Major Projects Report 2014 and the Equipment Plan 2014 to 2024, and reforming defence acquisition - Public Accounts Contents


1  Risks to delivering the Equipment Plan to time and cost

1. On the basis of two reports by the Comptroller and Auditor General, we took evidence from the Ministry of Defence (the Department) on progress in delivering major projects, on the affordability of its Equipment Plan and on the Department's plan to ensure Defence Equipment and Support (DE&S) has the skills to deliver military equipment to budget and time. We also looked at the Department's progress implementing the recommendations from our earlier report on Army 2020.[1]

2. Since 2012, the Department has published an annual Statement on the affordability of its 10-year plan to deliver and support the equipment that the Armed Forces require to meet the objectives set out in the National Security Strategy. This year's statement for the 10-year period from 2014 to 2024 was published in January 2015 and covered a budget of some £163 billion, made up of £69 billion for procurement, £81 billion for equipment support costs, a £4.6 billion central contingency reserve and an unallocated budget of £9.2 billion that the Department has not yet committed to specific programmes. The Plan is £1.4 billion less than last year's Plan for the period 2013 to 2023. Each year, the Department also presents a major projects report to Parliament with data on cost, time and performance of the largest defence projects where the Department has taken the decision to invest. This year's report was laid in Parliament in February 2015.[2]

3. For the first time, the National Audit Office has reported on the robustness of the assumptions underlying the Department's annual Statement on the affordability of the Equipment Plan, together with its observations on the underlying in-year variations to major project cost, time and performance in 2014, in a single report to Parliament. The NAO selected 17 equipment projects as the basis for reporting project performance and to support its review of the affordability position. This sample had been selected based primarily on value, but also to reflect the level of project maturity and type of equipment.[3]

4. The majority of the Department's budget is tied-up on equipment, personnel and infrastructure. The Department told us that it was assuming funding for its Equipment Plan would increase by 1% above inflation. This increase, combined with a reduction in the remainder of the defence budget, would increase the proportion of its overall budget spent on equipment. The Department is currently spending 44% of its budget on equipment, above the 41% planned with the Treasury. The Department told us that it was anticipating spending on equipment to rise to 47% of its budget by 2019-20.[4]

5. The Department noted that its working assumption was that forthcoming Comprehensive Spending and Strategic Defence and Security Reviews would be developed in concert to provide a coherent overall strategy to meet the UK's defence requirements from 2016-17. The Department told us that if funding was cut, or the anticipated 1% Equipment Plan increase did not materialise, it would expect the Government's defence strategy to be considered to ensure that the balance between strategy and resources was maintained. That might mean that the budgets for equipment, personnel and infrastructure would be rebalanced.[5]

6. The Department's current portfolio of major projects is relatively mature and stable, where the risk of cost growth is less. There had only been one new significant project approval during 2013-14 and no new procurements had been introduced. However, the Department's semi-independent Cost Assurance and Analysis Service had reviewed cost forecasts in the Equipment Plan and it had concluded that procurement costs were understated by £3.2 billion and equipment support costs by £2 billion. The latter was based on a review of 28% of total equipment support costs and therefore the understatement could grow as more support costs were reviewed.[6]

7. The Department accepted that the cost of its 10-year Equipment Plan was potentially understated.[7] However, the Department told us that it was more confident than last year that its contingency budget of £4.6 billion would cover the risk of project teams understating costs and a planned programme of activity would be undertaken over the next 12 months to identify better the risks of cost growth in equipment support projects.[8] The Department accepted that there continued to be inconsistencies in the way DE&S project teams were treating inflation, Value Added Tax (VAT), and risk. The Department told us that it allowed for risks at different levels. It wanted some risks to be held by the project team, which were risks that they could manage. It wanted some held at the 'portfolio level' such as foreign exchange risks and some at the departmental level for overall strategic risk against programmes such as the nuclear programme.[9] DE&S had recently let contracts to the private sector for business support. These managed service providers were expected to improve financial forecasting.[10]

8. The Department noted that addressing issues with how VAT was accounted for was complex. When setting budgets project teams took a view on how VAT legislation would apply to the project. If HMRC interpreted the legislation differently than expected, the Department could face unexpected project cost growth. The Department's primary concern was volatility in project costs created by uncertainty in the level of VAT payments. That could have an impact on the affordability of the programme and require decisions on capability at short notice.[11]

9. In addition to the potential £5.2 billion understatement of project costs, the Department was assuming that DE&S can deliver a further £6 billion of savings already taken from existing budgets. The Department told us that it had agreed with commands, and locked into project budgets, £2.3 billion of the required £4.1 billion savings on equipment support. It was working on a further £1 billion, leaving £800 million of savings still to be identified. The savings to be found on procurement projects from complex weapons and submarine procurement were proving harder to identify and the Department had only so far found £400 million of the £2 billion target. The Department told us that it was more confident of delivering the submarine savings. There were risks to finding £1 billion of anticipated savings from complex weapons, but the Department was confident that it could find these elsewhere.[12]

10. DE&S's failure to deliver projects successfully to cost and time may result in the £8 billion of unallocated budget being used to fund cost growth on existing projects. The Department viewed this unallocated budget as essential to the achieving its ambitions for transforming defence. It expected to reassess these ambitions if cost growth was drawing on this budget and reducing military capability.[13]


1   C&AG's Report, Major Projects Report 2014 and the Equipment Plan 2014 to 2024, Session 2014-15, HC 941-I, 13 January 2015; C&AG's Report, Reforming defence acquisition, Session 2014-15, HC 946, 26 February 2015; The Committee of Public Accounts, Army 2020, Eleventh Report of Session 2014-15, HC 104, 5 September 2014 Back

2   C&AG's Report, Major Projects Report 2014 and the Equipment Plan 2014 to 2024, paras 1.1, 2 Back

3   C&AG's Report, Major Projects Report 2014 and the Equipment Plan 2014 to 2024, para 4 Back

4   Qq 3-5  Back

5   Qq 2, 6-11 Back

6   C&AG's Report, Major Projects Report 2014 and the Equipment Plan 2014 to 2024, para 13 Back

7   Qq 12-16 Back

8   Qq 14, 23 Back

9   Q 49 Back

10   Qq 32-33, 49; C&AG's Report Major Projects Report 2014 and the Equipment Plan 2014 to 2024, paras 2.14-2.20 Back

11   Qq 36-48; C&AG's Report Major Projects Report 2014 and the Equipment Plan 2014 to 2024, para 2.16 Back

12   Q 16 Back

13   Qq 51, 52 Back


 
previous page contents next page


© Parliamentary copyright 2015
Prepared 20 March 2015