The completion and sale of High Speed 1 - Public Accounts Committee Contents


3  Lessons for the Department's future investment decisions

9. There are a number of important lessons from High Speed 1 which the Department needs to learn and apply to future transport projects, including HS2. We asked the Department what it was doing to ensure that these lessons were learned. In particular we were interested to know what was being done to improve passenger demand forecasts— use of High Speed 1 had been substantially overestimated by both LCR and by the Department.[17]

10. Demand forecasting for new projects is challenging but there was significant optimism bias in the original 1995 LCR forecasts of international passenger demand for High Speed 1 with actual passenger numbers, since the line opened in 2007, at a third of these predicted levels. International passenger numbers were also 30% below the Department's revised 1998 forecast, when the Department guaranteed the project debt.[18] More recent forecasts are more accurate, but this is to be expected as they predict demand over a shorter time period.[19] High Speed 1 is not the only case where the Department has shown optimism bias. For example, it accepted National Express's bid for the East Coast Passenger franchise, which was based on unachievable growth in passenger revenues.[20] The New Economics Foundation told us that demand forecasting is difficult and pointed out that inaccurate forecasts were also made by the private sector, for example, Disneyland got its forecasts dramatically wrong.[21]

11. The Department's models for forecasting passenger demand are highly sensitive to a variety of factors, particularly projections of GDP. The New Economics Foundation considered that it was critical "not to assume the best" and to be cautious. In relation to HS2, we asked the Department for the reasons underpinning the changing forecast of the year by which passenger demand will have doubled as this has fluctuated from 2033 to 2043 and back to 2037 (recently revised again to 2035). According to the Department the main reasons for the first fluctuation were downward revisions to projections of passenger growth following the economic crisis, combined with a change in fares policy. The second fluctuation was mainly due to updating the year on which the forecasts are based to reflect actual increases in long distance passenger demand which had been greater than expected. The Department does sensitivity testing on individual factors underpinning its benefit-to-cost ratio estimates but in reality changes tend not to happen in isolation.[22]

12. The Department's scenario planning for High Speed 1 was inadequate. The Department maintained that its estimate of the size of the total market for travel between the UK and France and Belgium was about right but accepted that it had over-estimated the share that would be captured by High Speed 1 because it had not anticipated the competition from low cost airlines and the competitive response from the ferry companies. The Department accepted that, although difficult, it could have predicted these developments in the mid-1990s.[23] HS2 is also being modelled on a limited set of assumptions. For example, the Department has not modelled the potential impact of the growth of video-conferencing on passenger numbers.[24] In addition passenger numbers for HS2 are being forecast on the assumption that premium prices will not be charged on the high speed line. This assumption is unlikely to be adopted when HS2 is in operation. Passengers may be willing to pay higher fares to travel faster and the operator of the 'classic' line may cut fares to compete.[25]

13. The Department's method of calculating the benefit-to-cost ratio of new rail infrastructure projects, including HS2, includes an assessment of the value of journey time savings for different types of passengers. For business passengers, the Department uses an assumption that all time spent on a train is not productive, so an hour less on a train will mean that an hour more can be spent on business activities. The Department uses an average of £70,000 a year as the value of business travellers' time when it calculates how much these time savings are worth. The Department told us that this figure is based on surveys carried out in 2002-03 and reflects not just salary costs but business travellers' productivity as a whole, including their contribution to profits.[26]

14. The New Economics Foundation considered that more up-to-date information is needed about how people actually spend their time on trains and on what they value most about travelling by train. Business travellers may value the right conditions to work on the train combined with arrival on time more highly than shorter journey times. The Department's assumption that time on trains is unproductive combined with a high value for business travellers' time risks overestimating the benefits of high speed rail, exaggerating the negative effects of intermediate stations, which make journey times longer, and skewing investment decisions in favour of long distance travel rather than commuting. The time business travellers save by using high speed rail is valued at £54 per hour yet commuters' time saved getting to and from work is only valued at £7 per hour.[27] Such differences are hard to justify and yet vital for proving the case for long distance investment.

15. The lessons identified above all impact on the benefit-to-cost ratio of a project. The Department told us there are a variety of other "pillars" which it takes into account, including strategic judgements, when making a decision on whether a project is value for money. Without clear, transparent criteria for making investment decisions, including for example that a project must have a benefit-to-cost ratio of at least 1.5, the Department may be able to justify any individual investment decision whether or not it is good value for money. We asked the Department if it had considered a wide range of options as alternatives to investing in HS2, such as increased investment in local transport or in broadband. The Department told us that it had not considered the benefits and costs of these alternatives in its assessment.[28]



17   Qq 1, 24 Back

18   Qq 24-25, 57; C&AG's Report, para 1.15 Back

19   Qq 31-32 Back

20   Qq 73, 77; Committee of Public Accounts, 39th Report of Session 2010-2012, The InterCity East Coast Passenger Rail Franchise, HC 1035 Back

21   Q 5 Back

22   Qq 3, 5, 35-41; Ev 39 - Department for Transport, HS2 Demand Forecasting and Cap Year, paras 9-11 Back

23   Qq 25-29, 70-72 Back

24   Q 62 Back

25   Qq 42-49 Back

26   Qq 3, 62, 92- 98 Back

27   Qq 3, 59-61, 68, 118-121 Back

28   Qq 20, 80-81, 111-116, 128-134 Back


 
previous page contents next page


© Parliamentary copyright 2012
Prepared 6 July 2012