The completion and sale of High Speed 1 - Public Accounts Committee Contents


Conclusions and recommendations


1.  The Department does not have sufficient understanding of the economic impact and regeneration benefits of transport infrastructure, compared with alternatives, so is not able to make fully-informed investment decisions. The Department needs a better understanding of both the economic benefits of transport investment and the relative merits of alternative investment, including non-transport options such as investment in broadband. In assessing the benefit-to-cost ratios of future projects the Department needs to improve its estimates of the regeneration benefits and wider economic impacts they will deliver and also evaluate a wider range of alternative options.

2.  The Department gives insufficient attention to evaluating its major projects. The Department has not got an evaluation framework in place and has only recently begun to develop an evaluation plan for High Speed 1. This risks the Department retro-fitting its evaluation to reflect what has occurred on High Speed 1 rather than properly evaluating it against original expectations. If the Department does not complete a proper evaluation there is also a risk that it will miss out on learning lessons from the project; for example, about how its decisions about the locations of intermediate stations are affecting local regeneration. The Department should develop a full evaluation framework urgently, including an assessment of the economic impact and regeneration benefits, for High Speed 1. It should also develop evaluation frameworks now for all its current major projects, and assure us that these frameworks are in place for all future projects including Crossrail and High Speed 2 (HS2).

3.  The delivery of regeneration benefits from High Speed 1 suffered from a lack of effective leadership from the centre. Regeneration is not the Department's core purpose and responsibility, but the Department justified High Speed 1 on the basis of the regeneration it would bring around stations at King's Cross, Stratford and Ebbsfleet. Development is under way at King's Cross and Stratford but is at a very early stage at Ebbsfleet. The Department has not been involved in regeneration at Ebbsfleet because the land is owned privately and so it considered sorting out delays there to be the responsibility of others. The Treasury should ensure that a single party has clear overall responsibility for coordinating the delivery of regeneration benefits and wider economic impacts from major public infrastructure investment.

4.  Over-optimistic and unrealised forecasts for passenger demand on High Speed 1 left the taxpayer saddled with £4.8 billion of debt. We have seen similar problems before with forecasting for the East Coast Main Line. In the case of High Speed 1the highly over-optimistic forecast was due in part to the Department giving insufficient weight to factors such as the emergence of low cost airlines and the competitive response of ferry companies. When deciding whether to proceed with a major infrastructure project the Department needs to do more than analyse the sensitivity of individual assumptions. The Department should specifically consider what combination of different factors has to happen for the project to no longer be viable.

5.  Unrealistic passenger estimates for High Speed 1 must not be repeated in the business case for HS2. The Department's case for HS2 has modelled demand on the assumption that ticket prices for HS2 will cost the same as tickets for slower 'classic' trains between London and Birmingham. This unrealistic assumption acts to exaggerate the HS2 passenger number forecasts. In reality the operator of HS2 is likely to be able to charge a premium price and the operators of 'classic' trains would be likely to drop their prices to retain passengers. The Department should rework their passenger demand forecasts and benefit-to-cost ratio for HS2 based on a more realistic estimate of ticket prices. Its assumptions must be transparent so that sounder judgements on passenger demand can be made in future.

6.  Some of the Department's assumptions about the benefit of faster travel are untenable. The Department uses a 'simplifying' assumption that all time travelling on a train is entirely unproductive. The value that it assigns to time saved by business travellers at £54 per hour also appears unfeasibly high and is more than seven times that of people commuting to and from work. These assumptions may skew appraisals of projects in favour of long-distance travel. Regeneration benefits of intermediate stations and benefits from relieving overcrowding and improving reliability may also be undervalued. The Department should undertake research to understand better the values passengers place on different transport benefits—faster journeys, reliability and over-crowding relief—and to more accurately assess how people actually spend their time on trains.


 
previous page contents next page


© Parliamentary copyright 2012
Prepared 6 July 2012