Scottish Affairs Committee - A Robust Grid for 21st Century ScotlandWritten evidence submitted by SP Energy Networks (SPEN)
FIGURE SHOWING AREAS SERVED BY SP TRANSMISSION, SP DISTRIBUTION, SP MANWEB1
Network & Fault Statistics from Typical Year2
1.0 Executive Summary
1.1 SP Energy Networks (SPEN) has a strong focus on customer service3 and is PAS 55 Accredited for our asset management processes, an internationally recognised standard. Within the regulatory framework we operate under, SPEN has made significant investment to ensure the network is resilient to storms, while also containing costs to customers. We requested and obtained increased investment allowances (+40 to 50%) from Ofgem to improve network performance through asset modernisation, maintenance, tree cutting and greater remote control and we continuously seek feedback from our stakeholders to support the investment plans that we put forward.
1.2 SPEN recognises the impacts that outages can have upon customers, especially under storm conditions where outages a can be prolonged. Keeping customers informed of progress under severe storm conditions is challenging in the initial stages given the sheer scale of the damage that has to be assessed, continuing access problems and adverse weather.
1.3 2011 was the worst year for storms for 11 years with six exceptional events.4 Our network and processes were rigorously tested as a result. Following any storm we complete a comprehensive review of our emergency processes and implement any recommendations that arise.
1.4 On 3 January the Met Office confirmed that we experienced the worst storm in 13 years and equal worst in 44 years, with structural damage to properties, transportation and other utilities wide spread across our area. Our Network experienced:
(a)
(b)
(c)
(d)
(e)
1.5 We are currently conducting a detailed storm review, engaging staff, customers and stakeholders to test our existing processes; this will be completed on 2 March 2012.
1.6 We recognise the difficulties our customers face during these events and the importance of effective communication to allow customers, who are able to, to make alternative arrangements. During and since the January event:
(a)
(b)
(c)
(d)
2.0 Investment in our Scottish Networks
2.1 In 2000 SPEN began a major investment cycle to replace a network that was installed in the period 19501–9705 (modern equivalent asset value of £15 billion). This investment has been improving resilience (to storms and flooding), restoration times, and advancing tree cutting and maintenance. SPEN has increased investment by a further 405–0% consecutively at the last two distribution price control reviews (2005 and 2010) to modernise our networks. In Transmission the increases have been even more significant at three times our current regulatory asset value (RAV, £1 billion). To justify this investment SPEN and our Regulator (Ofgem) conducted extensive stakeholder engagement to inform our plans.
(a)
(b)
(c)
2.2 This investment is critical to renewing the network. We believe that our proposals deliver strong performance at an appropriate cost to the consumer. This year we will be commencing further stakeholder engagement for the next distribution price control (to set our revenues from 2015 to 2023) and we will again be looking for customers views to inform our plans.
2.3 Cost to Consumer: According to Ofgem network charges represent 4% (Transmission) and 17% (Distribution) of the average £424 per annum electricity bill domestic customers receive from electricity Suppliers.6 If we were to underground SP Distribution’s overhead network it would cost over £5 billion, and add more than £225 p.a. (ca 50%) to each customer’s bill, before accounting for additional road opening costs and the cost of repairs that contribute to the higher full life cycle costs of underground cables.
3.0 Overhead Line Network Strategy
3.1 Following previous storms, and in particular the 1998 Boxing Day event, SPEN took the decision to improve the resilience of our overhead line network to storm conditions. This led to a revised strategy for our overhead network being built into our investment plans. This strategy includes:
(a)
(b)
(c)
(d)
3.2 Our strategy was based on a review of the primary causes of faults and extended restoration times. We also engaged an independent engineering consultancy (KEMA) to identify severe weather areas across our network (Figure 3.1); this is used in conjunction with performance information to target our investment programme at worst affected areas.
Figure 3.1: Severe weather areas identified by KEMA7
3.3 After implementing our strategy, KEMA were asked back to review the validity of our programme and strategy by assessing if it was having the expected impact.8 KEMA’s report concluded “the effectiveness of the improvement policies in addressing main line storm resilience has been demonstrated and the targeted improvement programme should continue”. Appendix 2 provides an example of a typical investment of this nature.
