MoD Supplementary Estimates 2012-13 - Defence Committee Contents


2 The MoD Supplementary Estimate


4.  The MoD sought, in the Estimate, a net increase in Resource Departmental Expenditure Limit (DEL)[6] of £398 million and a net reduction in Capital DEL of £1,957 million. It also sought a reduction in Resource Annually Managed Expenditure (AME)[7] of £685 million and an increase in Capital AME of some £35 million.[8] Table 1 provides a breakdown of the overall requests for increases or decreases in expenditure.

Table 1: Changes in Resource and Capital Expenditure in the Supplementary Estimate 2012-13
Resource Expenditure £ M
Provision of Defence Capability (Resource DEL) 758
Operations and Peace Keeping (Resource DEL) (360)
Net increase in Resource Departmental Expenditure Limit (DEL) 398
Reduction in Annually Managed Expenditure (685)
Total Net reduction in Request for Resources (287)
Of which: administration expenditure 140
programme(42)
Capital Expenditure  
Reduction in Provision of Defence Capability (Capital DEL) (1,807)
Operations and Peace Keeping (Capital DEL) (150)
Net reduction in Capital Departmental Expenditure Limit (DEL) (1,957)
Increase in Capital Annually Managed Expenditure 35
Total Net Request for Capital (1,932)
Total Change in Capital and Resource expenditure (2,209)

Source: Ministry of Defence[9]

Decrease in the level of expenditure requested

5.  The reasons behind the overall reduction in estimated expenditure for 2012-13 of over £2.21 billion are detailed in the MoD Memorandum, in particular, the impact of reductions in expenditure on the Equipment Programme and lower than anticipated redundancy and other restructuring costs.[10] The MoD has been allowed Budget Exchange[11] of some £1.59 billion and wishes to use this money in 2013-14 and 2014-15.[12]

BUDGET EXCHANGE

6.  We asked the MoD to break down the underspends which led to the need for Budget Exchange. The MoD told us they resulted from:

  • The Departmental Unallocated Provision of £480 million—a sum set aside as a risk provision against unforeseen events creating pressure on the Defence programme—which was not needed; and
  • Changes to the plans to deliver commitments made in the Strategic Defence and Security Review and involving the Equipment Programme and redundancies in the Armed Forces—£550 million of a provision for redundancy payments and industrial restructuring, £200 million for faster than planned drawdown of manpower due to higher rates of voluntary outflow and £250 million from the Equipment Programme because of project slippages and [lower costs through] successful commercial negotiations.[13]

7.  We welcome the availability of Budget Exchange. We will continue to monitor the future use of Budget Exchange by the MoD.

Additional costs of military operations

8.  The additional costs of military operations are met by the Treasury Reserve and not by the MoD. The MoD now estimates the bulk of the costs of operations in Afghanistan and elsewhere at the time of the Main Estimates and only requests adjustments in the Supplementary Estimate. In the early years of the operations in Afghanistan and Iraq, the MoD requested expenditure for such operations only in the Supplementary Estimate. In April 2012, the Treasury required the MoD to request at least 90 per cent of the cost of operations in the Main Estimate—we are exploring the rationale behind the use of a percentage with regard to the Main Estimate 2013-14.

9.  The MoD identified the costs of operations in Afghanistan, the Wider Gulf and the Conflict Pool within the Supplementary Estimate separately in its Memorandum.[14] The amount now requested for these operations in 2012-13 is some £3.2 billion, a 14 per cent reduction—some £0.5 billion—in the sum requested at the time of the Main Estimate. A summary of the costs of operations is given in Table 2 below.

Table 2: Forecast costs for operations in Afghanistan, the Wider Gulf and for the Conflict Pool
Supplementary Estimate 2012-13
Theatre of operation Total Main Estimate 2012­13

£m

Direct Resource DEL

£m

Non cash Resource DEL

£m

Capital DEL

£m

Total AME request

£m

Total Supplementary Estimate 2012­13

£m

Afghanistan3,610.4 1,972.3519.6 597.09.3 3,098.2
Wider Gulf42.7 38.70 4.00 42.7
Conflict Pool 52.2 54.3 00 054.3
Total3,705.3 2,065.3519.6 601.09.3 3,195.2

Source: Ministry of Defence[15]

AFGHANISTAN

10.  The additional cost of operations in Afghanistan is forecast at some £3.1 billion in 2012-13, some 14 per cent less than the forecast at the time of the Main Estimate. The MoD told us that this reduction of some £512 million was due to the "announced reductions in UK troop levels in Afghanistan in 2013 and consequent fall in activity costs".[16] We asked the MoD to provide us with a more detailed explanation of this reduction. Table 3 shows a comparison between the expenditure figures from the Main and Supplementary Estimates with accompanying explanatory notes.[17]

Table 3: The Estimated Cost of Operations in Afghanistan for 2012-13
Cost TypeMain Estimate

