3 Costs
and staffing
Operating costs
Figure 6: The composition of the Department's operating
cost budget over the Spending Review
NOTES
The values for 2010-11 are the baselines agreed by
the Department with HM Treasury in October 2010. Actual outturn
for operating costs in 2010-11 was £195 million.
The budget values for 2011-12 to 2014-15 are those
agreed during the 2010 Spending Review.
Front-line delivery costs are funded from the Department's
programme budget.
Source: NAO presentation of material from the
Department for International Development and from HM Treasury,
Spending Review 2010, Cm 7942, October 2010
50. DFID's operating costs were £190 million
in 2011-12. These costs comprise the Department's administration
costs and its front-line delivery costs.[48]
Over the Spending Review period administration costs will decline
considerably while front-line delivery costs will rise. As a result,
the Department's operating costs are likely to grow by a small
amount in real terms but they are due to fall as a proportion
of the Department's total budget, to around 2.2%.
Front-line delivery costs: front-line
staff
TRENDS IN STAFFING

51. In previous reports we have expressed concern
that DFID has insufficient staff in relation to its increasing
budget. This situation has been addressed. The number of frontline
staff in the Department is increasing. Its workforce is due to
increase by 525 (23%) full-time equivalent posts over the four
years of the Spending Review period to March 2015; almost 70%
of that planned growth had happened by September 2012.[49]
Largely as a result of the growth in the number of advisers, the
seniority of staff employed by the Department is increasing.[50]
ADVISERS
52. The main increase in staff has been in the
numbers of professional advisers DFID employs to help manage its
programme budget. The Department employed about 230 more advisers
(some 45% increase) during 2011-12, although it encountered some
delays in recruitment and barriers to filling posts in some locations.[51]
53. The Department now plans a further increase
of about 80 advisers (11%) in the second half of 2012-13 (taking
the total to around 760), including increases in the governance
and infrastructure cadres where posts have previously been hard
to fill. [52]
Figure 8: Number of adviser posts by cadre, planned growth between September 2012 and March 2013, and March 2013 and March 2015
|
| September 2012 actual
| Planned increase (REDUCTION) September 2012 to March 2013
| March 2013 planned
| March 2015 planned
| Planned increase (REDUCTION) March 2013 to September 2015
|
Conflict | 29
| 1 | 30 | 33
| 3 |
Economics | 122
| 14 | 136 | 131
| -5
|
Education | 35
| 6 | 41 | 41
| 0 |
Environment | 54
| 5 | 59 | 58
| -1
|
Governance | 108
| 17 | 125 | 124
| -1
|
Health | 70
| 3 | 73 | 73
| 0 |
Humanitarian | 23
| 5 | 28 | 27
| -1
|
Infrastructure | 25
| 7 | 32 | 31
| -1
|
Private Sector Development
| 46 | 13 |
59 | 54 | -5
|
Rural | 27
| 5 | 32 | 34
| 2 |
Social Development | 73
| 1 | 74 | 76
| 2 |
Statistics | 41
| -1
| 40 | 43 |
3 |
Evaluation | 35
| 3 | 38 | 37
| -1
|
Total | 690
| 77 | 767 | 761
| -6
|
Source: NAO presentation of departmental data
|
54. The figure above shows changes in the number
of advisers by expertise. We are unclear what the rationale is
for the mix of advisers and how far the Department has the right
staff to monitor the expenditure of multilateral programmes. We
also wondered why DFID was increasing the number of professional
advisers rather than traditional civil service generalists. We
were informed:
I would not draw such a clear distinction between
advisers and nonadvisory staff. For me, the distinction is between
staff doing programme delivery, which comprises a range of professional
advisers but also the core programme management staff. If you
go to a country office, as you know, you meet a mix of staff who
are doing core programme management and some people who are there
with a specific professional discipline. The shift is into that
group of staff and out of the staff doing support work in particular.[53]
The professional advisers in DFID are very much integrated
into our business units, whether they are country offices or policy
teams in London.[54]
55. In the past we had expressed
concerns that DFID did not have adequate numbers of staff to spend
cost-effectively its budget. DFID has addressed this and is rapidly
increasing the number of professional advisers and increasing
the proportion of its staff working overseas. However, we have
some concerns about the mix and skills of staff, including whether
it has the staff to oversee the huge expenditure of UK taxpayers'
money undertaken by multilaterals. In its reply to this report
the Government should explain the reasons for increasing the number
of professional advisers to a greater extent than any other group
of staff and for the variations in numbers of advisers in each
category.