3.4 During 2010 to 2015 this continuing strategy will deliver a programme targeting 6800km of wood pole overhead lines (33% of the network) and 10% (ca 2,000km) of the network will be made compliant with the storm resilient tree cutting specification (ETR 132).
Having analysed our strategy we can also demonstrate that it has:
(a)
(b)
(c)
Our investment shows a direct improvement in overall system performance achieved between 1999–2000 and 2010–11 for all voltage levels.9 Today an average customer will experience an outage once every three years, for a duration of approximately one and a half hours, equating to a reliability of supply of around 99.999%. 10 years ago the same customer would experience a fault once every two years for a duration closer to two hours on average.
3.5 The charts in Figure 3.2 and 3.3 below detail the numbers of customers off supply and high voltage faults at any one time for historic storms.
Figure 3.2: Comparative Storm Performance—Customers off supply at any one time
Figure 3.3: Comparative Storm Performance—High Voltage faults on network at any one time10
3.6 From records we are able to compare our performance in January to the last comparable event in 1998 (which at that time was the worst storm in 30 years). Our investment and improved response means that the impacts of these events are much reduced since the 1990s. The improvement between 1998 and 2012 provides the strong evidence of this see table 2.4.
Table 3.1
COMPARISON OF CUSTOMER IMPACTS 1998 AGAINST 2012
|
26 Dec 1998 |
3 Jan 2012 |
||
|
Faults |
1,731 |
1,174 |
32% fewer faults |
|
Customers affected |
230,000 |
135,000 |
41% fewer customers |
|
Customers at peak |
90,000 |
70,000 |
22% fewer customers |
|
Length of impact |
9,874 customers off for 4 nights |
600 customers off for 4 nights |
4.0 Recent Extreme Weather Events
4.1 The table below (Table 2.511) shows that our Transmission and EHV network remains resilient in these types of extreme weather, with very few faults and then for very short periods only. The majority of customers are affected by HV overhead faults, 87% on 3 January, as a result of different network design necessary at lower voltages to enable customers to be connected efficiently.
Table 3.2
RECENT EXTREME WEATHER EVENTS
5.0 Emergency Procedures and Severe Weather Event Management
5.1 In addition to our investment programmes SPEN has focussed on ensuring that when severe weather events occur, our emergency procedures deliver an effective response. Emergency procedures are initiated when severe weather is forecast and our key staff hold clearly defined emergency roles.
5.2 Our advance preparations for severe weather includes the activities listed below, each of which will be escalated dependent on the probability, severity and locality of the weather forecast:
(a)
(b)
(c)
(d)
(e)
(f)
5.3 When an event occurs we look to optimise restoration of supplies as follows:
(a)
(b)
(c)
5.4 Although the worst of the weather may have passed from the customers perception, under storm conditions it is also common that the weather conditions hinder our repair and restoration efforts for a number of reasons ranging from access to the fact that the weather conditions our staff are working in can continue to be challenging, especially when they have been working long shifts.
6.0 Management of 3 January 2012 Event
6.1 Following the amber alert issued by the Met Office, SPEN mobilised 350 field staff and opened its central control Emergency Action Centre (EAC) at head office at 0830. At 08:14am the Met Office changed its weather warning from amber to red.12 SPEN responded quickly and:
(a)
(b)
(c)
Ayrshire, Central & Fife, Dumfries, Edinburgh & Borders, Glasgow, Lanarkshire.
(d)
(e)
6.2 The main impact of the storm occurred over a relatively short period of time on 3 January which affected customers across our Scottish network.13 SPEN staff worked tirelessly in dreadful conditions in the days following the storm to restore supplies, working 18 hour days in adverse conditions, including strong winds and horizontal rain. In some areas work was suspended on 4 January due to gusts over 65mph causing unsafe working conditions, although these remained challenging throughout the repair period.
6.3 Figures 6.1 and 6.2 show the substations off supply and customers affected by postcode at 13:00 on 3 January when 45,000 customers were off supply.
