Smart meter roll-out - Energy and Climate Change Contents


3  Roll-out stages and timescale

37. Roll-out will happen in two stages—foundation stage and mass roll-out, when the vast majority of smart meters will be installed. Foundation stage, which is currently under way, is seen as a period for learning about smart meter usage and dealing with teething problems. Energy suppliers have taken very different approaches to installing smart meters during this stage. When we asked how many they had installed to date, the figures they gave ranged from 5,000 to 1 million.[81] Mass roll-out is set to take place between autumn 2015 and the end of 2020, but when this inquiry was launched, mass roll-out was due to start at the end of 2014 and finish by the end of 2019. On 10 May 2013, DECC put the dates back by a year in response to concerns about timescale.[82]

Concerns about the timescale for mass roll-out

38. A number of witnesses warned of the potential consequences of pressing ahead with mass roll-out, particularly with the 2014-2019 dates, before certain requirements had been met.[83] National Grid outlined its concerns as follows:

    Feedback gathered through our pricing consultation regarding the smart metering mass roll-out has indicated a general view that completion by the end of 2019 remains highly challenging...The uncertainties that still exist regarding technical and infrastructure requirements result in a slower roll-out profile than currently expected…with smart meter roll-out completion taking several years longer than currently forecast.[84]

39. Others raised concerns that if important technical and infrastructure requirements were not in place before roll-out, costs could increase significantly and some consumers could have a poor experience, which might have a reputational impact on the roll-out programme.[85] EDF and SSE described the potential for a "delivery bubble" towards the end of roll-out, with the cost of installing meters increasing as the deadline for completion approached.[86] EDF outlined the risks and the choices facing suppliers in this way:

    As the 2019 completion date is a Licence Condition, Suppliers have two choices: either to start the rollout ahead of the delivery of the key enablers, or delay rollout and compress the delivery period. Both choices are likely to increase the costs to consumers, deliver a sub-optimal customer experience and introduce unnecessary risk to the GB programme and the delivery of the expected benefits.[87]

40. Andrew Ward of ScottishPower gave an example of how consumers could be affected if problems were found in smart meters after they had been rolled out on a wide scale and these problems then had to be rectified by reinstalling meters:

    Of the initial 30,000 meters that we deployed in 2010, we have had to replace 5,000 of the SIM cards that are in those meters. The understanding we had when we installed the meters was that the SIM cards would be sufficient to last the life of the meter, so that has gone wrong. We have had to interrupt the lives of 5,000 customers and reinstall those meters.[88]

Witnesses were particularly concerned about:

  • the fact that the technical specifications that will ultimately need to be met by smart meters—SMETS 2—have not yet been finalised;[89]
  • the need for the Data Communications Company (DCC) and communications system to be up and running for SMETS 2 meters to be fully operational;[90] and
  • the need for proper end-to-end system testing before mass roll-out.[91]

We consider two of these key issues—SMETS 2 specifications and the DCC—in later chapters. The need for proper system testing is discussed below.

System testing and analysis

41. Many witnesses highlighted the importance of ensuring that the smart metering system and smart grid were secure and that sufficient time was allowed for end-to-end system testing and analysis.[92] The Institution of Engineering and Technology (IET) said:

    Throughout the programme, the IET has repeatedly stressed that secure operation of individual components of the smart metering system, though important, cannot guarantee system security. End to end system security is critical...The tight time constraints should not be allowed to compromise rigorous end to end security analysis and testing of the resulting system.[93]

Dr Martyn Thomas of the IET emphasised the need for rigorous analysis "using mathematically formal specifications and the associated tools" to establish whether there were "vulnerabilities that could be exploited, or combinations of circumstances that might cause a significant failure, which would only appear later on and which would then cause a need for substantial rework."[94] He also noted that such analysis was "not particularly expensive", had "reduced the final cost of systems" everywhere it had been used, and would "reduce the testing times".[95]

42. Andrew Ward gave a practical example of what could go wrong:

    The risks are real...I will give you an example from part of our global group in America. They have now installed over 600,000 meters and I believe the common misconception is that software upgrades on the meters can be done electronically from a distance—you don't need to attend the property. As part of that deployment they rolled out, at the point of 200,000 meters they had to replace 5,000 meters because they could not update the communications over the wire. They had to again attend that property, a physical visit. It is a real example of what could potentially happen in the UK. That is why there is a desire from a ScottishPower point of view to test thoroughly what is actually in there before we mass deploy in the UK.[96]