THE DEPARTMENT'S STAFFING OF COUNTRY
OFFICES
56. Increasingly, DFID staff are based overseas.[55]
Country offices are staffed by a mix of home civil servants and
locally engaged staff, known as staff appointed in-country (SAIC).
The number of posts the Department expects to be filled by staff
appointed in-country is growing at a similar rate to the numbers
of overseas posts for home civil servants. The seniority of posts
for staff appointed in-country is also expected to grow but at
a rate which is lower than the departmental average.[56]
UK-BASED STAFF
Institutional memory and knowledge of local languages
and cultures
57. During our overseas visits, we have observed
that DFID staff do not always have a good institutional memory
or appropriate levels of local language skills, nor knowledge
of cultural issues. One way of addressing this would be for staff
to serve for longer periods than the typical three year tour of
duty, especially in more secure countries. We were informed that
in such countries DFID staff were in post for four or five years
in some cases. DFID officials acknowledged the benefits of longer
tours of duty:
having some kind of institutional memory and longevity
of understanding is really important
we
need it in our
UK-based staff when we are posting them.[57]
On the other hand, the Department had to encourage
people to get sufficiently broad experience to be able to develop
their career and move on.[58]
58. The Permanent Secretary added:
We also try to make sure we get the best out of our
local staff in informing us of what is going on in the wider environment.
I was in Rwanda three weeks ago and Uganda last week, and some
of the best intelligence I got on what is going on and what we
should really be caring about was not actually from President
Kagame or President Museveni, both of whom I had conversations
with, but from what the citizens of the country, not least our
own staff, said to us.[59]
59. On the question of the language knowledge
of UK staff, the Permanent Secretary told us that there was a
cost barrier to language training,[60]
but he added:
I will have another look at that. It is very expensive
to equip someone from a standing start with a high level of knowledge
for some of the languages that you need in the places we operate.
One of the reasons we have larger numbers of highly professional
local staff is to get that capability inside the organisation
in a cheaper way.[61]
60. The Department did not routinely collect
aggregated data on the language skills and cultural awareness
of its home civil servants or the length of time they have been
in post. Mark Lowcock informed us that the information was collected,
but the Department had not aggregated it.[62]
61. Subsequent to the evidence session DFID informed
us that it
makes language training available to staff and is
currently engaged in a Government wide e-learning solution for
language learning in 31 spoken languages. The learning is
suitable for a range of students, from beginners to level A2 of
CEFR (Common European Framework of Reference). This learning
is paid for centrally by DFID and is the first option for individuals
who need to develop their language skills at this level. Where
language learning is required above this level it may be supported
through a variety of options e.g. extensive - one or two days
a week; intensive - one-to-one training (short and long periods
as required); and immersion - generally prior to taking up post.
We were also informed that DFID:
aims to recruit the best person for a post based
on a range of skills and competencies, rarely making language
skills a mandatory requirement. Where language skills are
considered necessary to be able to function effectively in country
intensive language training is provided to DFID staff. In terms
of length of posting, it should be noted that three years is not
a maximum but is the standard tour length in most countries.
There are many occasions where DFID staff have remained in-country
for significantly longer, sometimes up to six years where it suited
business needs. Even where a UK Civil Servant is fluent
in the local language they will often be accompanied by a local
member of staff at key meetings as local dialects can make it
difficult to be confident in interpretation.[63]
Institutional memory in high risk countries
62. Problems are particularly acute in high risk
countries. On our recent visit, we found that in some respects
there were more members in the Committee who had knowledge of
Afghanistan and had previously visited than the staff who were
there.[64] Mark Lowcock
noted he too had a bit more institutional memory than some of
the team on the ground. [65]
63. In our report on Afghanistan, published in
October 2012, we concluded:
While we
commend DFID staff for the job they
have done under these [difficult] circumstances, we are concerned
about the short postings, resultant loss of capacity and knowledge
and weak institutional memory. We recommend that DFID create a
cadre of experts with knowledge of Afghan language and culture,
who will work on Afghanistan, in London or in country... Longer
tours and routine rotations to Afghanistan would also aid in this
64. In its response, published in January 2013,
and therefore after the evidence session on DFID's Annual Report,
the Government stated that it partially agreed with this recommendation.