Figure 6.1: Substations affected
Figure 6.2: Customers affected by postcode14
7.0 Liaison with other Agencies
7.1 Our Head Office Emergency Action Centre (EAC) provides updates to officials of the Scottish Government, DECC and Ofgem. Our Customer Services Director and EAC staff engaged with the Scottish Government Resilience Room meeting throughout 3 January 2012 storm event. The meeting involved strategic members from relevant agencies eg Scottish Government, Local Authorities, SPEN, SSE, BT, Scottish Water, Transport Scotland, Police Service. Our Public Affair & Communications teams provided regular updates to the 44 MPs and 95 MSPs whose constituents we serve (following the recent storm we have identified two updates to our database resulting from a recent by-election and a boundary change). Our Communications team provide updates to the press and facilitate media interviews to communicate to our wider customer base.
7.2 Our Customer Liaison Officers work with local authorities and other third parties, such as charities, to ensure we can co-ordinate our efforts for our customers during storms.
8.0 Communication with our Customers
8.1 Our customer service operations coordinates the call centre activities from Kirkintilloch and is supported by our Prenton office to minimise wait times for our 3.5 million customers. Operational Control Centres in the same locations work closely with the Call Centre to restore supplies as quickly as possible through remote switching and dispatching field-staff.
8.2 As field-staff progress faults they communicate with the Control Centres to ensure up to date information is available for customers. However under severe storm conditions the level of accuracy is impacted by the scale of the task of assessing the damage and repairs.
8.3 Customer service strategy under normal circumstances:
(a)
(b)
(c)
(d)
(e)
(f)
8.4 Customer service strategy in storms has the following key differences:
(a)
(b)
(c)
(d)
(e)
(f)
8.5 Since April 2011 we have received:
(a)
(b)
(c)
(d)
8.6 From Thursday 5 January we offered more than 2,000 households hotel accommodation and hot meals if they were going to remain off supply beyond 9pm, households expected to be on supply by 9pm were also offered payment for hot meals.
9.0 Services for Vulnerable Customers:
9.1 We have 126,000 vulnerable customers on our Priority Services Register. These customers are contacted as a priority, when affected by a supply interruption, in order to understand their specific needs and to arrange assistance for them if necessary. We proactively seek information from customers who contact our call centres to ensure we update and expand our register.
10.0 Customer Compensation
10.1 Every five years (moving to 8 years from 2015) our regulator Ofgem reviews our investment plans and provides revenue allowances to fund agreed levels of investment and operating costs, and puts in place mandatory compensation levels for customers. Ofgem conducts “willingness to pay” research to inform these decisions. In December 2009 Ofgem concluded domestic customers should receive a £54 payment if they are off supply for more than 18 hours outside exceptional events.15
10.2 For Category 2 large exceptional events,16 compensation is due to customers off supply for a continuous period of 48 hours.
10.3 Customers affected by 3 January storm will receive:
(a)
(b)
(c)
10.4 The rules implemented by Ofgem require that customers claim this compensation, however we are contacting customers pro-actively to advise them of their entitlement and confirm payment details. We have set up a dedicated storm bureau to manage this process for our customers (see appendix 1).
11.0 Conclusions
11.1 SPEN is committed to delivering significant levels of investment to accommodate the demands of all our connected customers.
11.2 We have been focussing on continuously improving our network resilience and operational response in the face of emergencies since the 1990s.
11.3 We take seriously our obligations to our customers and the difficulties they face during prolonged outages and seek to learn from every event that affects us. These “lessons learnt” also feature in our price review submissions.
11.4 We welcome the opportunity to provide evidence to the Scottish Affairs Select Committee.
11.5 Finally, in Appendix 4 we have included pictures of both the general damage the storm caused and pictures of the specific dame caused to our network.
