Progress in delivering the Thameslink programme - Public Accounts Committee Contents


1  Programme management

1.  On the basis of a Report by the Comptroller and Auditor General, we took evidence from the Department for Transport (the Department) and Network Rail on the progress in delivering the Thameslink programme and the risks to delivery that remain.[1]

2.  The Department became sponsor of the programme in July 2005. The programme involves:

·  Infrastructure work to improve tracks and stations including extending platforms, reconstructing Blackfriars, Farringdon and London Bridge stations and introducing new signalling technology. This work is expected to cost £3.55 billion (at 2006 prices) and is being done by Network Rail, funded by the Department.

·  Buying a fleet of new trains and two new maintenance depots, with an estimated capital cost of £1.6 billion, which the Department is financing through a Private Finance Initiative.

·  New franchise arrangements for running the passenger service on the Thameslink route.[2]

3.  Since the Department became sponsor of the programme it has made most progress in implementing the infrastructure project, with the first phase delivered under budget and on time in December 2011. The Department has, however, deferred its planned completion date, from 2015 to 2018. The procurement of new trains has taken over three years longer than expected and the Department has also revised its timetable and approach for letting the new franchise.[3]

4.  The first proposals to modernise the Thameslink route and increase capacity were made in 1989, and were then developed by a succession of rail industry sponsors in the 1990s and early 2000s. The Department told us that the early stages of the programme were dogged with protracted planning issues and a period of unstable funding from 1990-2000. Once all planning issues were resolved in 2006, the Department and Network Rail moved quickly to start main construction work in 2009.[4] However, it will still be some 30 years since the need to upgrade Thameslink was first recognised before passengers see the benefits. The Department told us that it had learnt lessons from Thameslink and that if projects like this are to move quickly in the future they require clear objectives, political consensus and a stable, predictable funding base as well as very strong project planning.[5]

5.  The Department's Thameslink team is under-resourced for a programme of this profile, size and complexity. The Department told us that the senior responsible owner (SRO) has a core team of just five people, down from eight prior to the Spending Review in 2010.[6] The C&AG's report shows that the team is small compared with teams in other Department's such as the Department of Energy and Climate Change for its smart meter and carbon capture and storage programmes. There have also been a number of other external assurance reviews which indicated that the core team is tight for resource.[7] The Department told us that it has many other people across the Department and the industry supporting the delivery of Thameslink and has spent £28 million on consultants since the start of the programme.[8] However, the Department accepted that the small core team raised a 'resilience issue' for the programme and we remain sceptical about whether the Department has the capacity to deliver the remainder of the programme by 2018.[9]

6.  The continuity of the SRO has been important to the success of the programme so far but the Department now plans to move the SRO from the Thameslink programme on to High Speed 2. The current post holder has been involved in the programme since 2005 and has been the SRO for the last five years, providing valuable continuity of leadership and much needed programme management skills and experience.[10] The Department sought to assure us that the management of the succession planning has been carefully thought through. The Department believes that the award of the train contract provides a sensible break point at which to change the SRO.[11] The Department told us that the next 'key inflection point' would be 2018 which, recognising the personal dimension to the decision, the Department believes would be a long time to ask an individual to work on the same project.[12]

7.  Given the amount that remains to be done to deliver the programme by 2018 we remain concerned about the impact on the Thameslink programme of the Department's decision to move the current SRO. We are worried that the development of individual skills has taken priority over making sure that projects get delivered on time with good value for money. We are also concerned that the current, highly experienced SRO's move to High Speed 2 highlights the shortage of project management skills in the Department to deliver its wider portfolio of projects. [13]


1   C&AG's Report, Progress in the Thameslink programme, Session 2013-14, HC 227, 5 June 2013 Back

2   C&AG's Report, paras 2-3 Back

3   C&AG's Report, Progress in the Thameslink programme, Session 2013-14, HC 227, 5 June 2013, para 3 Back

4   Q2 Back

5   Qq 1-2 Back

6   Qq 30-33 Back

7   Q 17; C&AG's Report, para 1.20  Back

8   Q34; Ev 21 Back

9   Q 109 Back

10   Qq 23-27 Back

11   Q 24, 27 Back

12   Q 27 Back

13   Qq 25, 27 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2013
Prepared 29 October 2013