House of Commons Financial Plan 2014/15-2017/18, including draft Estimates for 2014/15 - Finance and Services Committee Contents


2  Administration Estimate

Background

6.  In December 2010 the House of Commons Commission committed itself to reducing the Administration Estimate by at least 17% by 2014/15, from a baseline of £231 million in 2010/11. This was in line with reductions being made across the wider public sector. The Commission also agreed provisional totals for the resource element of the Estimate of £228 million in 2011/12, £224 million in 2012/13, £220 million for 2013/14 and £210 million for 2014/15. This path was intended to deliver the Commission's savings target.

7.  Estimates were laid in line with this path in 2011/12 and 2012/13. The Estimate laid for 2013/14 was £218 million—£2 million below the path. This reflected the decision of the House on 20 March 2013 that the cost of Members' allowance of pre-paid envelopes and stationery would be met from the Members Estimate rather than the Administration Estimate from 2013/14.

8.  The current financial planning round extends beyond the period of the current savings target. In June 2013, the Commission agreed a remit for the round. In particular it agreed that the existing savings target for 2014/15 should be recalibrated to reflect transfers between estimates; agreed that the Finance and Services Committee should continue to look for opportunities to make further efficiencies and ensure value for money in the delivery of services; and agreed that future funding for enhanced scrutiny and related functions should not necessarily be financed from within existing budgets. Otherwise, for planning purposes, the resource budget is assumed to be flat in real terms from 2015/16 onwards. As the Estimate is agreed annually, this assumption does not preclude the actual budget for years after 2014/15 being set at a different level.

9.  To put the current plan in context, there was a steady increase in spending on the Administration Estimate in the five years 2004/05 to 2009/10—roughly the period of the 2005 Parliament. Once adjustments are made for non-cash items and grants, and the impact of inflation using the GDP deflator, total spending rose by some 14%, or 2.7% per annum, in real terms. This was a period when the House Administration faced a number of additional requirements, mainly driven by decisions of the House or its committees. Examples include decisions to expand public engagement and improve ICT provision. Another significant driver of spending was levels of activity, for example increases in the number of written Parliamentary Questions and Early Day Motions. External factors such as increased security requirements also added to total spending.

Recalibrating the target

10.  A further significant transfer will occur on 1 April 2014 as result of the merger of the pension scheme for House staff with the Principal Civil Service Pension Scheme. In return for a one-off payment in respect of outstanding liabilities, the Cabinet Office will bear the on-going accounting charges arising from the liabilities. This will reduce the net annual charge to the House by some £19 million per annum.

11.  The Committee is recommending that two additional charges are also treated as out of scope:

  • On 12 June 2007 the House of Commons endorsed a proposal by the Administration Committee that there should be a dedicated space for educational visitors to be provided on or off the Estate complemented by engagement with those who do not visit Westminster.[1] Options for such a facility are currently being considered. If such a facility be provided, the additional running costs (which include staff, security, ICT equipment, premises costs and travel subsidies) should be regarded as a new service and outside the scope of the savings target.
  • Alongside maintenance of the Palace of Westminster, the House of Commons has commenced a major programme of refurbishment of a number of outbuildings (known as the Northern Estate). This work will generate significant impairment costs. These arise where the value of the building does not increase by as much as the value of the works carried out, and a proportion of the capital cost is charged to the resource account. In the medium term the costs arise primarily from the refurbishment of 1 Canon Row and Norman Shaw North. If included within the scope of the savings target, there is a risk that these accounting charges would squeeze the resources for services to Members and the public as the scale of essential repair work increases. The Northern Estate refurbishment programme is also expected to require additional decant space, but as yet the costs of this cannot be quantified.

12.  As a result of the transfers and out-of-scope items, the provisional target of an Estimate of £210 million in 2014/15 has been reduced to £202.6 million (excluding the cost of the one-off payment in respect of the pension transfer).

Table 1: Re-calibration of the savings target
2014/15

(£m)

2015/16

(£m)

2016/17

(£m)

2017/18

(£m)

Existing target at 2014/15 prices 210.0210.0 210.0210.0
Transfers (a)-20.7 -20.7-20.7 -20.7
Out-of-scope items (b) +13.3+18.0 +24.0+21.7
Inflation (c) +2.8+6.7 +10.7
Assumed resource budget for planning purposes 202.6210.1 220.0221.7
Transfer of pension liabilities to the Cabinet Office 450.0

Notes:  (a) £2.0m in respect of Members' stationery and postage and £18.7m in respect of staff pensions.

