4 Procurement processes
Costs of procurement
56. Procuring goods and services incurs costs for
councils and those doing business with councils at all stages
of the process, including the pre-tendering stage, during the
tender process and during the implementation of the contract.
A typical procurement exercise for a contract above EU thresholds
costs a tendering body some £40,000-50,000.[121]These
costs are higher than those incurred by firms in other European
Union countries. The Centre for Economics and Business Research
(CEBR) report published in July 2013 found that UK procurement
processes were the most expensive in the EU and took some 53 days
longer on average.[122]
APPLICATION OF EU PROCUREMENT RULES
57. There are detailed rules on how procurement exercises
by public bodies must be conducted set out in the Public Contract
Regulations,[123] which
implement the current EU Directive on public procurement requirements.[124]
Witnesses criticised the manner in which the EU rules had been
transposed into UK law. ESPO considered that the UK regulations
made authorities "very timid" since they gave licence
to "vexatiously minded companies" to take public bodies
to court for the "slightest, most technical of transgressions".[125]
Dr Telles noted, however, that there was only a slim likelihood
of this.[126]ESPO recommended
the "wholesale rewriting" of regulations to allow councillors
freedom to decide what standards they wanted suppliers to meet
and to construct policies to meet local priorities.[127]
58. Some 75% of all contracts tendered in the UK
have a value below the thresholds at which the full EU requirements
apply, but witnesses contended that councils applied the full
rules to many of these lower value contracts, adding unnecessary
costs and bureaucracy. Dr Telles said that some councils used
for lower value contracts approaches designed for "very expensive
contracts" above the EU thresholds, noting that this disadvantaged
SMEs in particular.[128]
Scape considered such over-use of regulations to be due to a cultural
problem whereby council procurement officers were "paralysed"
by fear over breaching EU rules.[129]
However, a survey by FSB in 2013 identified an increase from 74%
to 83% in authorities adopting different processes for contracts
below EU threshold tenders. FSB considered this to be "significant
progress", but urged further rapid progress towards all authorities
adopting simplified processes for contracts below EU thresholds.[130]
The Federation of Master Builders recommended work across the
sector with the LGA and others to ensure all those involved in
public procurement were properly informed about any limitations
created by the rules.[131]
The new Directive on public procurement aims to make procurement
faster and less costly for businesses and procurers. The Cabinet
Office, with DCLG, is preparing for its early transposition so
as to take advantage of the new rules "as soon as possible".[132]
59. It is imperative that councils act swiftly
to cut costs for those wishing to do business with them. Too many
councils apply EU regulations over-zealously, using them as a
self-serving justification to retain overly bureaucratic approaches.
This approach is pervasive, and a cultural change is needed. Local
authorities need to become more confident in their application
of EU rules. The first step is for the Government and sector leaders,
including the Local Government Association, to spell out what
constitutes a sensible approach which will meet regulations in
a proportionate manner. The LGA should produce guidance on this
aspect of the new EU Directive on public procurement and work
with local authorities to disseminate best practice case studies
of those councils already minimising costs to suppliers and potential
suppliers.
Process improvements
60. The failure of councils to streamline procurement
processes was a key concern, particularly for SMEs. Market Dojo
for example told us that rigid processes had prevented it from
delivering "substantial savings" for one county council,
contrasting this with another council's acceptance of e-auctions
which had kept costs of auctions down. Representing the company,
Alun Rafique referred to a number of councils which had used a
"very onerous"procedure for low-value tenders, stating
that this "put off"SMEs from applying for these tenders
since they took up "a lot of time and money".[133]Shortcomings
in the public sector's ability to improve access by SMEs and social
enterprises to government contracts have been flagged up by the
Public Administration Select Committee (PASC). That Committee's
2013 Government Procurementreport concludedthat insufficient
change had been introduced to stop procurement favouring large
companies.[134]
61. Some councils are trialling simplified procedures
to keep procurement costs down. Dr Telles cited his work with
the Institute for Competition and Procurement Studies on a simplified
open procedure which it was piloting with three local authorities
through the 'Winning in Tendering' project. He noted that "given
the right tools and processes, contracting authorities will advertise
low value contracts instead of using a request for quotes".