It recognised that that the length of postings posed 'challenges
for institutional effectiveness'.
65. However, the Department pointed to the difficulty
in longer postings in dangerous countries:
Something like a quarter of those UK-based staff
who are posted overseas are in places where they cannot have their
partner or their children with them. ...[66]
it is not sensible in the most dangerous environments
to have people in post too long. Three years, for somewhere like
Afghanistan, is really the outer limits of what somebody should
do for their own physical and mental health...[67]
in Kabul
average tour lengths for DFID staff
are currently 20 months, providing us with a reasonable degree
of continuity. Extending tours and rotation lengths ..could
impact on our ability to attract and retain good quality, experienced
staff. We will however keep these issues under review as the situation
evolves.
66. DFID was dealing with the lack of institutional
memory in a number of ways. First it was increasing the number
of Afghan staff in the Kabul office. Secondly, DFID was ensuring
thorough induction and handover periods for UK staff. Thirdly,
DFID would also continue to draw on (and build up as needed) a
team or DFID advisers and policy managers working on Afghanistan
but based in the UK,
we have built a 'talent pool' of DFID staff who have
expressed an interest in working on our Afghanistan programme
and a list of specialists that are able to deploy for short-term
assignments as required. This remains a high priority area for
our senior managers.
a steady stream of staff have returned to Afghanistan
on a second posting, or are working on Afghanistan in policy teams
in London. .. [we have] larger numbers of staff now than we used
to who would do a London-based job on Afghanistan before they
go to Kabul and Helmand, and then maybe again afterwards.[68]
67. Nevertheless, DFID admitted that there was
room for improvement:
we have a lot of people
in the organisation
who have experience of Afghanistan. One of the things we are currently
working on is to see how we can do a better job of harnessing
those skills and experiences of people who may, for obvious or
good reasons, have moved on to a different area of DFID but still
have an institutional experience. We need to find a way of making
that knowledge and skill base available to the current staff who
are working there.[69]
68. The typical posting of a
home civil servant to a DFID country office is for three years,
and is usually shorter in fragile countries. Short postings bring
risks to continuity and institutional memory. We recommend that
the Department consider the merits of extending the standard length
of posting so that staff have more time to ground themselves in
the local culture and environment and then utilise that knowledge.
For more fragile environments, we repeat our recommendation that
the Department develop a cadre of staff who would have several
postings to the same location over a period of years, and who
could providing on-going support to country based staff once they
had completed individual postings.
69. The effectiveness with which
DFID country based staff engage with local people will in part
depend on their language and knowledge of local cultures. We
recommend that the Department spend a small part of its rapidly
growing budget on improving the language skills of its staff.
We recommend that the Department put in place a strategy for addressing
any gaps or shortfalls and take greater account of language skills
in making appointments and promotions.
STAFF APPOINTED IN COUNTRY
70. The Department's latest plans are that the
number of SAIC posts will increase from 745 in March 2011 to 980
by March 2015. As we have seen, the use of SAIC staff has many
advantages. SAIC staff have invaluable local knowledge and cost
less to employ, including lower non-wage costs such as flights
home to the UK.
71. While in-country staff responses to the 2011
Civil Service People Survey have been generally positive resignation
rates for staff appointed in-country are high compared to those
of home civil servants.[70]
Mark Lowcock told us:
One reason for that is most of the people we hire
in countries, by definition, are not available to work for us
in third countries or in the UK, so the number of additional opportunities
available to them, in an office of 50 or 60 people, is obviously
smaller than if you are one of our UK-based staff, for whom there
are 2,000 or 1,800 opportunities available. That is the first
thing to say.
