1 MoD Resource Accounts 2013-14
1. Government Departments are expected, under Treasury
guidance, to publish annual reports and audited accounts at the
end of each financial year and before the Parliamentary summer
recess.[1] In addition
to the accounts, the Annual Report contains data on the department's
performance against the input and impact indicators in its business
plan and a description of its activities. The MoD laid its Annual
Report and Accounts for 2013-14 before Parliament on Thursday
27 November 2014.[2]
2. We took oral evidence from Jon Thompson, Permanent
Under-Secretary at the MoD, and Mr David Williams, Director General
Finance, on the MoD's Report and Accounts for 2013-14 on 7 January.
The MoD also provided us with supplementary written evidence in
response to further questions that we subsequently sent to them
in writing.
3. The MoD delayed publication of the 2013-14 accounts
to avoid qualification of the accounts on the grounds of an incorrect
balance being reported for assets under construction within the
Defence Infrastructure Organisation (DIO).[3]
In his Governance Statement in the Report and Accounts, Jon Thompson
reported that the National Audit Office (NAO) had identified concerns
around the "substantiation" of the £2.7 billion
balance previously disclosed by DIO as Assets Under Construction
(AuC). DIO had worked to resolve these concerns but this work
had not been completed in time for the original publication date
for the Report and Accounts. He reported that
The final outcome is an accounting write-off
of £267 million and adjustment to the Annual Accounts. This
write-off has been approved as appropriate by HM Treasury and
the adjustments have been subject to audit by the NAO.[4]
4. In our Report on the Armed Forces Covenant: Accommodation
we expressed concern about the management of the DIO, given the
major transformation that it was undergoing, including the reduction
of staff from 7,000 to 2,000, and the significant programmes it
was undertaking, including the return of the Army from Germany,
rebasing and the renegotiation of major contracts. The Government
reassured us in its response to that Report that the Transformation
Programme was subject to internal review and would be held properly
to account within MoD.[5]
5. In his Governance Statement on the Annual Report
and Accounts, Jon Thompson noted the MoD's Internal Audit conclusion
that it could only give limited assurance on the management of
strategic and operational risks, and that, given the transformation
that DIO was undergoing, "the reduction of resources has
led to a weakening of the control environment."[6]
However, he added that steps were being taken "to improve
the quality of the control environment." [7]
We questioned Jon Thompson about the problems in the DIO. He told
us that a NAO report on the DIO had raised significant concerns
about the management of the estate, including the operation of
76 different information systems to record land and property.
These systems had now been consolidated into one system which
went live in December 2014.[8]
6. We sought reassurance that the delays in publication
of the accounts would not be repeated and asked about future financial
and accounting challenges for the MoD. Jon Thompson told us that
the new challenges would arise from the next Strategic Defence
and Security Review in respect of its impact on the annual finances
of the MoD and the management of balances in terms of writing
off assets or shortening the lives of equipment.[9]
7. The MoD also provided us with further details
on future accounting challenges, including the sales of the Defence
Support Group (DSG), the Government Pipeline Storage System and
Marchwood military port, future estate rationalisation and the
hand-back of the German estate.[10]
The MoD also told us that the move to the new Defence Operating
Model, with greater authority, responsibility and accountability
for budget holders, had inevitably increased complexity and the
consequential risk of inconsistent identification and treatment
in the financial accounts.[11]
8. It is disappointing that, once again, the MoD
was some five months late in laying its Annual Report and Accounts
before Parliament. While it may have been appropriate to delay
the laying of the Accounts to ensure the balance sheet figure
for assets under construction was accurate, it was concerning
that this problem was identified by the National Audit Office
rather than by the MoD itself. We were also concerned that the
resolution of the problem required a write-off of £267 million,
some ten per cent of the total valuation of assets under construction.
However, we are satisfied that steps are being taken to reduce
the risk of such problems arising again.
9. In response to this Report, the MoD should
tell us what planning it is doing to ensure that it appropriately
manages the impact of the likely changes to asset balances, such
as write-offs of assets or shortening the effective operational
lives of equipment, that will arise from the forthcoming Strategic
Defence and Security Review. It should also tell how it intends
to manage the impact of the continuing management reform of Service
Commands.
Qualification of the Accounts
2013-14
10. The Comptroller and Auditor General (C&AG)
qualified his audit opinion on the Department's 2013-14 Resource
Accounts for the eighth successive year. The principal reason
for qualification is the accounting treatment of single source
contracts that may contain leases (under International Accounting
Standard 17), but a qualification was also recorded in respect
of the impairment (write-off) of the valuation of the estate in
Germany and inventory and non-current items.[12]
ACCOUNTING FOR CONTRACTS THAT MAY
CONTAIN LEASES
11. The C&AG again qualified the MoD Accounts
on the grounds that the MoD is likely to have omitted a material
value of leased assets and associated liabilities from its Statement
of Financial Position.[13]
The C&AG explained that the accounting requirements for lease
type arrangements were particularly relevant to the MoD as, by
necessity, it enters into a number of strategic arrangements with
particular contractors to procure specialist defence platforms
on a non-competitive basis. These arrangements could entail exclusive,
or near exclusive, use of industrial assets making it reasonable
to allow recovery of fixed costs other than through market rate
or unit cost pricing.[14]
The C&AG could not quantify the impact on the financial statements
because, as a result of its accounting policies, the MoD had not
maintained appropriate records or obtained the information to
do so.[15]
12. In 2013-14, the MoD agreed with HM Treasury not
to gather the further management information required to understand
the impact on these contracts as it would not represent value
for money. [16] In written
evidence, the MoD told us that it planned to undertake further
work with the support of a commercial accounting firm to "assess
the implications of determining whether an arrangement contains
a lease (IFRIC 4) and the subsequent accounting under IAS 17".[17]
13. The MoD Annual Report and Accounts 2013-14
have again been qualified on the balances for contracts likely
to contain a lease. The MoD should report to us on the results
of its latest review of contracts.