Changes to keep costs down included the full use of e-procurement
from start to finish; publication of a one page executive summary
with all the necessary information required for the supplier to
make a decision whether to compete for a contract; refinements
to the wording and style of information presentation to improve
clarity especially for non-experts. This had reduced procurement
process timescales from more than 100 days to around 38 days.
Wider simplification of some processes is also likely to result
from the Government's recent consultationon procurement reforms
across the whole public sector,[135]
in response to Lord Young's May 2013 report Growing Your Business.[136]
The new EU Directive on public procurement will also require public
bodies to simplify processes, including for example by requiring
e-procurement processes to be used.
PRE-QUALIFICATION QUESTIONNAIRES
62. A specific issue addressed by the Government's
consultation and by many witnesses was the cost and unnecessary
burden of completing individual, and often complex, Pre-Qualification
Questionnaires (PQQs).[137]
The CBI cited the example of a construction company which spent
on average £8,000 per PQQ which, with 200 tender exercises
a year, added up to some £1.6 million spent on pre-qualification
alone.[138] The Specialist
Engineering Contractors' Group (SEC Group) told us that its research
had found that its member firms spent over 60,000 days a year
filling in questionnaires, and the duplication required to pre-qualify
in Wales as well as England cost its firms £20 million a
year.[139]The Sheffield
Third Sector Assembly told us during our visit to Sheffield that
the requirements councils placed on organisations in order to
get on supplier lists were disadvantaging many third sector organisations.[140]
The President of Sheffield Chamber of Commerce also considered
that PQQs were too complex and many firms were therefore "put
off" from entering tendering processes, but he welcomed Sheffield
City Council's proposed PQQ simplification.[141]
Indeed Sheffield City Council told us that it had developed a
standardised PQQ for use across the whole region.[142]Standardisation
of forms was recommended by a number of private sector representatives.
Alasdair Reisner from CECA considered it to be "insanity"
that suppliers must fill in "hundreds of bespoke forms [for
different councils] to do what in essence is one job" arguing
for a single, standard pre-qualification form, not solely for
local authorities but for all public sector procurement.[143]The
Federation of Master Builders supported the use of the standard
PAS 91 form for construction contracts,[144]
an approach endorsed by the Electrical Contractors Association
which further recommended that a common system of PQQs should
be established across the public sector.[145]
This standard approach would also assist councils in joining together
with other local bodies to deliver services funded by community
budgets.
63. DCLG told us the Government wished to see PQQs
eradicated for low value contracts, with mandation of a core,
standardised PQQ for high value contracts, which would allow suppliers
to provide data once only.[146]
The Minister, Baroness Stowell, told us that PQQs would only be
retained for contracts above the EU threshold and that there would
be a standard approach for these from 2014.[147]Halton
Borough Council told us that it had already removed PQQs from
the council procurement process for contracts above EU threshold
levels.[148]The LGA
told us that 85% of councils did not use PQQs for contracts below
the EU thresholds and would discuss the Government's proposed
recommendations with DCLG.[149]It
should be noted that we received little evidence arguing for total
abolition of PQQs since some form of pre-evaluation enables councils
to keep costs down by screening out unviable bids at an early
stage.
64. Whilst some councils have streamlined their
processes and are taking a proportionate approach to the pre-tender
information they require potential suppliers to provide, the default
option in too many procurement exercises appears to be to demand
excessive information not commensurate with the specific contract
needs. Furthermore, suppliers who wish to work with more than
one council are frequently required to complete similar, complex
forms. There is clear scope for more standardisation and simplification
across the sector to cut the suppliers' costs and to facilitate
the use of community budgets to deliver joined-up local services.
We therefore support the Government's proposals to standardise
on a national basis data collection from tenderers. The Local
Government Association should take the lead in ensuring that all
Pre-Qualification Questionnaires are as simple and straightforward
as possible. This would entail potential suppliers filling in
a form once only foruse by any public body. However, whilst we
concede that some council data collection processes for lower-value
contracts can be unduly burdensome, we do not consider the argument
to be fully made for the removal of Pre-Qualification Questionnaires
for such contracts. There are financial benefits to be gained
from weeding out unviable tenders at an early stage, prior to
more costly full evaluation of bids.
