2 Procurement Process and the European
Directives
7. Public sector procurement in the UK is governed
by the Public Contracts Regulations 2006. These implement the
EU Directives on public procurement intended to ensure equal and
non-discriminatory treatment of bidders and transparency in the
procurement process.[6]
For procurements with a value above specified thresholds,
the EU Directives require public bodies running a procurement
to advertise in the Official Journal of the EU, and to allow minimum
timescales for the completion of stages of the procurement.[7]
The Directives specify the main procurement procedures which shall
be used by public sector authorities. The most complex procedures
are the competitive dialogue and negotiated procedures, which
are generally most appropriate where the procuring authority has
not been able to determine precisely what it needs to procure.
8. The Cabinet Office has taken some steps to
improve the way in which Government bodies apply the procedures
specified under the Directives. In November 2011, the Minister
for the Cabinet Office, Francis Maude, announced a presumption
against the use of the competitive dialogue procurement procedure
on the grounds that "too often [...] public procurers have
relied on it as a means of engaging in dialogue with suppliers,
instead of engaging in thorough pre-market engagement".[8]
Under the terms of this presumption, departmental accounting officers
must formally approve the use of the competitive dialogue procedure,
before it can be used by civil servants.[9]
9. To improve procurement timescales, the Government
has also introduced training in "LEAN" sourcinga
streamlined procurement process which, as Andrew Coulcher, Director
of Business Solutions at the Chartered Institute of Purchasing
and Supply explained to us, involves "trying to do a lot
more in parallel, rather than have this highly strung-out serial
process of decision-making and building consensus".[10]
The Cabinet Office wrote in its evidence to us that "by November
2012, 626 staff had completed a 1 day programme and 400 had completed
a 3 day programme."[11]
It claimed further that this improvement in technical skills had
already begun to have an impact on the speed of procurements:
"Partly as a result [of training in the LEAN sourcing approach]
the average observed time for all but the most complex procurements
in 2012 fell from 180 to 153 working days".[12]
By applying LEAN processes and by having a presumption against
competitive dialogue, the Cabinet Office expect to achieve and
sustain a reduction in the average time taken to carry out procurements
by government departments and agencies to below 120 days.[13]
10. A number of witnesses to this inquiry welcomed
initiatives to train civil servants in the LEAN operating model.
The CBI said that initiatives such as LEAN sourcing were positive
and had some impact on the time taken to complete procurements.[14]
Peter Smith, a former president of the Chartered Institute of
Purchasing and Supply, similarly agreed that LEAN sourcing was
"a useful initiative" for improving technical skills.[15]
He thought that "it certainly covers elements of programme
and project management, and a certain amount around getting your
way through the EU regulations and things like that".[16]
Nonetheless, suppliers to Government continue to argue that doing
business with Government can and should be made much more efficient.
Jim Bligh, the CBI's Head of Public Services Reform said that:
"we still want to see a leaner, quicker process [...] Our
process is 50% longer than France or Germany's".[17]
11. We commend the Cabinet Office
for initiatives to make procurement practices across Government
more efficient but the progress is inconsistent and business argues
that processes are still slow and bureaucratic. It is intolerable
that UK public procurement still takes 50% longer than it does
in France or Germany; the Cabinet Office does not seem to know
why this is the case. It should reassess the impact of its
initiatives to streamline and modernise procurement practices;
identify what key factors in the procurement process must be addressed;
and report the results of this work in response to this recommendation.
12. The Chartered Institute of Purchasing and
Supply pointed out that part of the problem has been the tendency
of procurement staff in the UK public sector to focus too much
on process laid down by European Directives rather than outcomes:
The public sector has always been focussed on demonstrable
process and this has been underpinned by the European Procurement
Directives which have left UK procurement professionals process
driven and risk averse. Strict interpretation of the directives,
process focus and the use of unnecessary procedures has often
strangled innovation in the public sector and this has left suppliers
and procurement professionals alike frustrated and trapped by
prescription.[18]
13. Public procurements in the UK may also be
subject to the EU Remedies Directive which requires contracting
authorities to wait for 10 days after deciding who has won the
public contract before it is signed. [19]
This allows bidders time to examine the decision and decide whether
to initiate a review triggering the automatic suspension of the
procurement process. The Chartered Institute of Purchasing and
Supply wrote that "the combination of the standstill period
and the ability of rejected bidders to start a review procedure
during this period has made procurement teams more conscious of
the risk of challenge and therefore more anxious about following
the process precisely".[20]
14. Several witnesses agreed that European Directives
have not been sensibly applied in the UK. Social Enterprise UK
argued that:
Across the UK, many public bodies follow the full
EU procurement rules where it is not necessary to do so. Applying
the full set of EU rules adds complexity and cost for organisations
competing for contracts, which is both unnecessary and disadvantageous
to small organisations.[21]
Baroness Greengross's Transport Forum similarly noted
that: "No one would argue that there is anything wrong with
the spirit of EU procurement rules [...] In practice though, particularly
for SMEs, they can become rather bureaucratic and unwieldy".[22]
15. Tim Heywood, Director, Public Sector &
Procurement, Burges Salmon LLP, agreed that: "there are lots
of things wrong with the EU public procurement rules and yes,
the regime is quite complex".[23]
But he pointed out too that "if they did not exist we would
have to write them".[24]
The procurement consultant and former civil servant, Colin Cram,
agreed that the Directives were necessary and said that the problem
lay in how they had been applied. He also thought that blaming
EU Procurement Directives themselves is often a cover for incompetence:
"The EU procurement Directives have been responsible for
increased procurement professionalism in much of the public sector.
