
that, in the planning of future major events, the military might
more appropriately be considered as a first choice for venue security,
rather than a back-up, with appropriate recognition and reward
for the personnel concerned.
We also
commend the police on the additional contribution which they made
to support Games security and make good the failings of G4S.
G4S's treatment of applicants
and staff
24. The Deloitte Report noted that G4S's communications
with its staff and applicants was one of the weak points of its
operation. Over the summer, the Committee received dozens of submissions
sent by and on behalf of those who had applied to work for G4S.
Although these submissions come from numerous, unconnected individuals,
their accounts are remarkably similar.[39]
Some applicants passed the initial interview and vetting, but
were never allocated training courses. Some applications were
dropped with no explanation, even after the candidate had given
up several days for training and passed successfully. Candidates
were not reimbursed for training until they worked their first
shift, so some people ended up spending several days training,
foregoing other opportunities in some cases, for no reward.[40]
Some applicants were assigned to locations which they could not
possibly get to, with no accommodation offeredone applicant
from Northern Ireland says that he reported for work in Glasgow
as requested but was sent home because G4S had run out of uniforms.[41]
Candidates passed training and accreditation and were even issued
with passes and uniforms but still did not have work allocated
at the start of the Games.[42]
25. Overall, these submissions present a clear and
consistent picture of poor communication between G4S and its prospective
staff, with staff left to make all the effort to stay in touch
and, even then, not being able to get a satisfactory response
from G4S. In fact, Mr Deighton told us that LOCOG was so worried
by the situation that they decided to offer G4S advice and support
with its staff communications, based on LOCOG's own, highly successful,
experience of recruiting volunteer Games Makers.[43]
If further evidence of G4S's poor management of its prospective
recruits were needed, it can be found in the attrition rates (the
proportion of prospective recruits who drop out of the process)
discovered by Deloitte. By April 2012, the overall attrition rate
among staff at the "passed complete" stagethose
who had been successful at interview, had passed initial screening
and were ready for trainingwas 71%. G4S's baseline assumption
had been that it would lose only 31% of applicants at this stage.[44]
26. G4S's poor
communications with its staff and prospective staff was no doubt
a contributory factor to the overall failure of the company's
Olympic contract. It has also had an impact on those prospective
employees who went through the selection, training and screening
process in good faith, only to be left without work at the end
of it because of G4S's poor management. In our view , it is clear
that G4S is under a moral obligation to immediately make generous
ex gratia payments by way of apology to those
applicants who were left out of pocket because they were not offered
work despite successfully completing the training and accreditation
process. We are clear that this was not a fault of either the
Home Office or LOCOG but many people undertook training and made
themselves available not just because work was being offered,
but because they believed that they would be helping in a national
initiative, and the Government should therefore satisfy themselves
that G4S does generously and efficiently meet this moral obligation.
Redress
27. The precise scale of G4S's failure remains a
matter of some dispute between G4S and LOCOG. This use of a mixed
workforce, most of whom were managed by G4S but only some of whom
were employed by them, means that the figures we have been given
are not all calculated on a consistent basis. LOCOG have told
us that on 17 July, a total of 8,119 staff were required but only
7,340 were available, a shortfall of 10%. However, the total number
of staff supplied by G4S was 4,389, approximately 35% less than
the LOCOG demand. It was only through the use of an additional
1,159 military personnel that the overall shortfall was reduced
to 10%.[45]
28. G4S, on the other hand, is keen to focus on overall
numbers and Mr Taylor-Smith told us that G4S had supplied a total
of 11,000 staff against a demand of 10,400.[46]
However, many of these staff only became available during the
transition period between the Olympics and Paralympics. G4S later
clarified that, during the pre-Games period, the shortfall was
32%, and during the Olympics it was 19%. It was only on 13 August,
the day after the closing ceremony, that the number of staff supplied
first met the demand from LOCOG.[47]
29. Establishing the true picture is more complicated
than this, since it depends not only on the total number of staff
provided but on their availability for different shifts at different
venues. Mr Deighton explained that it was possible to cope with
a shortfall of up to 15% at a specific venue at any given time,
for example, by asking staff to work a bit longer or by tolerating
lengthier queues, but that shortfalls of more than 15% created
a problem.[48] We
recommend that LOCOG and G4S quickly seek to reach a common position
on exactly how far short G4S fell from its contractual requirements.