72. The results of the survey also indicate that
a significant minority of staff-appointed in-country have reported
concerns over discrimination, harassment and bullying and most
are not satisfied with levels of pay and benefits.[71]
Mark Lowcock informed us:
There are some places where our local staff have
said to us that we are not keeping up with the pay and benefits
of other comparable employers. We operate a cross-government approach
to terms and conditions for local staff, so we do that together
with the Foreign Office. We are not trying to compete, because
we cannot afford to, with the top employers in every market. On
the whole, we think that some degree of churn and refreshment
is a good thing, as I said earlier. We do not at the moment have
any places where we have a major problem in recruiting and retaining
staff of the calibre we need.[72]
73. On bullying and harassment we were told:
On the issue of other things that matter to people
when they come to work, our We have just taken delivery of this
year's staff survey. 2,300 people around the organisation have
answered 50 or 60 questions telling us exactly what they think
about that whole set of issues. We are digesting the results at
the moment. We absolutely have something to do on this bullying
and harassment issue, but it is very localised, and so we need
a local response to those kinds of issues. The managers in charge
of each location or business unit have a personal responsibility
to work out what is going on in their area.
74. There have been some instances where standards
of behaviour of a few SAICs were inadequate. Mark Lowcock informed
us:
We absolutely expect our local staff to absorb and
display behaviours that are consistent with the values we have
across the public service in the UK. ...as part of the induction
and support and training we give them, we are very clear about
standards of behaviour that are expected. That touches on a whole
range of issues. Lots of people have possibly previously worked
in environments where corruption or bribe-taking is tolerated
in a way in which it absolutely is not in our system.[73]
75. SAIC have a key role to
play in DFID country programmes. DFID is bound by HMG rules on
pay and conditions and thus if it is to retain good performing
staff it must ensure they are well managed and motivated. While
generally positive, the results of the Civil Service People Survey
show that a significant minority of staff-appointed in country
have reported experience of discrimination, harassment or bullying.
We welcome DFID's determination to address discrimination, harassment
and bullying. DFID must also ensure that SAICs' behaviour is in
accordance with the values of the UK public service.
DFID's use of consultants
76. DFID spends approximately £500 million
on technical co-operation. In our report last year we recommended
that DFID should improve its assessment of which types of projects
and services it should use consultants for, and in particular
it should assess more carefully the use of consultants to manage
the department's own service delivery programme. In its response
to the report, DFID recognised that there was room for improvement
and said it was considering the full range of options to resource
projects for service delivery. Moreover, the additional front
line delivery staff would increase DFID's capacity to manage service
delivery programmes. The Committee also recommended that DFID
identified expenditure on technical co-operation by purpose. In
its response DFID said it would consider what could be done.
77. This year DFID undertook a review of its
use of consultants. It found that there had been considerable
overall growth in the number and total value of supplier contracts
awarded and that the size of programmes and of contracts with
suppliers is increasing. As a result, DFID made changes
- Ministerial approval for the
award of all supplier contracts over £1million;
- the Secretary of State engaging directly with
top suppliers to DFID to reinforce the need to improve value for
money and;
- the introduction of tougher monitoring of supplier
performance
78. The submission from the UK Aid Network/BOND
called for additional measures: It
- argued that there was currently
a lack of data on DFID's commercial contractors which made it
difficult to judge whether they offered the best value-for-money
for the work they were contracted to undertake.
- recommended that DFID instruct all commercial
contractors and consultants to release open data conforming to
the International Aid Transparency Initiative (IATI) by the end
of 2013.[74]
The TUC urged DFID to 'where possible, invest in
strengthening in-house capacity to deliver aid, rather than excessively
relying on commercial contractors and consultants, and require
the latter to release open data conforming to the International
Aid Transparency Initiative (IAIT) by the end of 2013'.[75]
79. On the other hand, Adam Smith International
(ASI), one of DFID's largest contractors, argued that good quality
DFID technical assistance was much appreciated by beneficiaries
in developing countries and achieved excellent value for money.
We were informed of seven projects which
have together cost less than £100 million but
have to date generated benefits of at least £3,600 million.
Moreover, after another five years the benefits generated will
be much more - of the order of £12,000 million.