There is some room for improvement, but overall they do not inhibit
the application of best practice".[25]
16. We recognise that the regulation
of public procurement serves a valid purpose. However, we are
concerned that the EU Directives, and the fear of breaching them,
have driven a process-oriented, risk averse culture within the
Civil Service which has inhibited efficient procurement and lengthened
procurement times. The application of LEAN procurement training
does not seem to have fully addressed this problem. The Cabinet
Office should identify the factors which add to complexity and
delays in government procurement. The Cabinet Office must also
ensure that civil servants apply the minimum required by EU directives.
The EU should not be used as an excuse for over complex process
and delays which do not seem to affect other Member States.
17. In December 2011, the European Commission
set out proposals for reforming the EU Directives on procurement,
with a view to making them simpler and more flexible. The proposals
to revise the existing public procurement rules are currently
being negotiated through the EU Competitiveness Council and are
subject to debate in the European Parliament. A draft of the reform
proposals was approved by the European Parliament's Internal Market
and Consumer Affairs Committee in December 2012.[26]
The European Parliament is due to have its first reading of the
proposals in autumn 2013.[27]
18. Among the reforms advocated by the UK Government
in negotiations is an increase in the value thresholds above which
the EU Directives should apply. The CBI and others, such as Social
Enterprise UK, representing smaller businesses welcomed this.[28]
During our Brussels trip, we learned that many would like to see
EU procurement thresholds raised, but that the scope for changing
the EU thresholds is circumscribed by wider international agreementsin
particular the World Trade Organisation "plurilateral"
Agreement on Government Procurement (GPA). We were advised that
the Commission intends to defer any decision on this pending further
analysis.
19. The European Commission is also proposing
to implement the adoption of electronic procurement systems, or
"e-procurement" within a target two year timeframe.
In April 2012, the Commission published "a Strategy for E-Procurement"
noting that "contracting authorities and entities that have
already made the transition to e-procurement commonly report savings
between 5% and 20%".[29]
The Cabinet Office's response to the EU reform proposals supported
the wider take up of e-procurement, but raised concerns over the
achievability of the two year target.[30]
A number of MEPs expressed the view to us that an ambitious declaration
of intent was however needed in order to achieve progress.[31]
20. We welcome the principle that
the European Commission should act to streamline public procurement,
and we welcome in particular their plans to make procurement more
efficient through the use of e-procurement technology. The
Cabinet Office should publish its implementation plan for e-procurement
in the UK in its response to this recommendation to ensure the
public sector in the UK is able to meet the agreed timescale for
completing the transition to e-procurement.
21. The Chartered Institute of Purchasing and
Supply broadly welcomed the reforms to the main EU procurement
directives in its evidence to us. It pointed out however that
the European Commission has not proposed any reforms to the Remedies
Directive. Therefore, while reforms to EU Directives on procurement
may make processes simpler, the fear of a challenge under the
Remedies Directive, may continue to prompt unnecessarily strict
adherence to process.[32]
22. The EU Remedies Directive has
made civil servants risk averse and adhere too rigidly to process.
There is however value in a mechanism for challenging erroneous
procurement decisions. The Cabinet Office must monitor the
impact of the Remedies Directive and issue guidance on how its
negative effects can be mitigated. If this is not effective, the
Cabinet Office should insist that the Commission amend the Remedies
Directive to minimise its potential to inhibit effective public
procurement.
6 Directive 2004/18/EC of the European Parliament and
of the Council of 31 March 2004 on the coordination of procedures
for the award of public works contracts, public supply Contracts
and public service contracts; Directive 2004/17/EC of the European
Parliament and of the Council of 31 March 2004 coordinating the
procurement procedures of entities operating in the water, energy,
transport and postal services sectors Back
7
Cabinet Office, Procurement Policy Note - New Threshold Levels
for 2012 and changes in the use of the Accelerated Restricted
Procedure, Information Note 10/11, 12 December 2011 Back
8
Cabinet Office, Procurement Policy Note - Procurement Supporting
Growth: supporting material for Departments, Action Note 4/12,
9 May 2012 Back
9
Cabinet Office, Procurement Policy Note - Procurement Supporting
Growth: supporting material for Departments, Action Note 4/12,
9 May 2012 Back
10
Cabinet Office, Procurement Policy Note - Procurement Supporting
Growth: supporting material for Departments, Action Note 4/12,
9 May 2012, Q 351 Back
11
Ev w75 Back
12
Ev w75 Back
13
Cabinet Office, Procurement Policy Note - Procurement Supporting
Growth: supporting material for Departments, Action Note 4/12,
9 May 2012 Back
14
Qq 52-53 Back
15
Q 352 Back
16
Q 352 Back
17
Q 67 Back
18
Ev w20 Back
19 Directive
2007/66/EC of the European Parliament and of the Council of 11
December 2007 amending Council Directives 89/665/EEC and 92/13/EEC
with regard to improving the effectiveness of review procedures
concerning the award of public contracts. Back
20
Ev w20 Back
21
Ev w38 Back
22
Ev w45 Back
23
Q 334 Back
24
Q 334 Back
25
Ev w56 Back
26
Press Release, Towards greener and more responsible public
procurement, European Parliament, Internal Market and Consumer
Protection Committee 18 December 2012 Back
27
Press Release, Procurement package: New deal to ensure more
responsible public spending, European Parliament, Internal
Market and Consumer Protection Committee, 26 June 2013 Back
28
Q 109, Q 148 Back
29
European Commission, A strategy for e-procurement, April
2012 Back
30
Cabinet Office, Procurement Policy Note - Progress Update on
the Modernisation of the EU Procurement Rules, Information
Note 08/12, 24 August 2012 Back
31
See annex Back
32
Q 334 Back
|