Olympics Security - Home Affairs Committee Contents


WRITTEN EVIDENCE SUBMITTED BY JOHN G KELCEY [OS 10]

I watched the appearance and listened to the evidence that the Chief Executive of G4S gave to the House of Commons Select Committee with increasing incredulity. It seemed to me that he had simply turned up to plead guilty, was totally unprepared for the questioning and probably did not want to criticize the Home Office in order to jeopardize existing and bids for future contracts—in short, we will take the rap.

It is not for me to defend G4S but I do question whether the evidence was heard in the correct sequence. It seems to me that the fundamental issues relate to the preparation of the contract documents in the first place and the management of the contract in the second. Putting the CEO of G4S on first was putting the cart before the horse. The Select Committee would be better informed and much wiser had it first examined the terms and conditions of the contract by questioning the Home Office officials who prepared and managed it. The contract is likely to have a named person as the "contract manager".

If the contract had been properly prepared and managed G4S would never have been in the position it was. My experience of contracts awarded by Government Departments and their Agencies is that they are generally badly prepared and even more badly managed. The latter results from, amongst other things, inadequacies in the terms and conditions and poor management (including bad financial management) by the nominated officer and, as I understand it, a total lack of interest by Ministers. My experience of private sector contracts indicates that they are much tighter and much better managed.

Because the Government awards contracts to the lowest bidder, Government officials know only too well that contractors seek to make their profit by one or a combination of two means. First, cutting corners and second claims resulting from contract variations. It is not uncommon for Government Departments to award contracts that are well under the estimated cost.

<?oasys [pf10p0] ?>It also seemed to me that the contract was too big for a single contractor and should have been divided into say five to 10 smaller contracts. The contract sum may be satisfactory for certain types of Government work such as defence procurement and some road schemes but common sense suggests it was much too big and complex for the particular purpose. Notwithstanding that, there is a propensity (as frequently shown in television programmes that a large number of people do not want to work and will seek to blame the conduct of employers in preventing them doing so.

So, it appears to me that G4S should have appeared at the end of the process and not the beginning. I reiterate that I am not seeking to defend G4S, "contractors are contractors" who seek to make money via bad contracts and bad contract managers. That is what contractors do.

Fundamental responsibility for the failure MUST lie with the Home Secretary and her officials. I strongly suspect that the failure "blew up" because the Home Office could not keep the lid on tightly enough. Put in other terms, the Home Secretary and her officials should have been on top of the contract and interrogated G4S frequently as to progress, fulfilment of the terms of the contract and have dealt with the failures as soon as there was the slightest hint of something going wrong.

There needs to be personal accountability. The Select Committee roasted the Chief Executive of G4S, it should do so in terms of the Home Secretary and her officials who prepared and managed the contract. There was gross professional negligence (if not worse) in the Home Office, it needs to be flushed out.

July 2012

—— END ——


 
previous page contents next page


© Parliamentary copyright 2012
Prepared 25 October 2012