£m

Supplementary Estimate

£m

Difference

£m

Percentage Difference
Direct Resource DEL
Civilian Personnel 32.132.1 00
Military Personnel 240.2235.0 (5.2)A(2%)
Stock/Other Consumption 716.1654.0 (62.0)B(9%)
Infrastructure Costs 233.1176.1 (57.0)C(25%)
Equipment Support Costs 652.3482.3 (170.0)D(26%)
Other Costs and Services 483.0415.0 (68.0)E(14.)
Income Foregone/ (Generated) (28.0)(28.0) 00
Non nuclear charge against provision 5.75.7 00
Total Direct Resource DEL 2,334.41,972.2 (362.2)(11%)
Non cash Resource DEL 519.6519.6 00
Total Resource DEL 2,854.02,491.8 (362.2)(9%)
Capital DEL
Other capital (fiscal) 325.7213.7 (112.0)(34%)
Single Use Military Equipment 421.3383.3 (38.0)(9%)
Total Capital DEL 747.0597.0 (150.0) F (20%)
TOTAL ESTIMATED DEL COSTS 3,601.13,088.8 (512.2)(14%)

A: Council Tax relief for troops deployed on operations in Afghanistan are now included in the cost of Defence Capability and is no longer met from the Special Reserve.

B: The progress made in Afghanistan and the increasing ability of Afghan National Security Forces (ANSF) to lead operations means that less consumables, such as fuel, certain types of ammunition and vehicle spares are required by UK Forces. In addition, the reduction of UK troops to 9,000 at the end of 2012, and the announced reduction to 5,200 by the end of 2013 means that less materiel will be required for Afghanistan-specific pre-deployment training.

C: The ongoing and on-track transition process in the UK Area of Operations means that locations, such as Patrol Bases, are being handed over to the ANSF or closed, reducing the infrastructure costs. As the UK draws down, less additional infrastructure to support Afghanistan PDT will be needed.

D: Efficiencies in contract management, better use of existing resources and a change in operational tempo has resulted in a reduction in the cost of maintaining and supporting equipment in Afghanistan. The entry into service of the bulk of the Protected Mobility fleet, procured under the Urgent Operational Requirements (UOR) process, means that these support costs are being anticipated and managed more effectively.

E: Additional costs have been reduced in line with the current and forecast troop levels. In particular, skill transfer to MoD personnel has reduced some of the cost of external specialist support.

F: A proportion of this reduction reflects the reduction in operational tempo and hence consumption of capital spares. However, the majority is simply the result of the £5.8 billion investment in equipment. through the UOR process since operations began. The success of this equipment purchased means that the MoD has reduced its requirement for further expenditure this year.  

Source: Ministry of Defence[18]

11.  The handover of responsibility for security in areas of Afghanistan to the Afghan National Security Forces has resulted in lower than expected expenditure. The closure of some forward operating bases and reduced numbers of patrols by UK Armed Forces has led to the need for less materiel, fewer capital spares and reduced infrastructure costs.[19]

12.  As we noted in our recent Report: Securing the Future of Afghanistan,[20] the MoD has already started to withdraw some equipment and materiel from Afghanistan and we remain concerned that equipment should not be withdrawn early in such a way as to cause difficulties for the UK Armed Forces still in Afghanistan.

13.  We welcome the fall in the costs of operations in Afghanistan reflecting a reduced involvement in combat operations. But the closer we get to final withdrawal the riskier the circumstances in which UK Forces will be operating. The MoD should not withdraw equipment early or reduce costs to the extent that would put the lives of UK Armed Forces personnel at risk or that would leave them living or operating in circumstances which place them at unnecessary risk.


6   Department Expenditure Limits (DEL) cover all administration costs and programme expenditure except where programme expenditure cannot be subject to close control over a three year period or spending relates to non-cash costs other than depreciation and impairments-Public Expenditure Statistical Analyses 2012 Cm 8376.  Back

7   Annually Managed Expenditure (AME) is spending which does not fall within DELs. Expenditure in AME is generally less predictable and more difficult to control than expenditure in DEL-Public Expenditure Statistical Analyses 2012 Cm 8376.  Back

8   Ev 1 Back

9   Ev 1-2 Back

10   Ev 4 Back

11   Budget Exchange is mechanism by which Departments can carry forward underspends in resource an capital budgets subject to rules set out in the Consolidated Budgetary Guidance by HM Treasury. Back

12   Ev 4 Back

13   Ev 15 Back

14   Ev 7 Back

15   Ev 7, Table 9 (modified) Back

16   Ev 7, paragraph 5.2  Back

17   Ev 16 Back

18   Ibid, Table 8 and notes Back

19   Ev 7 and Ev 16 Back

20   Defence Committee, Securing the Future of Afghanistan, Tenth Report of Session 2012-13, HC 413 Back


 
previous page contents next page


© Parliamentary copyright 2013
Prepared 13 June 2013