NEW MASS ROLL-OUT DATES

43. Several witnesses welcomed the new 2015-2020 timescale for mass roll-out.[97] Tony House of SSE said it would enable a lot of the risks that had been identified "to be mitigated", and Dr Neil Pennington of RWE npower agreed that the delay was "welcome".[98] British Gas, E.ON and First Utility thought the 2014-2019 timescale had been achievable, but also saw the change in timescale as "pragmatic".[99]

44. The IET was more cautious about welcoming the new dates. Dr Thomas told the Committee:

    They are better than the old dates, in that they do give us an additional year to make sure that the specifications are sound and to fit things in better to the engineering realities. However, since we don't have the full specifications, we don't know the details of the bids that have been put in by the DCC and other communication suppliers, we don't know what their proposals for assurance will be, we don't know what compromises will come out of the negotiations over those contracts, therefore we don't know the full engineering reality of the roll-out of that process. On that basis, setting timescales now is simply a mistake. At the very least we need to be flexible, once those things are known, and to be willing to adjust them again if necessary...timescales need to be driven by the engineering realities.[100]

Consumer Focus and the Federation of Small Businesses also thought that there should be sufficient flexibility in the timescale to ensure that roll-out was done well.[101] Audrey Gallacher commented:

    The way we look at it is that nobody is going to remember when roll-out commenced or whether it took five or six years. They are going to remember whether it worked. Let's not sacrifice what is, after all, a multi-billion-pound programme for the sake of meeting a date. Let's make sure it fulfils its objectives in terms of the consumers accessing the benefits of smart meters as well as industry.[102]

We asked DECC whether there would be flexibility in the timescale to accommodate any further possible problems. Baroness Verma said: "I don't see further delays...I think we are in a very good place now".[103]

45. We welcome DECC's recent announcement that the dates for mass roll-out are being pushed back by a year. However there needs to be some flexibility in the new timetable, which should be driven by engineering and infrastructure requirements and the need to avoid artificial deadlines acting to push up programme costs. DECC should be prepared to amend the timetable further if more time is needed to address any systemic issues that may arise, to respond to further delays to technical and infrastructure requirements for roll-out, or to prevent cost escalations for other reasons.


81   Q 205 [Tony House, Paul Spence, Dr Andrew Pennington and Andrew Ward]; Q 258 [Stuart Rolland, Darren Braham and Don Leiper] Back

82   DECC, Written Ministerial Statement by the Rt Hon Edward Davey MP: Secretary of State for Energy and Climate Change on Smart Metering, 10 May 2013 Back

83   Ev w5; Ev 80; Ev 87; Ev 99; Ev 126  Back

84   Ev w5 Back

85   Ev 80; Ev 87; Ev 99; Ev 126; Q 220 [Andrew Ward]; Q 247 [Tony House] Back

86   Ev 87; Ev 99  Back

87   Ev 99. More on EDF's key enablers can be found in its submissions of written evidence Ev 99 and Ev 104, and in the oral evidence transcript at Q 211. Back

88   Q 220 [Andrew Ward] Back

89   Ev 65; Ev w75; Ev 80; Ev w27; Ev 126; Ev 146; Ev 150. SMETS 2 = the second version of the Smart Metering Equipment Technical Specifications. SMETS are discussed in more detail in chapter 5. Back

90   Ev 65; Ev 121; Ev 104; Q 247 [Tony House]; See background section for more on the DCC. See also Chapter 4, where it is discussed in more detail. Back

91   Ev 65; Ev 80; Ev 126  Back

92   Q 72 [Allen Creedy]; Q 75 [Audrey Gallacher]; Q 82 [Sean Weir]; Qq 170-73 [Dr Thomas]; Q 220 [Andrew Ward]; Ev 65; Ev w75; Ev 80; Ev 87; Ev 89; Ev 99; Ev w122; Ev 110; Ev 121; Ev 126  Back

93   Ev 80  Back

94   Qq 170-73 Back

95   Qq 170-73 Back

96   Q 220 Back

97   Qq 215-19 [Tony House and Dr Neil Pennington]; Ev 104; Ev 145; Ev w136 Back

98   Qq 215-19 Back

99   Ev 110; Ev 71; Ev 85; Q 265 [Stuart Rolland, Don Leiper and Darren Braham] Back

100   Qq 175-77 Back

101   Qq 74-5 [Audrey Gallacher and Allen Creedy] Back

102   Q 69 Back

103   Q 343 Back


 
previous page contents next page


© Parliamentary copyright 2013
Prepared 27 July 2013