...input costs are very modest compared to the cost
of professional services used by other parts of the UK government,
and are surprisingly roughly equivalent or a little less than
the daily cost of civil servants, military personnel and international
donor officials. The questions that need to be addressed are
not 'how can we make technical assistance inputs even cheaper'
or 'what else could we do instead' but rather matters such 'how
can we make technical assistance more effective', 'how can it
be provided faster and more flexibly,' and 'how can procurement
processes take proper account of excellent past performance.'[76]
Administration costs
80. In 2011-12 the Department reduced its administration
costs by £21million (about 20%) to £103 million (£18
million below its budget).[77]
Figure sets out the cost reductions by type of cost.
Figure 9: The Department's administration costs, 2010-11 to 2011-12
|
Type of cost (income)
| 2010-11 £million
| 2011-12 £million
| Increase (reduction) in cost between 2010-11 and 2011-12
| Percentage increase (reduction) in cost
|
Employee costs (salaries, pensions, contract & agency staff)
| 75.2 |
62.8 | -12.4
| -16%
|
Property costs
| 26.1 |
24.0 | -2.1
| -8%
|
Staff training costs, business travel, subsistence and overseas costs
| 10.7 |
8.9 | -1.8
| -17%
|
Communications and information technology
| 8.9 |
6.3 | -2.6
| -29%
|
Consultancy, service and supply costs
| 4.7 |
2.5 | -2.2
| -47%
|
Other
| 4.1 |
5.3 | 1.1
| 27% |
Income
| (5.9)
| (6.5)
| - 0.6
| -10%
|
Total Cost
| 123.8
| 103.3
| - 20.6
| -17%
|
NOTES
2. The values for the individual cost elements may not sum exactly to the total because of rounding.
Source: NAO presentation of Departmental data
|
81. The majority of the savings in administration
costs arose from a £12 million reduction in employee costs.
Reductions were also made in most other areas of administrative
spending, with large percentage reductions (47%) in consultancy,
service and supply (NB not to be confused with spending on consultants
to provide technical co-operation) and communications and information
technology (29%) (see Figure 11 on page 23).
82. The Department's administration budget will
decline in cash terms to £94 million in 2014-15, equivalent
to a real terms reduction of one third over the Spending Review
period. The Department expects that its employee costs will fall
again in 2013-14 and 2014-15. By 2014-15, the London accommodation
move should contribute net savings. [78]
Costs associated with the location
of staff
THE DISTRIBUTION OF STAFF BETWEEN LONDON AND EAST
KILBRIDE
83. DFID's UK staff are based in London and East
Kilbride. The number of staff in each office is shown in Figure
10. The numbers of staff in both locations increased from March
2011 and will increase to March 2013 and thereafter decline. In
both locations there will be more staff in senior posts in March
2015 than there were in March 2011.
Figure 10
Number and grade of posts in London and East Kilbride,
actual March 2011 and September 2012, planned March 2013 to March
2015

NOTES
There are three bands of staff below Senior Civil
Service, with Band A being the most senior.
Source: NAO presentation of departmental data
84. The overall costs of running an office in
Scotland are significantly less than those in London.[79]
While maintaining two offices imposes travel costs, these have
remained relatively stable over the last three to four years and
DFID hopes to make increasing use of video technology to communicate
between the two offices. We were told
That travel costs us £400,000 to £450,000
a year, so it is quite a small element of our overall global travel
budget. ... we are stepping up our video capability, so everyone
will be able to run videos over their own office laptop, and the
spaces in both buildings to make that work sensibly will be much
better than they have been in the past. We do expect video to
still be really important, but face-to-face travel and meetings
will also be important. In the context of the overall savings
and costs of accommodation, even if we had a 10% or 20% increase
in travel, you are talking about tiny sums of money in relation
to the overall value that we gain by having an office in Scotland.
85. DFID UK-based staff are split between London
and East Kilbride. At the latter location, there will be 290 Band
B and C staff and 290 senior civil service and Band A staff. We
will be undertaking an inquiry later in the year to look at the
implications for jobs in East Kilbride of Scottish independence.