(b) £1.0m for Education Centre running costs and £12.3m to £23m for impairment costs related to the Palace of Westminster and Northern Estate refurbishment.

  (c) 1.5% in 2015/16 (when it is assumed that pay restraint will continue) and 2% thereafter.

Medium-term financial plan

13.  Appendix A to this report summarises the House's draft medium-term financial plan for the period 2014/15 to 2017/18. This indicates that projected resource spending will be £2 million below the recalibrated target for 2014/15, and £1 million below the assumed budget for 2015/16. However, additional savings in the order of £3-£4 million will be required in the two subsequent years if the assumed resource budget is to be adhered to.

Table 2: Medium Term Financial Plan 2014/15 to 2017/18: Resource
2014/15

£m

2015/16

£m

2016/17

£m

2017/18

£m

Assumed resource budget for planning purposes 202.6210.1 220.0221.7
Projected spending in Medium-Term Financial Plan (including planned savings) 200.6209.1 223.2225.6
Further savings required (+)/headroom available(-) (2.0)(1.0) 3.23.9

Catering

14.  In June 2013 the Commission agreed a new financial regime for catering services. A revised pricing mechanism allows factors such as gross profit margins and customer acceptability to be taken into account alongside benchmark prices from appropriate comparators. Prices will be reviewed, and changes implemented, at six-monthly intervals as part of the regular operation of the business, with Member committees being consulted on significant changes. This is supplemented by two further financial controls to be set annually: an overall target for gross profit margin (sales less cost of sales as a percentage of sales) to control kitchen costs; and a target for the net cost of catering to bear down on staff and other non-food costs.

15.  We propose to recommend to the Commission that for 2014/15 the target gross profit margin should be 66% and the net cost target should be £3.8 million excluding income generation activities. (It is anticipated that, after income generation activities, the subsidy will be £2.7million in 2014/15.)

Grant-aided bodies

16.  Six bodies receive their primary funding from the Administration Estimate: History of Parliament Trust, Commonwealth Parliamentary Association (UK Branch), Inter Parliamentary Union (British Group), British Irish Parliamentary Assembly, British American Parliamentary Group and Association of Former members of Parliament. In 2012/13 payments to these bodies by the House of Commons totalled £3.0m. For most of these bodies, grant levels were reduced by 10% in 2010 as part of the initial savings package, with the expectation that they would be frozen at this level until 2014/15.

17.  The bids received from CPA, IPU and BIPA all reflect a continuation of the current funding levels for the period to 2016/17. No bid had been received from the BAPG by the mid-September deadline. The History of Parliament Trust has submitted a bid for a substantial increase in funding in 2015/16 and 2016/17. The Association of Former Members has requested additional funding from 2014/15.

18.  We propose to recommend to the Commission that most grants should stay flat in 2014/15 in line with the current agreements and, unless there are exception circumstances, should thereafter be subject to the same financial remit as overall House spending: namely a maximum increase of 1.5% in 2015/16 and 2% thereafter. In the case of the Association of Former Members of Parliament, which receives a small grant of £6,000 per annum (unchanged since 2007), the Committee sees merit in increasing this to £12,000 in 2014/15, after which it should be subject to the same constraints.

Capital expenditure

19.  Capital expenditure relates primarily to investment in the Estate (the Palace of Westminster and other buildings on the Parliamentary Estate) and ICT. Most of the programmes are carried out on a bi-cameral basis, with costs shared, using agreed ratios, between the two Houses.

Table 3: Medium Term Financial Plan 2014/15 to 2017/18: Capital
2014/15

£m

2015/16

£m

2016/17

£m

2017/18

£m

Capital Estimate/plan 44.052.0 64.058.0

20.  Capital expenditure is planned to increase in the medium term due to a major building refurbishment programme, mechanical and engineering works, high priority works to improve fire safety and security, and investment in the ICT network.

Draft Estimate

21.  The Finance and Services Committee is proposing to recommend to the Commission in December 2013 a draft Estimate for 2014/15 with resource budget of £200.6 million and a capital budget of £44.0 million.


1   Improving Facilities for Educational Visitors to Parliament, HC 434 2006/07 Back


 
previous page contents next page


© Parliamentary copyright 2013
Prepared 23 October 2013