30. G4S has already acknowledged that it is solely
responsible for its failure to deliver the contract, a view which
is shared by LOCOG and others. We agree with Lord Coe, who told
us that "it is difficult to look beyond their inability to
deliver on the contracted number of security personnel that we
were consistently assured by them that they would be able to deliver".[49]
LOCOG has various financial penalties and other remedial rights
at its disposal under the contract and these are now a matter
for discussion between LOCOG and G4S.[50]
LOCOG stopped paying G4S on 13 July, after it had received between
£89 million and £90 million. How much of the remaining
£146 million G4S will receiveand whether there will
be a substantial sum recovered from the £89-90 million already
paidremains to be seen.[51]
It is clearly a matter for LOCOG to negotiate robustly in the
public interest, and Parliament will expect to know the outcome
in due course.
31. When he appeared before us in July, Mr Buckles
gave a number of undertakings:
a) To reimburse police forces for all costs arising
from the shortfall in G4S staff, including accommodation;
b) To reimburse the military for all costs arising
from the shortfall in G4S staff, including accommodation;
c) To forego payment, pay a penalty and forfeit
a portion of their management costs for every shift that was not
covered; and
d) To make an
appropriate charitable contribution for the benefit of police
and armed forces personnel, something which G4S has already done.
[52]
The total cost of these commitments is expected to
generate an overall loss of £50 million to G4S, which was
announced in the company's half-yearly results.[53]
32. Mr Buckles was, however, less contrite when he
appeared before the Committee in September, when he insisted that
G4S would be claiming full payment from LOCOG in line with the
contract provisions. He appeared to think that G4S's contribution
to the Games was being under-valued:
"I am not going to sit here and say we did a
great job. I am nowhere near saying that but what I am saying
is that we did deliver ... We delivered a significant portion
of the contract, and our people ... did an excellent job and played
a very major role in securing these Games".[54]
Mr Buckles also said that G4S would be claiming its
£57 million management fee, or as much of the fee as it was
entitled to under the contract. He argued that the management
fee represented costs that G4S had already incurred in running
the recruitment and training operation, albeit with limited success.[55]
33. The
blame for G4S's failure to deliver on its contract rests firmly
and solely with the company. There is no suggestion that LOCOG,
the Home Office or anybody else involved in the process contributed
to the problem in any way. All our witnesses, including those
from G4S, were in agreement on this point. It is understandable
that G4S, having taken a £50 million loss on the Games, alongside
a significant fall in its share price, should now seek to minimise
the scale of any further losses. But we believe that the company
should look to the bigger picture, and its long-standing relationship
with its biggest client in the UK: the taxpayer. By waiving the
£57million management fee in its entirety, a small fraction
of the £759 million that it receives from the British taxpayer
every year, G4S would send a strong signal to the public that
it is serious about offering fair and reasonable redress when
things go badly wrong. By doing so, the company would accept,
and be seen to accept, responsibility for its failings in respect
of this extraordinary and uniquely high-profile contract, and
therefore draw a line between that failure and the continued fulfilment
by this important UK company of other contacts, both in the UK
and internationally.
34. It is clearly
a matter for LOCOG to examine the legal position and to protect
the public interest as robustly as possible, but Parliament and
the general public would regard it as absurd for the company to
be claiming a management fee which was clearly negotiated on the
basis of the delivery of services which were not delivered. We
were shocked by Mr Buckles' apparent reluctance to grasp this
point.
35. Mr Buckles
confirmed to us that G4S would not be bidding for the Rio Olympics
in 2016. We believe this is the right decision, given that their
chances of winning the bid on the strength of their performance
at London 2012 would be slim, at best.