THE LONDON ACCOMMODATION MOVE
86. The Department will move its London-based
staff to 22-26 Whitehall in early 2013, which should reduce steady
state accommodation costs by around £6.5 million per annum.[80]
87. The accommodation in 22-26 Whitehall is significantly
smaller than Palace Street and thus the Department is moving some
posts from London to Abercrombie House in East Kilbride.[81]
The Cabinet Office, the previous occupant of DFID's new premises,
had 600 staff in the new offices, DFID will have 800.[82]
SECURITY COSTS
88. In 2012 we visited Afghanistan and Pakistan
and noted the high level of security. DFID provided information
about its operating costs (Admin and Front Line Delivery) related
to overseas offices charged to Close Protection, PropertyInsurance
charges, Property Protection, Property Security and Patrols, Security
Equipment Maintenance and Upgrades. Total costs have varied considerably
from year to year but operational security costs in Afghanistan
consistently represent a significant proportion.
89. In confidential meetings with a number of
individuals the Committee heard concerns about the provision of
security for DFID staff. Organisations have been unwilling to
criticise DFID publicly but privately have argued that DFID might
make more use of local drivers and less high profile vehicles.
Non-governmental organisations use low profile cars with trained
drivers who are always in radio contact and only use armoured
cars in very dangerous provinces. A relaxation of the security
rules for civil servants and related costs with accompanying reductions
in security costs has been suggested.
90. We were told
To draw this comparison with the NGOs is the right
question to ask. I am afraid to say, though, that, in some of
the countries where we operate, there is a material difference
between working for an NGO and being associated with the UK Government
in a Government Department. We have to take the security of our
staff extremely seriously and we have to make these kinds of judgments
about how to keep them safe.[83]
We...have a legal obligation to provide a proper
duty of care to our staff... the cost of dealing with it [a problem],
with a kidnapping for example, is very high. Minimising the number
of times we have to deal with those costs is also something we
need to bear in mind. [84]
91. We also wondered whether security inhibited
the ability of DFID staff to do the job. We wondered whether 'if
we could not do this in a slightly more low profile way, maybe
through third parties rather than directly, maybe we should not
do it at all'. The Permanent Secretary agreed to consider this
issue.[85]
92. Security expenditure in
high risk countries is significant. We understand the Permanent
Secretary's concerns about the Department's duty of care to its
staff but there appears to be less attention paid to how this
impinges on the ability to deliver departmental objectives on
the ground. We recommend that the UK Government consider changing
working and/or delivery methods to take this fully into account.
ADMINISTRATIVE STAFF COSTS
93. While the Department is increasing the number
of frontline staff, it is planning to cut the total number of
administrative posts by around 100 (18%) to around 450 over four
years to 2014-15. By May 2012 it had made a net cut of 28 posts,
with a 45 post reduction being made in its Business Solutions
Division which is responsible for IT and telecommunications.[86]
Figure 11:
|
Number of administrative posts by division, actual change between March 2011 and May 2012, and planned change May 2012 and March 2015
|
Division | March 2011 Actual
| Actual increase (decrease) between March 2011 and May 2012
| May 2012 Actual |
Planned increase (decrease) between May 2012 and March 2015
| March 2015 Planned
|
Corporate Hub and Business Change & Strategy
| 28 | 0
| 28 | 1
| 29 |
Internal Audit | 22
| -1 | 21
| 5 | 26
|
Communications | 60
| -7 | 53
| -5 | 48
|
Human Resources, Security and Facilities
| 129 | 25
| 154 | -57
| 97 |
Business Solutions | 156
| -45 | 111
| 8 | 119
|
Finance and Corporate Performance
| 158 | -3
| 155 | -21
| 134 |
Total | 551
| -28 | 523
| -69 |
453 |
NOTES
1. A small team transferred from Business Solutions to the Corporate Hub in 2011-12. The March 2011 baseline figures for the two Divisions have been revised to strip out the effect of this move.
2. The values for individual elements may not sum exactly to the total because of rounding.
Source: NAO presentation of departmental data
|
94. The TUC argued that:
DFID has slightly increased its staff over the last
two years to help deliver the increased aid budget. However there
has been a significant reduction, around 10%, of administrative
staff which is impacting upon DFID's ability to deliver aid effectively.