APPENDIX 1
DEDICATED STORM BUREAU
(a)
(b)
(c)
(d)
(e)
(f)
APPENDIX 2
EXAMPLE OF INVESTMENT STRATEGY
Dumfries, Penpont Primary substation circuit 12:17
(a)
(b)
(c)
In 2010 this circuit was targeted for modernisation:
(a)
(b)
(c)
This was completed for a cost of £1.1 million and the subsequent performance is as follows:
April 2010 to 8 December 2011:
(a)
8 December 2011:
(a)
(b)
(c)
3 January 2012:
(a)
APPENDIX 3
TREE CUTTING FOR SAFETY AND TREE CLEARANCE FOR STORM RESILIENCE
SPEN carries out tree cutting activities for two different purposes which are laid down in the ELECTRICITY SAFETY, QUALITY AND CONTINUITY (AMENDMENT) REGULATIONS 2006:
Tree cutting for safety.
Tree clearance for network resilience.
Safety Distance Tree Cutting
This involves tree cutting to provide a safe area around existing Overhead Line circuits to prevent the public from making contact with live Overhead Line circuits. There are also performance benefits for customer interruptions due to removing close proximity trees.18
(a)
(b)
(c)
(d)
Storm Resilience Tree Clearance
This involves the felling of trees which are within falling distance of existing Overhead Line circuits.19
Specified in Engineering Technical Report (ETR) 132—Improving Network Performance under Abnormal Weather Conditions by use of a Risk-Based Approach to Vegetation Management near Electric Overhead Lines—March 2006.
DTI Officials worked with the Electricity Industry (SPEN led the industry working group) in the development and publication of a new risk based methodology (ETR132) for determining where and when to best prioritise vegetation management work for the purposes of improving network resilience.
The obligation on electricity distribution companies is to have an additional 20% of their network compliant by 2035, which the DTI considered was balanced and proportionate to ensure the environmental, social and regulatory impacts were not overlooked.20
ETR132 reflects the practices that SPEN has been implementing since 1998. Had SPEN waited until 2009 to begin to implement the requirements of ETR132 we expect that recent storms would have resulted in greater disruption to customers.
APPENDIX 4
PICTURES SHOWING GENERAL AND NETWORK DAMAGE ON 3 JANUARY 201221
2 February 2012
1 Figure not printed. Available on request to the Committee.
2 NAFIRS (National Fault and Interruptions Reporting Scheme) reports for 2008–09. Transmission—132kV/275kV/400kV, Distribution—33kV Extra High Voltage (EHV), 11kV High Voltage (HV), and 415v/230v Low Voltage (LV)
3 Ranked 3rd and 5th in Ofgem customer service league tables for 2010–11
4 Exceptional events defined by Ofgem as more than 8 times the normal daily average high voltage faults, introduced in 2000
5 Consistent with all U.K.s electricity transmission & distribution infrastructure
6 http://www.ofgem.gov.uk/Media/FactSheets/Documents1/updatedhouseholdbillsjan11.pdf
7 Figure 3.1 not printed. Available on request to the Committee.
8 Kema Limited—Scottishpower An assessment of HV overhead asset storm resilience—19 February 2007
9 Includes all fault types, detailed system performance reports are available from Ofgem’s homepage
10 Figures 3.2 and 3.3 not printed. Available on request to the Committee.
11 Customer numbers associated with distribution faults as reported to Ofgem
12 Defined by Met office http://www.metoffice.gov.uk/weather/uk/advice/
13 http://www.metoffice.gov.uk/climate/uk/interesting/2012_janwind/
14 Figures 6.1 and 6.2 not printed. Available on request to the Committee.
15 Defined by Ofgem as causing > 8 times daily average number of high voltage faults
16 Defined by Ofgem as causing >13 times daily average number of high voltage faults
17 Map not printed. Available on request to the Committee.
18 Diagram not printed. Available on request to the Committee.
19 Diagram not printed. Available on request to the Committee.
20
THE ELECTRICITY SAFETY, QUALITY AND CONTINUITY (AMENDMENT) REGULATIONS 2006 GOVERNMENT RESPONSE
Full document at: http://webarchive.nationalarchives.gov.uk/+/http://www.berr.gov.uk/files/file33408.pdf
21 Pictures not printed. Available on request to the Committee.