PAYMENT POLICIES
65. Whilst most councils operated policies that ensure
that their suppliers were paid promptly, we were told that there
was a problem with passing these terms on down the supply chain
to sub-contractors. FSB noted that, although 95% of councils had
policies specifying prompt payment of suppliers, with 68% adopting
a 28 day or less payment period, only 38% of councils required
their contractors to apply the same standard. Many contractors
applied policies to pay sub-contractors only after 60, 90 or even
120 days which could be particularly problematic for small firms
vulnerable to cash-flow crises.[150]
FSB noted that the issue could be addressed swiftly and effectively,
as Wakefield Council had done, through the use of explicit contract
clauses requiring suppliers to pass the council's payment terms
on through their supply chains. FSB strongly encouraged all local
authorities not already requiring the passing on of payment terms
to revise their terms and conditions accordingly as a matter of
urgency.[151]
66. Councils should as a matter of course pay
contractors promptly and include a requirement in contracts requiring
contractors to ensure their sub-contractors are paid promptly
right down the supply chain. Councils should publicise this policy
and monitor closely the implementation of these terms through
spot checks. Contracts must also require contractors to report
failure to comply with these conditions. Local authorities should
take into account any failure by a contractor to comply with the
conditions when assessing tenders for any future work.
121 Q142 Back
122
"UK public sector procurement most expensive in EU"
Supply Management, 11 July 2013 Back
123
Public Contract Regulations 2006 (SI 2006/05) Back
124
Directive 04/18/EC will be repealed following adoption of the
new Directive/2014/../EU of the European Parliament and of the
Council on public procurement The full formal EU procedures must
be followed for any public contract relating to certain categories
of procurement. Under the proposed new EU measures, the threshold
will be set at £175,000, broadly equivalent to current Directive
levels. The new Directive will however introduce a higher threshold
equivalent to £620,000 to apply to a wide range of health
and social services, above which member states are required to
issue prior information notices but will then be free to determine
their own procedures Back
125
Eastern Shires Purchasing Organisation (LGP 06) Back
126
Q380 Back
127
Eastern Shires Purchasing Organisation (LGP 06) Back
128
Q363 [Dr Pedro Telles] Back
129
Q128 [Mark Robinson] Back
130
Federation of Small Businesses (LGP 30) Back
131
Federation of Master Builders (LGP 70 ) See also Federation of
Master Builders, Improving public procurement for construction
SMEs,, June 2013 Back
132
Department for Communities and Local Government (LGP 63) Back
133
Q363 Back
134
Public Administration Select Committee, Sixth Report of Session
2013-14,Government Procurement, HC 123,p5 Back
135
HM Government, Consultation: Making public sector procurement
more accessible to SMEs, September 2013 Back
136
Lord Young, Growing your business: a report on growing micro-businesses,
May 2013 Back
137
A Pre-Qualification Questionnaire is an initial questionnaire
seeking information about an organisation which may wish to tender
for a council contract. It may cover financial, legal compliance,
policies and procedures and customer base of an organisation.
A PQQ may be required when an organisation applies to join an
approved/preferred supplier list, at the first stage of a tender
process or when applying to join an accreditation scheme. The
EU rules on PQQs are set to change under the new Directive (Article
59). Back
138
Confederation of British Industry (LGP 59) para 8 Back
139
Specialist Engineering Contractors' Group (LGP 60) para 4.3 Back
140
Q281 [Ian Drayton] Back
141
Qq280-281 [Stephen Williams] Back
142
Q310 Back
143
Q 173 [Alasdair Reisner] Back
144
Federation of Master Builders (LGP 70) Back
145
Electrical Contractors Associations (LGP 40) Back
146
Department for Communities and Local Government (LGP 63) Back
147
Q425 Back
148
Q2 [Lorraine Cox] Back
149
Q6 Back
150
Federation of Small Businesses (LGP 30) Back
151
As above Back
|