Capital and operating costs over 5 years (this is the same method as used in the Commission IA)
Annex
GB Costs associated with implementation of Roadside
Inspection proposal
As at 15 May 2013
Item
|
Requirement
|
Original Cost
(£m)
|
Likely General Approach Cost
(£m)
|
New Roadside testing vehicles
| Purchase (will not be needed)
| £11 | £0
|
Meeting 5% Roadside target
| Extra staff cost (specific target dropped and will not include the N1 van fleet)
| £19 | £0
|
Annual retraining of testers1
| Training cost and trainee time (Roadside inspectors)
| £18 | £0
|
TOTAL
| | £48
| £0
|
|
All costs are GB only, NI and Gibraltar are
not included. Notes (relate to Periodic Testing proposal):
1 Existing training
will be sufficient.
|