Update on preparations for smart metering - Public Accounts Committee Contents


2  Managing the programme

10. The Department has overall responsibility for the Programme and has overseen its implementation since 2011. As the Programme moves towards mass roll-out the Department expects the transition to enduring industry-led governance to take place progressively over the next two years or so. Suppliers will be responsible for roll-out, and Ofgem will oversee suppliers' and other industry participants' compliance with their licence and Smart Energy Code obligations.[22]

11. The Department stated that it was ultimately accountable for the Programme and that it would devolve responsibility to Ofgem once the transition to industry-led governance was complete. However, the Department confirmed that there would be no changes to the accountability framework until it was confident that Programme risks had been sufficiently reduced.[23] Ofgem told us that it would deal with complaints relating to smart meters, where consumers were not satisfied with their supplier's response.[24]

12. The Department has mandated suppliers to take "all reasonable steps" to roll out smart meters to 100% of the market, and the central communications service provider is contracted to provide a network that will enable smart meters to be reached in 99.25% of premises. Some suppliers have asked the Department to reduce the requirement to, say, 80% roll-out because of the additional expense of achieving the last 20% of installations. The Department told us it was resisting these requests very strongly, particularly as it believed that these last 20% might include a disproportionate number of vulnerable consumers, and it does not want smart meters to be rolled out at the suppliers' convenience. It was for Ofgem to determine whether suppliers had taken all reasonable steps to achieve 100% roll-out. Ofgem has not provided guidance on what all reasonable steps will mean for suppliers, but told us it was very likely that it would do so in due course.[25]

13. Under the Programme, a home area network is required to allow in-home displays and other devices to connect to consumers' smart meters. However, the radio system currently in use for the home area network operates at a frequency of 2.4 GHz which is not suitable for up to 30% of premises, mainly high rise flats and buildings with thick walls. Suppliers are developing an alternative solution using a different radio frequency but this will still not work in 5% of premises.[26] Suppliers are working on a range of further solutions for these remaining premises, which may include wired connections, and these must be ready to allow roll-out to be completed by the end of 2020.[27]

14. We asked the Department whether it was necessary to have an in-home display in every home, and whether savings could be achieved by not providing an in-home display to households who wanted to use other devices such as smart phones or tablets to receive data from their smart meters. The Department told us that in-home displays cost £15 each and noted that all available evidence showed that in-home displays lead to additional energy savings of between 2% and 4%, bringing substantial cost savings for the consumer.[28] There is also a danger that the Government favours an existing technology when technologies are changing fast—leading to consumers paying for investment in a systems which is already out of date.

15. The Department told us that it had spent £19 million on running the Programme in 2013-14. Of this, around £14 million had been spent on external experts. In 2014-15, it expects to spend £12 million, of which around half will be spent on external experts. The Department explained that, during 2013-14, it ran four major procurement exercises for the data and communications services, so it had been crucial to have the technical and commercial expertise necessary to be able to engage effectively with commercial companies and safeguard consumers' financial interests. The Department told us its procurements had delivered a reduction of several hundred million pounds relative to the estimated cost of the central communication system in the impact assessment.[29]

16. We asked why the Department was relying so heavily on consultants to progress the Programme rather than developing its own in-house expertise, given it has a large portfolio of projects that require an ongoing commercial capability. The Department said it was building its in-house capability, but that the Programme required a lot of expertise over a short timeframe, and it would not be practical to carry this expertise within the Department in the longer term.[30]

17. We also asked whether the Department had examined the approach taken by the Ministry of Defence of setting up a new organisational structure that allowed permanent civil service staff to be employed and paid outside traditional pay structures. The Department said it had not looked at the Ministry of Defence's initiative, but it believed that a degree of pay flexibility was necessary to enable the Department to bring in the commercial expertise it needed, because not doing so would mean reliance on consultants that would cost more, and whose knowledge and experience would be lost to the Department once their work is completed.[31]

18. The Major Projects Authority reviewed the Programme in 2011, 2012, and 2013. The Department told us that it had not published the MPA's assessments as they are designed to facilitate a frank discussion of the Programme, to review Programme management and processes, and to provide confidential advice to the Senior Responsible Officer on the delivery of the Programme. The Department maintained that it had followed Cabinet Office advice and was constrained by Cabinet Office rules from placing these reports in the public domain as the reviews were conducted on a confidential basis, and expressed the view that publishing the reports would remove the confidentiality of the process and inhibit frank contributions to the review.[32]



22   C&AG's report, paras 6 & 7 Back

23   Q 147 Back

24   Qq 148 & 152 Back

25   Qq 114 - 116 Back

26   Q 94 Back

27   Q 94 Back

28   Q 89 Back

29   Qq 33- 157 Back

30   Qq 158 - 161  Back

31   Q 163 Back

32   Q 166 Back


 
previous page contents next page


© Parliamentary copyright 2014
Prepared 10 September 2014