Lessons for the future
34. In awarding the contract to G4S, LOCOG appears
to have been influenced by G4S's size and reputation. This is
not unreasonablea bidder's previous performance on other
contracts is something which any diligent procurement exercise
should take into considerationand it is a natural assumption
that the world's largest security company would be a safe choice
for such a large project. As Mr Deighton told us:
"I think somebody else probably could have done
it but [G4S] were the obvious and best candidates to do it. They
are the biggest security company in the world. The Government
is their most important client. The eyes of the world are on this
project. They were highly incentivised to succeed because of all
those reasons and believed they could succeed".[56]
The Olympic security contract was, in Mr Buckles's
words "one of a kind ... there wasn't a track record, there
wasn't a blueprint".[57]
That did not stop the company, as we know, boasting that G4S could
be delivering Olympic security operations simultaneously around
the world. There is no doubt that the contract presented a tremendous
challenge, involving the recruitment, training and accreditation
of thousands of staff, and allocating them to 49 different roles
across 110 venues, all of which had to be completed to a tight,
non-negotiable timetable.[58]
35. However, it remains the case that, on this occasion,
the world's largest security company simply failed to deliver
the goods. As Mr Deighton told us:
"... I think they could have done this job ...
This was a very doable job. They should and could have been able
to do it and they simply failed to manage this part of their business
efficiently enough to deliver it".[59]
Mr Deighton has every right to describe the job as
"very doable" since LOCOG itself succeeded in recruiting,
training and accrediting 70,000 volunteer Games Makers, allocating
them to different roles, supplying them with uniforms and scheduling
them to shifts under much the same constraints that G4S was working.
36. The fiasco surrounding G4S's Olympic contract
has focused attention on the role of the private sector in delivering
public services, and the way in which private-sector providers
are managed and monitored. Both the Culture Secretary and the
Defence Secretary have been quoted in the media as saying that
the issue had caused them to think again about the role of the
private sector;[60] that
would in our opinion be a wise thing to do. The Minister for the
Cabinet Office also has concerns about the failure to take account
of providers' previous track-record, which can lead to contractors
who are already failing being awarded new contracts. Mr Buckles
himself agreed that a company's long-term track-record was an
important element in its ability to win new contracts.[61]
37. The precise reasons for G4S's failure remain
unclear, though all the evidence points to poor management information
and poor communications as the two main contributory factors.
G4S has commissioned a review from PwC, and Mr Buckles has agreed
to share its findings with the Committee.[62]
We look forward to receiving
a copy of the PwC Report on G4S's performance on its Olympic contract.
A detailed, internal review is clearly necessary if the right
lessons are to be learned from this experience, but it is no substitute
for Parliamentary scrutiny.
38. Few would
have expected a company the size of G4S to fail in delivering
such as high-profile contract. But it did fail. By contrast, LOCOG
was able to recruit and deploy 70,000 volunteers, nearly seven
times the number of people that G4S was asked to provide, working
to the same timescale and under similar constraints. In letting
major contracts, a company's past performance is clearly an important
factor, but government departments, police forces and other public
bodies must not place too much weight on a company's size and
reputation alone. We
also wish to see evidence that the company's recruitment, training,
personnel management and cash recovery systems have been reviewed
in the light of the experience of so many of those recruited for
employment during the Olympics who were severely let down by G4S.
We expect this to be fully covered in the PwC report or in a
separate independent report commissioned by G4S. Cost effectiveness
and savings in the delivery of public services should not be at
the cost of exploitation and neglect of management responsibilities
to staff and potential employees. The Government should satisfy
itself as to the quality of these aspects of G4S's practices in
respect of the delivery of other services, given that these failings
only came to light as a result of the high public profile failure
of the G4S Olympic contract.
39. When he
was asked whether staff were paid for training, Mr Buckles said
'They will be if they come to work' but a significant complaint
set out in evidence to the Committee and widely reflected in the
press and media was that people were not paid for training if
they were ready and willing to work but were not offered a time
and place to report for work. Others were expected to pay for
their own uniforms unless they worked a number of shifts. We can
understand a company wishing to recover costs if an individual
benefits from training but then fails to turn up for work without
good reason, but when the lack of shifts work is entirely due
to the company's failure to provide employment, this is an entirely
different matter. We expect the company to make public a means
by which people can be recompense in such circumstances and to
be quick and generous in settling such claims.
40. The Government should not be
in the business of rewarding failure with taxpayers' money. As
private sector providers play an increasingly important role in
the delivery of police and criminal justice services, it is vital
that those commissioning services look at the track-records of
prospective providers. We recommend that the Government establish
a register of high-risk providers, who have a track-record of
failure in the delivery of public services. This would provide
a single source of information for those conducting procurement
exercises about companies which are failing or have failed in
the delivery of public contracts.