With DFID due to increase its budget significantly, continuing
to maintain arbitrary restrictions on staffing levels, or indeed
any further cuts to staffing levels, will exacerbate this problem.
[87]
The UK Aid Network and BOND state
We believe that DFID's human resources need to be
at a sufficient level to deliver its aid programmes effectively.
We are concerned that a rising DFID budget is not matched by a
rising DFID headcount. We do not think that an arbitrary departmental
headcount is the best way of ensuring value-for-money.[88]
95. Officials were asked what impact the cuts
in administrative staff would have on DFID's capacity to scale
up the aid programme and, in particular, the consequences of reducing
administrative costs by a third while increasing the numbers of
frontline staff. We were told:
We are doing it over a three to four year period,
so I think that gives us enough time to get it right... There
is a significant chunk of staffing reductions that will follow
from automating a lot of our HR processes. We are also looking
at the staff who essentially do corporate activities around the
network and ... whether we simplify some processes there. The
timescale means that we have been able to do this in a way that
has not compromised our ability to provide the support that we
need to provide from the centre to the business.[89]
My current estimate is that we do have the capacity
to deliver, particularly across the bilateral programme, because
we have so substantially grown the professional capability of
the major overseas offices.[90]
96. We also asked officials about concerns that
tasks which were previously done by administrative staff were
now being done by people on high salaries. Mark Lowcock replied:
Most of the tasks are being automated away. We used
to have hundreds of people in DFID whose job was to put papers
on to files. We do not have those jobs anymore, because we have
automated our recordkeeping.[91]
Richard Calvert added:
we also want people who are doing programme management
and doing professional jobs to care about the people and the money
side of what they are doing. If you had gone back 15 years, you
would have found a lot of professional advisers in DFID thinking
that looking after the money was someone else's job, and we had
a layer of administrative people to do that.[92]
97. The Department has made
clear its intention to reduce administration costs despite an
increasing budget; however, the evidence relied upon to support
these reductions is either historical, in relation to changing
from paper based systems to computerised systems, or lack detail,
described as simplifying processes. There is a lack of substance
in the explanation provided by the department. We recommend that
DFID provide a detailed breakdown of the changes of processes
that have allowed savings to be made.
98. Employee costs have borne
the largest reduction in administrative costs. It is important
that as a result too many administrative tasks are not farmed
out to front-line staff, thereby reducing the overall efficiency
of the Department. The level of administrative costs should not
be an arbitrary target, but should be determined by what is best
for delivering the Department's results.
48 NAO briefing, paragraphs 2.1-2.3 Back
49
NAO briefing, paragraph 3.2 Back
50
NAO briefing, paragraph 3.3 Back
51
NAO briefing, paragraphs 3.5-3.7 Back
52
NAO briefing, paragraph 3.8 Back
53
Q42 Back
54
Q43 Back
55
NAO briefing, paragraph 3.3 Back
56
NAO briefing, paragraphs 3.10 and 3.11 Back
57
Q49 Back
58
Q49 Back
59
Q55 Back
60
Q52 Back
61
Q52 Back
62
Q48 Back
63
Ev 28 Back
64
Q50 Back
65
Q50 Back
66
Q45 Back
67
Q49 Back
68
Q49 Back
69
Q50 Back
70
NAO briefing, paragraph 3.12 Back
71
NAO briefing, paragraphs 3.13 and 3.14 Back
72
Q53 Back
73
Q55 Back
74
Ev w17 Back
75
Ev w12 Back
76
Ev w8 Back
77
NAO briefing, paragraph 2.4 Back
78
NAO briefing, paragraph 2.6 Back
79
Q35 Back
80
NAO briefing, paragraph 2.7 Back
81
NAO briefing, paragraphs 2.9-2.11 Back
82
Q33 Back
83
Q37 Back
84
Q37 Back
85
Q38 Back
86
NAO briefing, paragraph 3.9 Back
87
Ev w15 Back
88
Ev w17 Back
89
Q41 Back
90
Q40 Back
91
Q44 Back
92
Q44 Back
|