INVENTORY
14. For the 2013-14 Accounts, the C&AG was satisfied
that the MoD had provided sufficient evidence that the closing
balances of non-current assets, capital spares and inventory items
were correct but there was not sufficient evidence on the opening
balances or to which periods the impairment of £860 million
belongs.[18] The C&AG
said that challenges remained in respect of systems, inventory
checking procedures, inventories held off system, changes to the
business and embedding good practice. In particular, he drew attention
to the fact that investment in the new Base Inventory Warehouse
Management System (BIWMS) had been suspended while the MoD re-assessed
its user requirement. He also said that "the full implementation
of BIWMS was to be a significant step in enhancing the Department's
ability to efficiently manage and control its inventory".[19]
David Williams told us that the suspension of the BIWMS had been
reversed by the investment committee in early January.[20]
15. In response to our written questions, the MoD
told us that a detailed review of inventory items had resulted
in the £860 million impairment for events which had not been
properly accounted for in previous years and should be seen as
a one-off correction. Many of these events had resulted from the
outcome of the last Strategic Defence and Security Review.[21]
The MoD also told us:
A further detailed line item assessment will
be conducted following the outcome of the next SDSR to ensure
that decisions arising from the review are identified and reflected
within inventory valuations in a timely manner.[22]
16. We are pleased to see that the MoD is finally
managing to get to grips with the management and control of its
inventory and capital spares and welcome the PUS's assertion that
the MoD Accounts will no longer be qualified on this basis. We
also welcome the commitment by the PUS to a detailed item by item
impairment review following the outcome of the next Strategic
Defence and Security Review. The Comptroller and Auditor General
(C&AG) does, however, point to ongoing challenges in respect
of systems and embedding good practice. The MoD should tell us
how it will address these challenges.
Costing information for the next
Strategic Defence and Security Review
17. Given its problems with financial and management
information, we asked how well the MoD would be able to cost defence
outputs for the next Strategic Defence and Security Review. David
Williams explained that the strategic cost model was a high level
cost model which would answer two questions:
First, if you change the force structure in big
handfulsat the level of brigades or frigates or fast jet
force elementsroughly speaking, what does that do to the
cost of defence? Secondly, if you fix the defence budget at a
particular level, depending on which aspects of defence capability
you want to prioritise, what would an affordable force structure
look like? It is a high level tool to aid decision making. The
implementation of those decisions will then require a lot more
detailed financial modelling to allocate budgets and so on.[23]
18. The strategic cost model is a crucial tool
for preparation of the next Strategic Defence and Security Review.
Decisions about which capabilities the UK can afford have to be
taken on the basis of the most robust information and a clear
understanding of the cost drivers behind capabilities. The MoD
should provide us with a description of the strategic cost model,
its accuracy and any limitations that it has identified in its
utility.
1 HM Treasury DAO(GEN) 03/13 Back
2
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Back
3
Q 1 Back
4
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 97 Back
5
The Armed Forces Covenant in Action? Part 2: Accommodation Government Response
Third Special Report 2012-13 HC 578 Back
6
Ibid page 96 Back
7
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 97 Back
8
Q 3 Back
9
Q 11 Back
10
Ministry of Defence Memorandum: Response to follow-up questions Back
11
Ministry of Defence Memorandum: Response to follow-up questions Back
12
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 97 Back
13
The FReM requires preparers of accounts to comply with International
Accounting Standard (IAS) 17, Leases, to establish whether contracts
contain lease-type arrangements and whether those are, in substance,
either a finance or operating lease. A finance lease is a lease
that transfers substantially all the risks and rewards incidental
to ownership of an asset. An operating lease is any other type
of lease. The classification made by preparers of accounts could
have a significant impact on the financial statements.
If the contract is classified as a
finance lease then the value of assets used to deliver the service
would be recognised in the Statement of Financial Position alongside
a liability for the minimum lease payments due under the contract.
As an operating lease, no assets would be recognised and the payments
made under the lease would be reflected in the Statement of Comprehensive
Net Expenditure as spend is incurred. Back
14
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 102 Back
15
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 102 Back
16
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 102 Back
17
Ministry of Defence Memorandum: Response to follow-up questions Back
18
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 103 Back
19
Ministry of Defence Annual Report and Accounts 2013-14 HC 764
Certificate of the C&AG page 105 Back
20
Q 29 Back
21
Ministry of Defence Memorandum: Response to follow-up questions Back
22
Ministry of Defence Memorandum: Response to follow-up questions Back
23
Q 13 Back
|