1 Olympic Britain, House of Commons Library
,2012; www.olympics.org.uk Back
2
Q 406 (Lord Coe) Back
3
Letter from Paul Deighton, Chief Executive of LOCOG, to the Chair
of the Committee, dated 16 July 2012 Back
4
Commercial and Operational Managers Procuring Asylum Support Services Back
5
Letter from the Home Secretary to the Chair of the Committee,
dated 19 July 2012 Back
6
Q 636 Back
7
Letter from Paul Deighton, Chief Executive of LOCOG, to the Chair
of the Committee, dated 16 July 2012 Back
8
Ian Horseman-Sewell, Director of Major Events, G4S Secure Solutions,
speaking at a conference on Olympic and Paralympic security at
the Royal United Services Institute, 25 January 2012. Details
of the event, including an audio recording or Mr Horseman-Sewell's
speech, are available on-line at www.rusi.org. Back
9
Oral evidence on the Work of the Home Secretary, 6 September 2012,
HC 563-i, Q 36. See also Q 445-450 (Mr Farr). Back
10
Olympic Security Commission - Phase 1 (LOCOG Security), HMIC,
30 September 2011. The Report is published on the Committee's
website. Back
11
Ibid, section 1.2. Back
12
Q 310 Back
13
HMIC Report, September 2011, paragraph 2.4. Back
14
Q 407ff & 466ff Back
15
Olympic Assurance - Review of LOCOG's Security Operation (Follow-up),
HMIC, 27 February 2012. The Report is published on the Committee's
website. Back
16
Q 311 Back
17
Q 408 Back
18
Security G4S Workforce Delivery Programme Review - Final Briefing
Paper for LOCOG, Deloitte, 11 May 2012. The Report is published
on the Committee's website. The internal audit report is not published. Back
19
Q 407 & 425 (Mr Deighton) Back
20
Deloitte Report, p. 8 Back
21
Ibid, p. 5 Back
22
Ibid, pp. 5-6 Back
23
QQ 14-17 Back
24
Q 504 (Mr Farr) Back
25
QQ 343-346 Back
26
QQ 528-533 Back
27
Q 545 (Mr Taylor-Smith) Back
28
Letter from the Home Secretary to the Chair of the Committee,
dated 19 July 2012 Back
29
Ibid & Q 477 (Mr Farr) Back
30
Q 407 (Mr Deighton) Back
31
Q 478-481 (Mr Farr) and Letter from the Home Secretary to the
Chair of the Committee, dated 19 July 2012. The Military Contingency
Force had already been established to deal with a possible civil
emergency during the Games, such as flooding. Back
32
QQ 481-483 Back
33
QQ 485-487 & 493 Back
34
Q 18; G4S targets big events after Olympics boost, Reuters,
6 July 2012 Back
35
Q 511 (Mr Farr) Back
36
Ibid Back
37
Q 341 (AC Allison) Back
38
Q 432 Back
39
An open letter of complaint to G4S dated 20 August, signed by
over 100 applicants and employees, summarises most of the problems.
See submission from Cameron Wauchope. Back
40
Submission from Miss Jo Fish; submission from Mr John Hughes-Jones
MBE Back
41
Submission from Michael Graham Back
42
Submission from Mr John Hughes-Jones MBE Back
43
Q 425 Back
44
Deloitte Report, p. 21 Back
45
Letter from Paul Deighton, Chief Executive of LOCOG, to the Chair
of the Committee, dated 10 September 2012 Back
46
Q 625 Back
47
Letter from Nick Buckles, Chief Executive of G4S, to the Chair
of the Committee, dated 12 September 2012 Back
48
Q 440 Back
49
Q 433 Back
50
Letter from Paul Deighton, Chief Executive of LOCOG, to the Chair
of the Committee, dated 16 July 2012 Back
51
QQ 452-455 Back
52
QQ 125-218 Back
53
Q 586 Back
54
QQ 588-591 Back
55
Q 595 Back
56
Q 413 Back
57
Q 582 Back
58
Q 558 Back
59
Q 413 Back
60
G4S proves we can't always rely on private sector, says minister,
The Independent, 14 August 2012. Back
61
QQ 606-607 Back
62
Q 235 Back
|